EXHIBIT "A"
WORK ORDER FORM
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
ANDERSON CONSULTING ENGINEERS, INC.
Citvof Fort Collins
BID NO. 7084
Date:
June 13, 2011
Work Order:
ENG 08 — 001-LDS
Purchase Order:
Project Title:
Consulting
Commencement Date:
6/1/2011
Completion Date:
8/1/2011
Maximum Fee:
Per Contract Unit Prices
Project Description: Floodplain Permitting Support for
Lemay Ave. Repaving at Dry Creek
Scope of Services: (1) Per attached Exhibit A, dated May 17, 2011
Acceptance:
User
Service Provider agrees to perform the services
identified above and on the attached forms in
accordance with the terms and conditions
contained herein and in the Services Agreement
between the parties. In the event of a conflict
between or ambiguity in the terms of the Services
Agreement and this work order (including the
attached forms) the Services Agreement shall
control.
Service Provider
By:
Date: cz✓ /a L701 /
CC: Purchasing
The attached forms consisting of two (2) pages
are hereby accepted and incorporated herein by
this reference, and Notice to Proceed is hereby
given.
City of Fort Collins
By:
Date:
Director of Purchasing and Risk Management
Over $30,000
S:1StreetslPMPlCommon\p.m.p\PROJECTSt20091Project CoordinatlonT loodplaln Use PermitsWMerson Consulting InMork Order
Eng 11-001•ACl.doc
EXHIBIT A May 17, 2011
SCOPE OF WORK
for
FLOODPLAIN PERMITTING SUPPORT FOR
LEMAY AVENUE REPAVING AT DRY CREEK
The intention of the work effort defined in this scope of work is to conduct the necessary
evaluation necessary to support the preparation of a City of Fort Collins no -rise certification for the
completed repaving project along Lemay Avenue at Dry Creek, directly north of Vine Drive. This scope
includes an optional task that addresses hydraulic modeling, in the event modeling Is required.
For the Lemay Avenue at Dry Creek project, rood surface elevation tolerances only apply along
the street centerline (crown). These tolerances require that post -project rood surface elevations along
the street centerline, within the regulatoryfloodplain, be constructed no higher than 0.01 feet above the
corresponding pre -project road surface elevations; however, there is no restriction on post -project road
surface elevations being lower than pre -project road surface elevations. If the above criterion cannot be
met an alternate criterion will be considered prior to resorting to hydraulic modeling. This alternate
criterion would allow individual spot elevations to exceed the 0.01-foot threshold, provided that the
corresponding flow area over the street crown, below the 100-year water surface elevation, has
increased for the post -project condition. This can occur when other post -project spot elevations along
the street crown profile are lower than pre -project elevations to the extent that they compensate for the
road elevotion(s) that exceed the normal threshold.
This scope of work assumes that survey data points of post -project road surface elevations will
be provided by the City as a text file, in State Plane coordinates. It is also assumed that the City will
provide a hard copy map showing post -project road surface elevations, with this map stamped and
signed by a registered Professional Land Surveyor (at the discretion of the City Surveyor, this map may
provided as a PDF file).
Task 1. Data Collection/Review and Base Map Preparation
ACE will collect all available information that is pertinent to the project, including: (a) post -
project condition survey data; (b) effective hydraulic model for Dry Creek; and (c) effective floodplain/
floodway mapping for Dry Creek, available through the Stormwater Department as a series of GIS shape
files. ACE will also conduct one site visit to visually verify post -project conditions. Also as part of this
task, ACE will prepare a base map in AutoCAD' showing the effective floodplain and floodway
boundaries for Dry Creek in the vicinity of Lemay Avenue, channel cross sections used in the effective
hydraulic model, and post -project survey points along the centerline (crown) of Lemay Avenue.
Task 2. No -Rise Certification for Lemay Avenue at Dry Creek
ACE will review the pre -project street centerline profile (as depicted in the effective hydraulic
model) and post -project condition survey data also along the street centerline. A graphical profile will
be prepared showing both pre -project and post -project condition road surface elevations. Road surface
elevations will be compared throughout the regulatory floodplain with respect to meeting the
tolerances identified above. If the 0.01-foot threshold is not met at all locations within the floodplain,
then a cross -sectional (centerline profile) area evaluation will be conducted in accordance with the
alternate criterion identified above. A brief memo will be prepared that discusses the critical areas of
the project with respect to meeting City floodplain regulations, and whether or not the post -project
condition meets these floodplain regulations.
