HomeMy WebLinkAboutCHANGE ORDER - BID - 7204 VETERANS PLAZA AT SPRING CANYON COMMUNITY PARK (5)CHANGE ORDER NO. #5
t
PROJECT TITLE: Veterans Plaza
CONTRACTOR: Landtech
PROJECT NUMBER: 72b4
PURCHASE ORDER NO.:
DESCRIPTION: add rebar Into stairs at statue
1. Reason for change: all rebar deleted in oo #4, add back in rebar for stairs.
2. Description of Change: all rebar deleted in co #4, add back in rebar for stairs.
3. Change in Contract Cost: $423.50
4. Change in Contract Time: 0
TOTAL APPROVED CHANGE ORDER
($26,811.75)
TOTAL PENDING CHANGE ORDER
$6,621.20
TOTAL THIS CHANGE ORDER
$423.50
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.
TOTAL" % OF ORIGINAL CONTRACT, ALL C.O.'S
13.390%
ADJUSTED CONTRACT COST
$1�77,187.95
(Assuming all change orders approved)
ACCEPTED
Contractors
ACCEPTED BY:
Project Manager
REVIEWED BY:
Title: pLSve
ra rf
APPROVED BY:
Title:
APPROVED BY:
Purchasing Agent over $30,000
oc City Clerk Architect
Contractor Engineer
Project File Purchasing
DATE:
DATE:
DATE: 7— / — /I
DATE:
DATE:.
n