Change Order Form
PROJECT TITLE: Harmony/College Landscape & Urban Design Improvements .
PROJECT NUMBER: 400901802.6 (Bid #7161)
CONTRACTOR: American Civil Constructors (PO #9104728)
CHANGE ORDER NUMBER: 6
1. Reason for change. 2. Description of change.
3. Change in contract cost. 4. Change in contract time.
1&2. See attached sheet for detail.
3. The contract cost will decrease by $ 1,247.60
4. There will be no change in contract time.
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS .
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O. % OF ORIGINAL CONTRACT
ADJUSTED CONTRACT COST
(Assuming all change orders approved)
ACCEPTED
0.20 %
5.90 %
DATE:
REVIEWED BY:
--f
DATE:
/ �(Engine
'7�p�/
SUBMITTED BY.
DATE:
.(L
(Project Manager)
APPROVED BY:
C d�Gy
DATE: ' I " I
�J
� ( artmen Head
APPROVED BY:D
DATE:
(Purchasing Agent over $60,000)
cc Canlracler
Purchasing
Project File
$638,617.00
$36,411.31
$0.00
$1,247.60
$676,275.91
CHANGE ORDER S
College Harmony Landscape and Urban Design Project
SUMMARY OF WORK
Item # Item Ouantlty unit .F r una T„ r.�
1
Additional Sleeves under Sidewalk
1
LS
$ 287.30
$ 287.30
2
Concrete Pole Base Repair
1
LS
$ 496.00
$ 496.00
3
Cedar Post
1
LS
$ 218.30
$ 218.30
4
Bollard Plate Removal and Sealing
1
LS
$ 246.00
$ 246.00
TOTAL
1,247.60
REASON FOR CHANGE
1
Additional Sleeves were required under the sidewalk at Spotlight Music and Livingston's corner
2 Concrete pole base repair made at Mason Street signal pole base.
3 Installation and removal of a cedar posts that was requested by City parks but later agreed that it would look out of place and not necessary.
4 Removal of Ballard plates on bollards thatwere knocked over by traffic. Price includes sealing the holes left from unbolting the plates.
Additonal Ono Irrigation was installed along the east side of Colelge Ave In an area that was originally bid as gravel but later revised for
6
landscape plantings by BHA/City. - REMOVED FROM CO - WAS NOT INSTALLED
WHEN POSTED
Posted to Pay App #5