HomeMy WebLinkAboutCHANGE ORDER - BID - 7212 WEST MYRTLE ALLEY - DOWNTOWN ALLEY ENHANCEMENTSCHANGE ORDER NO. 3
PROJECT TITLE:
Downtown Alley Enhancements • West Myrtle Alley
CONTRACTOR:
Technology Constructors, Inc.
PROJECT NUMBER:
7212
PURCHASE ORDER NO:
9112350
DESCRIPTION:
(See below and attached)
1. Reason for change
The reason for this contract change includes modifications to contact value only. This change order
accommodates both additions and deletions to the constrution contract. It reconciles the final contract
amount.
2. Description of Change:
The description of the contract changes can be found in the attached field orders which are incorporated
into this change order by reference.
Field orders included in this change order are: Field Order No. 22, 23, 24, 27
The field orders are summarized on the attached pending issues log.
3. Change in Contract Cost: ($8,069.19)
4. Change in Contract Time: +0 calendar days for intermediate milestone
+D calendar days for substantial completion
+0 calendar days for final completion
TOTAL APPROVED CHANGE ORDERS
$48,933.17
TOTAL PENDING CHANGE ORDERS
$0.00
TOTAL THIS CHANGE ORDER
$ (8,069.19)
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.
-0.90%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S
4.54%
ADJUSTED CONTRACT COST
940,736.98
(Assuming all change orders approved)
ACCEPTED BY DATE: c 11,11-61
Contractor's Representa lve
ACCEPTED BY: DATE: ZC>-//
DDA Project Manager
REVIEWED BY: !li S DATE:
Engineer ✓ /
�,,l�APPROVED BY: i DATE:
City Project Manager
APPROVED BY: DATE
Purchasing Agent over $60,000
cc: City Clark Architect
Contractor Engineer 1 uj, 35
Project File Purchasing '1
'qoo16/0/o.�3so�-0
ditesco
Project & Construction Services
Project: Downtown Alley Enhancements
West Myrtle Alley
Date: September 1, 2011
Contractor: Technology Constructors, Inc.
5636 Kendall Court, Unit A
Arvada, CO 80002
Field Order
Project No.: 7212
Field Order #: 24
Contract Date: April 26, 2011
Contract Value: $899,873.00
Purpose: This Field Order directs the Contractor to make a change in work as defined in the Contract
Documents. The Contractor shall provideal fixed cost for the work, add this work to the Pending Issues
Log for the project and gain approval from the Owner prior to proceeding with the work. Approval will
be granted by full execution of this Field Order. By proceeding with the work, the Contractor
acknowledges that a change in the Contract Amount or Time is not warranted.
Description:
This Field Order addresses a request from the Contractor to be compensated for addition of
topsoil and mulch throughout the planting beds on the West Myrtle Alley project. Here, the
Contractor was directed to install additional topsoil after the beds were graded and prepared
due to City of Fort Collins Forestry Dept personnel concerns surrounding the beds being too
low for proper tree and plant establishment. After this, additional time to prepare the mulch,
mound and deliver additional mulch was incurred by the Contractor.
I
The total cost for this change is: $7941.54
Attachments: TCI pricing
By:
Engineer
Date: Sept 29 2011 (approved
Copy to: Contractor ❑x Owner ❑O
Engineer O File ❑O
TECH N(DLC)GV
CONSTPUCTOPS
INCCX2PC 2ATED
CHANGE ORDER REQUEST
September 29, 2011
Mr. Keith Meyer
Ditesco Project & Construction Services
1315 Oakridge Dr., Suite #120
Ft. Collins, CO 80525
RE: Project No. 7212; West Myrtle Alley Downtown Alley Enhancements
FO #24 — Topsoil and Mulch - Breakdown
Dear Mr. Meyer:
Listed below is our breakdown of the costs associated to adding topsoil and mulch.
Golden Landscaping Costs: Topsoil
Labor: Landscape/Irrigation Lead 2 hrs @ $33.00/hr = $ 66.00
Landscape/Irrigation Technician 3 hrs @ $22.000/hr = $ 66.00
Materials: Topsoil/Compost 1 8 cy @ $15.00/cy = $120.00
Topsoil/Compost (Delivery) 1 is @ $68.00/ls = 68.00
Sub -Total $320.00
15 % Markup 48.00
Golden Landscaping Total $368.00
5% TCI Markup 18.40
Total $386.40
Golden Landscaping Costs: Mulch
Labor: Landscape/Irrigation Lead
3 hrs @ $33.00/hr
= $ 99.00
Landscape/Irrigation Technician
2.25 hrs@ $22.000/hr
= $ 49.50
Equipment: Skid Loader
3 hrs @ $46.50/hr
= $139.50
Trucking
2 hrs @ $25.00/hr
= 50.00
Sub -Total
$338.00
15 % Markup
$ 50.70
Golden Landscaping Total
$388.70
5% TCI Markup
19.44
Total $408.14
Please review and let me know of any discrepancies.
