HomeMy WebLinkAboutCHANGE ORDER - RFP - P1161 PEDESTRAIN AND BICYCLE GRADE SEPERATED CROSSING AT TROUTMAN PARKCity of
Flirt Collins
ngineedng ..
Nds.
Planning, Development &
Tr nsportation
Engineering
281 North College Avenue
Ro. Box 6B0
Fart Collins, CO 80622.0680
070.221.660S
970.221.6378 - Iax
Change Order Form
PROJECT TITLE: Mason Corridor Troutman Crossing
PROJECT NUMBER: 400903206.3 (P1161)
CONTRACTOR: J F Sato & Associates (PO #9962494)
CHANGE ORDER NUMBER: 2
1. Reason for change. 2. Description of change.
3. Change In contract cost 4. Change in Contract time.
1&2. See attached sheet for detail.
3. The contract cost will increase by $ 89,621.38
4. The contract time will be extended to December 31, 2011.
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O. °% OF ORIGINAL CONTRACT
ADJUSTED CONTRACT COST
(Assuming all change orders approved)
ACCEPTED BY:
REVIEWED BY:
ACCEPTED BY:
ivro)ect manager - Lngmearing)
ACCEPTED BY: -t2E.b I-
ep nt Head) `lam
APPROVED BY:
(P rohas' g Agent over $60,000)
W. Contractor
Purchasing
Prolaet Flle
41.07%
41.07%
$21B,211.00
$0.00
$0.00
$89,821.39
$307,832.38
DATE: Q-I-L)
_ DATE ( (n / /!
Al deja.
J �� Engineering, Environmental, es and Program Management Servic
5878 South Rapp Street • Littleton, CO 80120
Phone 303.797.1200 • Fax 303.797.1197
J. F. SATO AND ASSOCIATES www.jfsato.com
JF0919
August 15, 2011
Mr. Jin Wang
City of Fort Collins Engineering
281 North College Avenue
Fort Collins, CO 80521
Subject: Proposal for Additional Services Fees
Final Design — Troutman Parkway Grade Separation Structure
Dear Jin
As discussed over the last year, there have been numerous additions to our scope of work that have
required additional work hours. The majority of these have been due to changes requested by the BNSF
Railroad but there are some due to the BRT changes to the project. Also, recent discussions with the
BNSF indicated they are willing to allow a cut -and -cover operation during the 7 days their tracks are shut
down in July, 2012.
By allowing this open -cut type of construction, the City can save over $400,000 by eliminating the use of
the BNSF RR construction forces and just allowing the City's contractor to do all the work. In order to
meet this 7 day "window" however, it is required that precast frame type structures be used. The existing
design and plans must be revised for this new type of structure.
I have broken this scope of work for additional services into two parts:
(1) All the BNSF and BRT changes prior to the BNSF allowing an open cut; and
(2) Revising the design and plans to accommodate a precast frame structure for the cut and cover
operation to occur in the 7 day window when the BNSF will be shut down.
Work shall be performed in accordance with the Scope of Services described below
(1) ADDITIONAL SERVICES FOR BNSF AND BRT CHANGES
After the January 13, 2010 meeting with Michael Baker regarding the BRT Corridor design coordination
with Troutman Parkway, you directed us to proceed with the final design of the bridge prior to receiving
the BNSF comments due to the length of time it was taking the BNSF to reply. JFSA proceeded with the
final design of the girders, caps and foundations. On February 17, 2010 we had a phone conference call
with the BNSF and received comments from them. Some of their comments required that we revise the
structure selection report to address their issues, revise the location of the piles and hence, the pile cap
configuration, and allow the BNSF to construct the portion under the railroad tracks. The BNSF wanted
revised plans before they would complete their initial review.
The BNSF estimate to do their portion of the construction is close to $1.2 million, almost 3 times what our
original plans were developed for. We feel this indicates that the amount of work that went in to making
Page 1 of 3
J Engineering, Environmental,
and Program Management Services
FS61%k 5878 South Rapp Street • Littleton, CO 80120
Phone 303.797.1200 • Fax 303.797.1187
J. F. SATO AND ASSOCIATES www.lfuto.com
the BNSF changes is commensurate with the increase in construction costs and that the estimated hours
provided are valid increases.