Assuming that all post -project condition road surface elevations or the cross sectional area
along the street centerline meet the tolerances identified above, a City of Fort Collins No -Rise
Certification will be prepared and submitted to the Stormwater Department with a copy sent to the
WFC2011.05_LemayOryCr_mw.dwx Page 1 of 2 ANdERSON CONsulliNc, ENCIiNEEnS, INC.
EXHIBIT A May 17, 2011
City's Project Manager. It is noted that any changes to the documentation or no -rise certification
required due to Stormwater Department comments are not included in this Scope of Work.
This task will Include up to two (2) meetings with Streets Department Staff and/or Stormwater
Department Staff to define the project limits and intent, as well as project requirements with respect to
floodplain regulations. Coordination via telephone and email will be provided on an as -needed basis
throughout the course of this task.
Task 3. Hydraulic Modeling for Dry Creek at Lemay Avenue
This task will be pursued if the identified road surface elevations do not meet the required
tolerances. This task will include hydraulic modeling of a short reach of Dry Creek in the vicinity of
Lemay Avenue using the effective HEC-RAS model for Dry Creek.
A duplicate effective analysis of the 100-year event will be conducted to verify the effective
hydraulic model. A post -project condition hydraulic analysis of the 100-year event will be completed
utilizing the available post -project condition survey elevations of the street centerline.
A comparison of effective and post -project condition 100-year water surface elevations will be
made at each cross section. Assuming that all post -project condition water surface elevations are no
higher than 0.01 feet above the corresponding pre -project condition water surface elevations, a memo
will be prepared documenting the analyses and their results. As identified in Task 2, a City of Fort Collins
No -Rise Certification will be prepared and submitted to the Stormwater Department with a copy sent to
the City's Project Manager. It is noted that any changes to the documentation or no -rise certification
required due to Stormwater Department comments are not included in this Scope of Work.
This task will include up to one (1) additional meeting with Streets Department Staff and/or
Stormwater Department Staff to define the requisite hydraulic analyses and the results of these
analyses. Coordination via telephone and email will be provided on an as -needed basis throughout the
course of this task.
If the hydraulic analyses reveal increases in post -project condition 300-year water surface
elevations above the 0.01-foot threshold, possible options for mitigating these increases will be
discussed with Streets Department Staff and pursued under a separate scope and budget.
COFC2011.05_LewyDrVU_ sow.docx Page 2 of 2 ANdERSON CONSUhiNq ENgiNEERS, INC.
LemayAvenue at Dry Creek
EXHIBIT 8
BUDGET
for the
FLOODPLAIN PERMITTING SUPPORT FOR
LEMAY AVENUE REPAVING AT DRY CREEK
May 16. 2011
PROJECT: F/oodplain Permitting; Lemsy Avenue at Dry Crook
CLIENT: City of Fort Collins Streets Departrnent
. Anderson Consuldrig Engineer, Inc.
Direct Lab"
01
Totals
ACEPROJECTNO.: COFC2011.05
PREPAREDBY: GJK
DATE. 05/16,2011
Principal
Engineer
$1321hr
Project
Engineer ll
894nx
Senior
GIS/CADD
Terhria rm
877ar
GISICADD
Technician
872/hr
Admen.
872/hr
Admin.
Assistant
885/hr
Other
Direct
Costs
TasidDeseription
Hours
Hors
Hours
Hours
Hours
Hoes
Cost
Hours
Cost
1. Data Collaction/Review and Base Map Preparation
6
4
8
18
2. No -Rise Certification fee m Leay Avenue at Dry Crank
16
24
8
2
450
50
{5,1 64
3. Hydraullc Modeling for Dry Creek at Lamy Avenue
8
24
4
2
5100
38
53, BU
TOTAL PROJECT HOURS
30
52
20
0
0
d
106
TOTAL PROJECT BUDGET-
S3,960
84,888
,81,540
So
80
,5260
5150
8f0,78