Grand total = $794.54
Since
Edward R. Callejo
Project Manager/Estimator
5636 Kendall Court, Unit A, Arvada, CO 80002, (303) 431-2961, (303) 431-0091 fax
ditesco
Project & Construction Services
Project: Downtown Alley Enhancements
West Myrtle Alley
Date: September 29, 2011
Contractor: Technology Constructors, Inc.
5636 Kendall Court, Unit A
Arvada, CO 80002
Field Order
Project No.: 7212
Field Order #: 27
Contract Date: April 26, 2011
Contract Value: $899,873.00
Purpose: This Field Order directs the Contractor to make a change in work as defined in the Contract
Documents. The Contractor shall provide a fixed cost for the work, add this work to the Pending Issues
Log for the project and gain approval from the Owner prior to proceeding with the work. Approval will
be granted by full execution of this Field Order. By proceeding with the work, the Contractor
acknowledges that a change in the Contract Amount or Time is not warranted.
Description:
This Field Order addresses a request from the Contractor to be compensated for costs
associated with preparing additional concrete stain samples through Colorado Hardscapes.
Here, the initial staining subcontractor did not provide acceptable mock ups which were
rejected by the Owner. The Owner then requested selection of a second subcontractor to
perform concrete stain mock ups. This work was completed yet the staining work itself was
deleted from the overall contract due to cost.
The total cost for this change is: $294.25
Attachments: TCI pricing
By:
Engineer
Date: Sept 29, 2011(approved)
Copy to: Contractor O Owner O
Engineer 191 File O
TECH NC3LOGy
CC3NSTPUCTC)QS
INCC> 2PCX2ATED
FIELD ORDER REQUEST
September 28, 2011
Mr. Keith Meyer
Ditesco Project & Construction Services
1315 Oakridge Dr., Suite #120
Ft. Collins, CO 80525
RE: Project No. 7212; West Myrtle Alley Downtown Alley Enhancements
FO #27 — Staining Samples
Dear Mr. Meyer:
Pursuant to the City's request to eliminate the lithochrome staining for the concrete benches, we
hereby submit a request to be compensated for the test sample as noted below.
Sample (Colo. Hardscape) 1 Is @ $285.00/ls = $285.00
5% Markup $ 14.25
Total $299.25
Please review and let me know your decision.
Sincerely /�
Edward R. Callejo
Project Manager/Estimator
Attachment
5636 Kendall Court, Unit A, Arvada, CO 80002, (303) 431-2961, (303) 431-0091 fax
=a
8085 E. Harvard Ave.
Denver, CO 80231
303-750-8200
Fax:303-750-8886
www.coloradohardscapes.com
SEP 2 0 2011
WORK AUTHORIZATION #
Job Nam
Job Number: Date: 9 /6 11
Tc�� nd JvSY Csh�,
..ro,eq
Job Address:
Original Proposal M
J
Price
Description of work:
p,-'Cf
A s�
4 yc-S t
`�
SGp'j btc-s�tOMNI
Total work authorized:
$ a
The above prices, specifications and conditions are satisfactory and hereby accepted. You are authorized to do the work
as specified. Payment due upon completion of this work. No retention to be held. 1'h % per month on accounts past due.
Authorization: Owner/Contractor
LIM
Date
Colorado Hardscapes, Inc.
Date: q //16///
While: Off ice Copy Yellow: supervisor Copy Pink: Customer Copy
ditesco
Project and Construction Services
CHANGE ORDER NO. 3
SUPPORTING DOCUMENTATION
Project: Downtown Alley Enhancements - West Myrtle Alley
Project No. 7212
Date: October 18, 2011
Description of Change:
1315 Oakridge Drive - Suite 120
Fort Collins, CO 80525
970.204.1673 fax
ditescoservices.com
This change order reconciles the Downtown Alley Enhancement -West Myrtle Alley construction contract (#7212)
as of October 18, 2011. This reconciliation is the final for the project. The work is complete and fully accepted.
Change in Contract Value:
The contract value is being decreased by $8,069.19. Please see attached pending issues log summary and field
orders.
