HomeMy WebLinkAboutCHANGE ORDER - BID - 7209 REGISTRY NEIGHBORHOOD PARK (2)8- CHANGE ORDER NO. 2 PROJECT TITLE: Registry Neighborhood Park CONTRACTOR: J•2 Contracting Co. PRQIECTNUMBER: 7209 PURCHASE ORDER NO.: 9111342 DESCRIPTION: Miscelaneous Small Contract Changes 1. Reason for charge: Sawcul Existing 4' Walk at 6" wide to gel consistent cross slope on adjacent walk. Repour newwalk at 4.5'. Modify plating for Restrcom Roof Rake for 2:12 root. Paint Equipment Room (Interior). Change Bluegrass sod to Kerby Vortex Sod. Charge Bluegrass Seeding to Korby Vortex Seed. Add landscape area in playground walk section with (1) Honey Locust, (5) Karl Forester Gasses, and associated drip irrigation. Thicken sand section to 10" for'diggee playground equipment. 2. Description of Charge; 1) Refer to CWRN2 Dated A29/11 for details S 15,528.20 3. Change in Contract Cost: 4. Change In Contract Time: Extend by 3 Days TO IAL APPROVED CHANGE ORDER 3 22.003.20 TOTAL PENDING CHANGE ORDER S TOTAL THIS CHANGE ORDER 28.20 S 15,528.20 TOTAL % ORIGINAL CONTRACT, THIS C.O. TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S 3.59% ADJUSTED CONTRACT COST f1,081,831.40 (Assuming all charge orders approved) ACCEPTED BY: ',�G•Ce /� DATE: = t OI I Conracloes Represonl�llvo ------ / (� ACCEPTED BY: /ram t— DATE: Project Manager REVIEWED BY: Tille: APPROVED BY: Title: DA PLU=11 APPROVED BY: DATE: Purchasing Agent over $30,000 «: city aenr ArehNw Conlmclor EgInear PMjW FI4 Pw .slna CHANCE IN WORK RE.QU¢ST "2" Initiation Date: 7n9Q0/1 Project) Rcipi Neighborhood Park Owner: City of Fort Collins To: J4 Counsellog Co. Requested by Craig Killing Authorized by: Craig Kisling Please furnish change in contract sum lot the change in work described below. Do not order material or start any work until approval is received, Every effort will be made to incorporate this change gran the work without afpecling the conlracr dale. Description of Proposed Changes - amount 1) Sawwt e' Concrete on 4' Walk In ROW (700 LF Q $3 0015F) $2.100.00 2) Demo- Existing Concrete Flatwork (390 SF Q $4.00/SF) $1,500.00 3) Standard Grey Concrete Flatwnrk (390 SF ® $2.801 $1,014.00 4) Paint Equipment Room (Intedor) $920.00 5) Additional 2"x B" Plating Material for 2:12 Rake Roof to malmaln wnsistant 2.12 around lower roof $138.00 given inconsistent Top of Child elevations 8) Addition be Landscape Bed In Playground Area- Irrigation Staining under Side milk/Sand Area, Drip Irrigation In Tree/Grasses $315.00 7) Addition of Landscape Bed In Playground Area- 5 Karl Forester Grasses at $27D0hEA $135.00 8) Addition of Landscape Bed In Playground Area- 1 Honey Locust at 3250.00 EA $250.00 9) Change all Sod to Kerby Vortex Sod (No Additional Cost) $0.00 10) Change all bluegrass seed to Korby Vortex Seed E8,897.00 11) Add 4" Sand to 'Digger area (484 SF/l0 Tons @ 535,00Ron) $350.00 12) Deduct 58 SF Grey Concrete Flatwork for in Playground Landscape Island (5B SF @ $2.801 4150,810 TOTAL $15,528.20 J-2 Cuomcfi.e C.. , egrens to change the work described above for the change to price shown below. 1 have attached a brcul down which lists all costs of labor, materials, taxes, overhead, profs) and all other changes and/or charges involved. Signature oflhc Contractor indicates his agreement herewith, including any adjustment in the Contract Sum or Contract Time. The Controct Time will be Increased by 3 Days. No change in Contract SUM (Inital ifna chsnse) _ ADD to the Contract Sum S 15.528.20 DLUUCf form the Contract Sum S Phis information shall be valid for thirty, (30) calendar days from die date of signature below. CON TRACTOR'S SIGNATURE—,---' 'oxi-n: 7129R011 Contractor Than hero one copy and mmm ORIGINAL te O r APPROVED BY OWNER: (�/� / / I"� ) t Accepled Chung, ra work request will be included in a future formal change order DO NOTbill for this change anti a forum! change aide, has been exec and by all purdi . Acceptance is direction toproceedwtrh the work describedherefe. Nor valid unless signed by the owner and the contractor.