HomeMy WebLinkAboutCHANGE ORDER - BID - 7274 RESTROOM ADDITION & RENOVATION AT ROLLAND MOORE RACQUET FACILITYPROJECT TITLE:
PROJECT NUMBER:
CHANGE ORDER FORM
Rolland Moore tennis restroom renovation
Bid # 7274 PO # 9116144
CONTRACTOR: Classic Contractors, Inc
CHANGE ORDER NUMBER: 1
In preparing change orders show in order as separate numbered paragraphs the following
1. Reason for change. 2. Description of change.
3. Change in contract cost. 4. Change in contract time.
Reason for Change: Bring urinal area up to code
Description of Change: Remove existing partition, replace w/steel partition and relocate urinal
Change in Contract Cost: $1,769.00
Change in Contract Time: none
ORIGINAL CONTRACT COST $86,677.00
TOTAL APPROVED CHANGE ORDERS $0.00
TOTAL PENDING CHANGE ORDERS $0.00
TOTAL THIS CHANGE ORDER $1,769.00
TOTAL % OF THIS CHANGE ORDER 2.04%
TOTAL C.O. % OF ORIGINAL CONTRACT 2.04%
ADJUSTED CONTRACT COST $88,446.00
(Assuming all change orders approved)
ACCEPTED BY: Gy� DATE:
(�or's Representative)
rr%\ f +i _
SUBMITTED BYA - e 1, �� ��'����/G (i� DATE:
(Project Manager)
REVIEWED BY:
DATE:
(Engineer,
APPROVED BY:
' i
DATE: I /)I !
(Department Head)
cc: Accounting
Contractor
Purchasing
Project File
-