Change in Contract Time:
The contract time is not changing.
Page 1 of 1
not including field order attachments
Pending Issues Log
ditesco
Project and Construction Services
Project: DDA Downtown Alley Enhancements JWest Myrtle Alley)
Contractor: TO
Project No. #7212
Date: October 18, 2011
Ref. No.
SSpecn
Reference
Item Description
Date Requested
Amount
Status
1
Div 5
FO #1
Trash enclosure changes throughout
5/172011
IS, 884 1,
priced and accepted
2
Div 5
FO #2
Planter basket fabdwbon and installation
5232011
$41,08069
priced and accepted
3
Div 5
FO#3
Specht fence changes and bollard installation
6/132011
$6,650 30
priced and accepted
4
Div 3
FO #4
Seal mall subbase and reinforcing
61132011
$406 00
priced and accepted
5
FO #5
Light Pole Relocation Change north side alley)
awol l
$2,033.00
priced and accepted
6
FOR 08
Contract time extension request - meather days
6/172011
$0 00
partal acceptance see response
7
FOR #7
Contract time extenbon request - Xcel Energy delay
61172011
$000
not accepted
8
FOR #8
Removal of excess dirt - Xcel Enerify
6/172011
$350.00
priced and accepted
9
FOR #9
Notice of found ublit - Rader Sanitary Semer
6117/2011
$0 00
111 not a field order
10
FOR #10
Atldrtronal suNturng to establish control
6/172011
$0 00
$1 450 00- not accepted
11
Div 3
FO #11
Add concrete pole bases to light pole foundations
620/2011
$734 25
pnced and accepted
12
Div 2
FO #12
Raider Sevver Cleanout Installation - Time and Material
610/2011
S455.74
pniced and accepted
13
FO #13
Additional specialty signs
7/t12011
$864 13
priced and accepted
14
Div 2
FO #14
Delete alley name concretesigns
82/2011
aced and accepted
15
ON 2
FO #15
Additional asphalt patching
82/2011
S1 894 80
priced and accepted
16
Div 2
FO #16
Delete sewer caps at main - south afley to Laurel
Sipriced
and accepted
17
Div 5
FO #17
Add Sign Posts
Sf9/2011
$2.338.78
priced and accepted
18
Div 16
FO #18
LCC control changes to photo cell and protection cage
81112011
597500
priced and accepted
19
Div 2
FO #19
Tree changes remove oak
SA92011
and accepted
20
Div 3
FO 020
Add drain pans at all dovvnspDut locations
8/182011
S2 231 59
priced and accepted
21
Dry 5
FO #21
Add guard posts to vanous locations on the ste
8 232011
$1 40000
priced antl accepted
22
Div 2
FO 022
Delete Staining from seat walls
8292011
and accepted
23
Div 2
FO 023
Relowle1hansplant trees
9112011
$937 02
priced and accepted
24
Div 2
FO 924
Add topsoil and mulch
9/12011
$794 54
priced and accepted
25
Div 2
FORM
Asphalt Patching
9/162011
$0 00
$9,78Z68- not accepted
26
FOR #25
Add weather days
9/162011
00
addressed in change order #2
27
Div 2
FO #27
Staining sam tes
9282011
$299.25
priced and accepted
28
Div 5
FOR #28
Reconstruct norm trash enclosure
929/2011
$0.00
$4.102.IS -not accepted
Change Order#1 Subtotal
Change Order #2 Subtotal
Change Order #3 Subtotal
Job Totals $40,863.98
$45 792 88
$3,140 29
Total Ori final Contract Amount 99,67300
Final Conbacl Amount $940,736,98
IFervang Issues as a %of contract Amount 4.5,11%
= Change Order #1 Items
= Change Order #2 Items
= Change Order #3 Items
dmilesco
Project & Construction Services
Project: Downtown Alley Enhancements
West Myrtle Alley
Date: September 29, 2011
Contractor: Technology Constructors. Inc.
5636 Kendall Court, Unit A
Arvada, CO 80002
Field Order
Project No.: 7212
Field Order #: 22
Contract Date: April 26, 2011
Contract Value: $899,873.00
Purpose: This Field Order directs the Contractor to make a change in work as defined in the Contract
Documents. The Contractor shall provide a fixed cost for the work, add this work to the Pending Issues
Log for the project and gain approval from the Owner prior to proceeding with the work. Approval will
be granted by full execution of this Field Order. By proceeding with the work, the Contractor
acknowledges that a change in the Contract Amount or Time is not warranted.