1.1. Revise plans per BNSF changes.
1.2. The structure selection report actually had most of the BSNF concerns addressed but not the
order they wanted. The report was revised to accommodate their required order. The piling
revision and cap revisions were made but these also required changes to the girder layout in
order to maintain standard 7-foot girder widths and keep the track centered on the girder gaps.
1.3. In addition, in April 2010, the BNSF decided to relook at doing a portion of the construction. They
originally said they could not do the construction in-house due to legal issues. Then in May, after
the plans were 65% complete, they notified us that in order for them to give the City a
construction cost bid on the project, they needed all the drawings brought up to "shop drawing"
level of detail, including bill of ladings and rebar bar lists. This work was partially compensated for
by charging the construction administration portion of the budget. However, that quickly ran out
due to the numerous changes.
1.4. Also, the notice that the BNSF would now be constructing the portion of the bridge supporting the
existing track and future track now required that JFSA revise the plans to indicate this two part
construction. This required additional calculations to ensure that the two portions were distinct
construction phases and more revisions to the general layout plan, the construction and
foundation plan, the phasing plans (2), the abutment plans (2), the pier plan, and the
superstructure plan.
1.5. The BNSF RR changed their standard plans after much of the plans were completed and they
required that we change all the drawings that were done to conform to the new standards. We
were notified of the change in standards in September 2010. The changes affected almost all the
plans dealing with the railroad standards (approximately 12 drawings).
1.6. The BNSF then required that we change the crown of the bridge to a Flat slope, after they had
agreed to the crown. This work required extensive changes to elevations of the deck, walls,
ramps, and stairs. This also affected the pier caps requiring extensive changes to the geometry
and reinforcement of each piece of cap.
1.7. The BNSF also revised the grading around the track. Rather than keep the grades the same as
the existing situation, they wanted only 6-inches of ballast. This required much excavation and
complete changes to the grading plan that had been completed earlier by JFSA.
1.8. The BNSF originally said no deck drains were required. Later, they changed their minds and
required a transverse deck drain at the north side of the bridge. This required an in depth review
of the pipe path since there are now numerous other drain pipes involved.
1.9. The BRT designers added their drainage system to the drainage pipes on our project. This
required adding one manhole, one new stretch of pipe, revising almost all the invert elevations,
and changes to the size of our pipes. While the BRT designers provided some of the details,
almost all the details on our drainage plans had to be revised.
1.10. Additional project management and coordination effort for the above work.
Page 2 of 3
Engineering, Environmental,
and Program Management Services
5878 South Rapp Street • Littleton, CO 80120
- Phone 303.797.1200 • Fax 303.797.1187
J. F. SATO AND ASSOCIATES wanv.ifsato.com
(2) DESIGN AND PLAN REVISIONS FOR 7-DAY ALTERNATIVE
2.1. Revise design and plans to allow precast 3-sided bridge with precast slab footing. Provide
performance specifications to specify AREMA loadings requirements on the portion of the
structure under BNSF ROW and for AASHTO specifications for the portion under the BRT. This
includes redesign of the walls and ramps at each entrance to the underpass.
2.2. Design and detail cast -in -place reinforced concrete skewed end portion of structure.
2.3. Provide independent design check of the cast -in -place portion.
2.4. Provide bridge rating of the cast -in -place portion.
2.5. Design, detail, and coordinate with BRT designer for modifications to storm sewer system to
accommodate the precast bridge and slab footing.
2.6, Design, and detail, for modifications to the lighting details due to change from a two span
structure to a one span precast structure. Coordinate with BRT designer for location of new
power source, including details of equipment and revise electrical conduit for the new location.
2.7. Provide plans, coordination, and revisions for new submittals (50%, 80% & 100%) to the BNSF
RR for the new plans and include meetings and revisions.
2.8. Revise and add new specifications for the new structure.
2.9. Provide new construction cost estimates at each of the new submittals (see item 5)
2.10. Provide project management and coordination for the new submittals.
2.11. Geotechnical engineer review of impacts of precast structure on geotechnical recommendations
Design for the portion of the structure under the BRT lanes will be in accordance with AASHTO
specifications. Design for the portion of the structure under the BNSF RR will be in accordance with
AREMA and the BNSF RR standards.
Please review my fee proposal and scope of services to verify that they are acceptable to you. If you
have questions or need additional information, please contact me at 303-868-2489 or e-mail me at
skobayashi64@msn.com.
