Change Order Form
PROJECT TITLE: College & Mountain Federal Work
PROJECT NUMBER: 158639 ^—
CONTRACTOR: Colorado Boring
CHANGE ORDER NUMBER: 1
n preparing change orders show In order as separate numbered paragraphs the owing:
1. Reason for change. 2. Description of change.
3. Change in contract cost. 4. Change in contract time.
1. Extra excavation and potholes required
2. Additional exavatlon pits and potholes
3. The contract cost will be effected. $ 4,320.00
4. There will be no change in contract time
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O. % OF ORIGINAL CONTRACT
ADJUSTED CONTRACT COST
(Assuming all change orders approved)
20.03%
20.03%
$21,565.00
$0.00
$0.00
$4,320.00
$25,885.00
ACCEPTED BY: r DATE: 6-
oo
APPROVED BY: DATE:
(City of Ft.Collins)
APPROVED BY: DATE:
(Purchasing Agent over $60,000)