Description:
This Field Order directs a contract change thereby deleting the entire concrete seat wall
staining work from the West Myrtle Alley contract. This includes all staining shown in the
contract drawings on sheet LS505
The total credit for this change is:-$10,100.00
Attachments: TCI subcontractor pricing
By:
Engineer
OJk� NC 10?0
C0/1 �t7� dgo q /Ao *- l c
ate- �ut4_4b
Date: Sept 29, 2011 (approved)
Copy to: Contractor ❑x Owner ❑x
Engineer ❑x File ❑x
TECHNOLOGY
C0N5TRlJCT0925
INC0RP0F2ATED
FIELD ORDER REQUEST
September 9, 2011
Mr. Keith Meyer
Ditesco Project & Construction Services
1315 Oakridge Dr., Suite #120
Ft. Collins, CO 80525
RE: Project No. 7212; West Myrtle Alley Downtown Alley Enhancements
FO 422 — Staining Concrete Benches
Dear Mr. Meyer:
Pursuant to discussions regarding the use of a new subcontractor to color stain the concrete
benches, we hereby submit to you the following price.
1) Add: Colorado Hardscapes 1 is @ , _ , Z) 0
2) Deduct: Decorative Coatings & Concrete 1 Is @ <$10,100.00> = <$10,100:00>
10% Markup $ 1,752.10
Total $19,273.10
Attached are the proposals from Colorado Hardscapes and Decorative Coatings and Concrete.
Please review and let me know your decision.
Sincerely,
Edward R. Callejo
Project Manager/Estimator
Attachments
5636 Kendall Court, Unit A, Arvada, CO 80002, (303) 431-2961, (303) 431-0091 fax
RADO
HWtnsc. PES
Proposal Submitted To:
Technology Constructors
Attn: Ed Callejo
5636 Kendall Court - Unit A
Arvada, CO 80002-2700
Salesperson: Keith Craig
Section A: Scope of Work:
1
8085 East Harvard Avenue
Denver, CO 80231
Ph: (303)750-8200
Fax:(303)750-8W6
rnone: 303-431-2961
Fax: 303-431-0091
Job Name: Myrtle Alley Project
Job Location: Ft. Collins
Architect:
Colorado Hardscapes hereby proposes to furnish labor, materials and equipment to install:
Sandblasting and staining of seat walls: (8 ea)
➢ Provide reasonable protection of surrounding areas
➢ Supply blast templates for the designs per the plans
➢ Sandblast the designs into the concrete seat walls
➢ Apply stain system
Proposal #: 11-10226
Note: The sand from the blasting will blow around the site. CHI will do reasonable
cleaning within the area of the blasting, but excludes excessive cleanup .
of sand.
Please Note: A deposit of 25 % is required before work can begin. If work is postponed
by the client once started, a remobil/iation fee of $2,000 will be charged for each
occurrence.
Section B: Exclusions:
Excessive cleaning or containment of sand; Permits; OT work; Davis Bacon Wages; performance or
payment bonds (available at 2%), more than 1 mobilization.
Proposal Total
Page 1 of 3
Date: 9/8/2011
Price
1.00
Quote;
#96`53
:wp3:MAveCmi
C91m:,
j
k:w3.deoa•
^u:
1 u. er -neat r,
FROM: DCandC, 1.703 5 Moline Court, Aurora, CO 80012
DATE: MARCH 30, 2011
TO: 1703 5 Moline Court
Aurora, CO 80012
QUOTE GOOD THROUGH: AUGUST 30, 2011
Off. 303 745-1172
Cell: 303 359-4748
To
Technology ConstructorsCorporation
Project: City of Ft Collins
Att: Ed Calejo
Myrtle Alley Downtown Alley Enhancemenu
5636 KENDALL CT., UNIT A
Bid No: 7212
ARVADA, CO 80002
P: (303) 431-2961
F: (303) 431-0091
Mike Fifrraro
Due Upon Canpledws
Concrete Seatwall Al = 3 ea - Lithochrome
67 Chestain Area Only = 29 s.f/ea $'600-00
m
Concrete Seatwall A2 = 1 ea - Lithochrome 1
29 Chemstain Area Only = 29 S.f. ( I 1 $1,200.00
Concrete Seatwall Bt = 2 ea - Lithochrome
76 Chemstain Area Only = 38 s.f./ea I 1
$2,400.00 s
Concrete Seatwall 82 = 1 ea - Lithochrome
67 Chemstain Area Only = 67 s.f. I I
$1,20D.00
was
Concrete Seatwatl 83 = 1 ea - Lithochrome
29 Chemstain Area Only - 29 s.f. s+,20o.ao
Sample I $300 00
Generator
SUCrorAL 1 $10,400.00
SALESTAI
TOTAL $10,400-00
Quotation pe areel W
Dlmldmw: Thh h . sp,a,adon an Iha koeds named, w bject to the ewrditbw noted Maw. I
In the cam of wld stained ewveoe:
Dfnd.imer. Celar yxlaewe: DCandC, LLC Mll,ae on, p,ofdswor j W, W"t m neM every As sn oon of the apeemenl of our contract. OCi , LLC cannot Ise repwmble for
cntw ean.tions In tha remo rote. oCwnx, l3C is not responsible /or ta,ryeein,, that ow, mew on tin side WsUo Mule es, Wert H Mnr pMwxd w once it Is canpemd. non
cwdnct W, maim the we, wr, We tnn rAeted Wssr , uC remonsfisIe for AM damage that may wcw Mlle wort 4 W M done and woe the.mh is eonpeted. lM po)eet MAl a
cwMderM co nplete, wee the General Ccwis etw w Owner isas impeetsd the Mohes.