Sinceerrely,
Stan Kobayashi, P
Project Manager
Attached: Exhibit A, Engineer's Estimate of Fees
Page 3 of 3
J FS
J. F. SATO AND ASSOCIATES
Engineering, Environmental,
and Program Management Services
5878 South Rapp Street • Utgeton, CO 80120
Phone 303.797.1200 • Fax 303.797.1187
vmvw.jfsato.com
EXHIBIT A - FEE SCHEDULE
ENGINEER'S ESTIMATE OF FEES FOR DESIGN CHANGES
Troutman Parkway Grade Separation
LABOR HOURS
J.F. Sato and
Assoc.
KDG Engineering
Sr. Bridge
Hydaulic
Bridge
CAD Tech
Scope Item
Subs
Expenses
Total
En r
En r.
Tot. Hra.
Labor
Billing Rates:
$75.00
$94.52
$80.00
$65.00
(1) ADDITIONAL SERVICES
85.0
12.0
108.0
333.0
538.0
$37,794.25
$0.00
$37.794.25
1.1. Revise plans due to BNSF requirements
12.0
0.0
24.0
71.0
107.0
$7,435.00
$7.435.00
1.2. Revision to Structure Selection Report for
80
0.0
7.0
8.0
21.0
$1,530.00
$1,530.00
BNSF
1.3. Shop drawing level of plans for BNSFbid
120
0.0
32.0
88.0
132.0
$9,180.00
$9.180.00
t
1.4. Revise plans and estImate for BNSF
4.0
0.0
22.0
68.0
94.0
$6,48D.0
$6.480.00
construction
1.5. Revise plans for new BNSF standards
4.0
D.0
8.0
24.0
36.0
$2,500.00
$2.500.00
1.8. Changes to plans and elevations due to
4.0
0.0
12.0
32.0
48.0
$3,340.0
$3,340.00
BNSF gat bridge
1.7. Regrading due to BNSF change in existing
2.0
0.0
1.0
22.0
25.0
$1,660.
$1,680.00
lope.
1.8. BRT drainage system changes and
2.0
12.0
2.0
2D.0
36.0
$2,744.2
$2,744.25
coordinabon.
1.9. BRT Storm Line Changes
20.0
20.0
$1,500.0
$1,500.00
1.10 Project management
19.0
19.0
$1,425.0
$1,425.0
(2) 7 DAY CONSTRUCTION REDESIGN
168.0
6.0
160.0
344.D
678.0
$48,327.131
$3,500.00
$0.00
$51,827.13
2.1 Revise plans for precast units. Revise
80
32.0
180.0
220.0
$14,860.00
$14,860.0
design of entrances.
2.2 Design & Plans for CIP Skewed end.
12.0
40.0
48.0
100.0
$7,220.0
$7.220.00
2.3 Independent Design and Plan Check
40.0
8.0
40.0
88.0
$6,240.0
$8,240.00
Skewed End
2.4 Bridge Rating Skewed End
4.0
8.0
12.0
$940.0
$940.00
2.5 Modifications to Storm Lines
16.0
6.0
8.0
30.0
$2,287.1
$2,287.13
2.6 Revise lighting and power
8.0
Ere
16.0
$1,120.0
$3,500.00
$4,620.00
E7 Addlbonal submittals & meetings (3) &
240
24.0
60.0
108.0
$7,620.00
$7,620.00
revisions
2.8 SpecIflcations
8.0
16.0
24.0
$11880.0
$1,880.00
2.9 New Construction Cost Esflmates
24.0
24.0
48.0
$3,720.00
$3,720.00
2.10 Additional Project MgL & Coord.
24.0
8.0
32.0
$2,440.00
$2.440.00
2.11 Geotechnical Engineer Review
Total Addendum Not to Exceetl Hours and
253.0
18.0
268.0
677.0
1216.0
$86,121.3E
$3,500.00
$89,621.38
Fees'
NOTES:
i- Note: Does not include hwrs used for shop OWN level of plans work that was charged to Shop Ommngs under the Conmiction
Administration Phase previously. These are In addition to those hours.
2-Note: Does nolinclude hours replacement of construction administration hours used for BNSF Shop Drawings. The Construction
Administration hours will be shod due to this.