HomeMy WebLinkAboutCHANGE ORDER - PURCHASE ORDER - 9957271SECTION 00950
CHANGE ORDER NO.
PROJECT TITLE: Police Services Facility Fueling Installation
CONTRACTOR: Kubat Equipment & Service Co.
DESCRIPTION: The installation of two above ground 1000 Gallon fuel tanks and dispensing facilities for
refueling at the Police Services Facility.
Reason for change: Incorporation of various changes.
2. Description of changes: Upgrade the Fuelmaster from an FMU 2500 plus to a FMU 3550 plus -
$3,585.00; Upgrade the Fuelmaster software — $295.00; Install the TCP/IP Network Card — $719.04; Install
Black Box Ethernet Extender - $705.37.
3. Change in Contract Cost: $5,304.41
4. Change in Contract Time: None.
ORIGINAL CONTRACT COST $61,189.88
TOTAL APPROVED CHANGE ORDERS
0.00
TOTAL PENDING CHANGE ORDERS
0.00
TOTAL THIS CHANGE ORDER
Q04.41
ADJUSTED CONTRACT COST
$66.494.29
ACCEPTED BY: a 6
Contractor's Representative D e
APPROVED BY: 1. CT /1' 1, . R c e) / C, Z 6 I
Facilities Project Manager Date
cc: Purchasing, Contractor, Project File