DCW, C, LLC MR enly_Lryel e rewb(e for maldnr m the entity (cwrgen tW W') we are MM swore of on' ion. It wM ha Use respemiblllty of that wdity
tarttrarbr w owner'. reprewnanw•1 m pn,,, the fnlormal en In ods dixlainer is, tha. At dose soUorrsed to m.ke deign 4teisiom on this gaiwt. This ducldmw
idmnile WM ,At can cane irreyWanties in ose floor enter. p:ofAe and finish, Here "I be t'ntra chwles If Use contractor Is asked N repair irrq,latides in tie now, that wete
dilesco
Project & Construction Services
Project: Downtown Alley Enhancements
West Myrtle Alley
Date: September 1, 2011
Contractor: Technology Constructors, Inc.
5636 Kendall Court, Unit A
Arvada, CO 80002
Field Order
Project No.: 7212
Field Order #: 23
Contract Date: April 26, 2011
Contract Value: $899,873.00
Purpose: This Field Order directs the Contractor to make a change in work as defined in the Contract
Documents. The Contractor shall provide a fixed cost for the work, add this work to the Pending Issues
Log for the project and gain approval from the Owner prior to proceeding with the work. Approval will
be granted by full execution of this Field Order. By proceeding with the work, the Contractor
acknowledges that a change in the Contract Amount or Time is not warranted.
Description:
This Field Order addresses a request from the Contractor to be compensated for multiple tree
relocation efforts during the final landscape planting phase of the project. Here, TCI and
Golden Landscaping were directed through Field Order 19 to change the location and type of
trees to be planted. After this, field direction from both the Landscape Architect and City of
Fort Collins Forestry Dept. caused further relocation of trees after two walk through sessions
were completed.
The total cost for this change is: $937.02
Attachments: TCI pricing;
Date: Sept 29, 2011 (approved
Engineer
-Copy to: Contractor ❑x Owner O
Engineer 21 File ❑x
TECH NCQLCX5V
CC3NSTQUCTC)QS
INCC 2PC P2ATED
CHANGE ORDER REQUEST
September 29, 2011
Mr. Keith Meycr
Ditesco Project & Construction Services
1315 Oakridge Dr., Suite #120
Ft. Collins, CO 80525
RE: Project No. 7212; West Myrtle Alley Downtown Alley Enhancements
FO #23 — Transplanting Trees Breakdown
Dear Mr. Meyer:
Listed below is our breakdown of the costs associated to relocating trees after they had already bei
installed.
Golden Landscaping Costs:
Labor: Landscape/Irrigation Lead
Landscape/Irrigation Technician
Equipment: Skid Loader
Warranty ($12.50/tree relocated x 12)
Please review and let me know of any 'discrepancies.
Sincerely,
Edward R. Callejo
Project Manager/Estimator
8 hrs @ $33.00/hr
= $264.00
8 hrs @ $22.00/hr
= $176.00
4 hrs @ $46.50/hr
= $186.00
1Is @ $150.00/Is
= $150.00
Sub -Total
$776.00
15 % Markup
$116.40
Golden Landscaping Total
$892.40
5% TCI Markup
$ 44.62
Total $937.02
5636 Kendall Court, Unit A, Arvada, CO 80002, (303) 431-2961, (303) 431-0091 fax