HomeMy WebLinkAboutPrebid - BID - 7212 WEST MYRTLE ALLEY - DOWNTOWN ALLEY ENHANCEMENTS (2)Downtown Alley Enhancements
Pre -Bid Meeting and Walk Through
March 11, 2011; 1:00 pm
Agenda
Introductions
Procedural Items — John Stephen, City of Fort Collins Purchasing
1. Sign -in sheet; mandatory pre -bid meeting
2. Bid Opening: March 24, 2011 at 3:00 pm; Purchasing Department
3. Ensure bid addendums are documented/received
4. Bid Bond — 5%
5. Sealed bid with separate qualifications
a. Qualifications listed in Section 01010 Part 1.3
6. Provide list of unit prices (add/deduct) in addition to lump sum bid
7. Last day for questions: March 21, 2011 end of business (5 pm MST)
a. Direct all procurement questions to John Stephen
b. Direct all plan and specification questions to Keith Meyer
III. Contract Times
Substantial Completion (entire project) — 100 calendar days
Liquidated Damages - $1,300 per day
Substantial Completion (intermediate milestone) — 45 calendar days
Liquidated Damages - $1,000 per day
Final Completion — 20 calendar days from Substantial Completion (entire project)
Liquidated Damages - $750 per day
IV. Warranty — 2 year
V. Plan set scale (full size at 22x34, half size scale at 11x17)
Presentation Handout:
VI. Project Locations and Scope of Work
VII. Staging, Demolition, Access and Traffic Control
Vill. Utility Relocation Coordination
IX. Business Owner and Tenant Access and Coordination
X. Temporary Facilities
XI. Permits
XII. Technical Specifications
XIII. Site Walk Through
3/11/2011
Alley Enhancement Project
West Myrtle Alley
Bid #7212
Pre -Bid Meeting
March 11, 2011
1:00 pm
No
FortCollins
Itasca '"'4r� :`j cLl:l
Bid Process
• Purchasing Questions:
— John Stephen: 970-221-6777;istephen®fcgov.com
• Plan/Specification Questions:
— Keith Meyer: 970-988-8605;
keithmeyer@ditescoservices.com
• Bid Opening Date rime:
— March 24'h, 3:00 pm (Purchasing Clock)
• Qualifications Based Bid
— Please note required qualifications submittal
— Section 01010 Part 1.3
urt`
Fort Collins
itesco -� 6add;,
Project Locations & Scope of Work
• West Myrtle Alley(WMA)
— laurel Street to Myrtle Street
— Main alley to Mason Street
• Scope of work:
— Utility relocation; electrical and irrigation installation;
concrete paving; light pole, site furnishing, fencing
and unit paver installation.
ort
ditesco Collins F�r .EN
1
3/11/2011
iwe Wexr Myrtle Mey
IIR.F jis —
zz
.I FiO as", E3 FE
"`:� r' �rrif ! MlW
IA1 ' A s,: x Ail•
--�. P,Tary sraeing + ll
aoM1emlan Peoperty r--ll
Clryef to
Fort Collins
ditesco
W. MMIe a,
Y 4
rl � yy
-- Demolition ore. w'i MSS'
�11
_
Fo`rytC
ditesco ollins
-�— F I�
Access and Traffic Control
• Pedestrian
—Isolated businesses require 24/7 access (see G004)
— Alley Cat access to be maintained from Laurel
• Vehicular
— Access from College to Bohemian Lots (KRFC)
— Delivery access throughout the day primarily from
College and Laurel
— Trash pick up
• Traffic Control plans shown are schematic for
bidding purposes only
lryor
FortColllns
itesco '-�i� trl�i&a
3/11/2011
Utility Relocation Coordination
• Comcast- vault and pedestal upgrades
• Qwest- overhead to underground (prior to start)
• City Light and Power- underground relocation
and vault adjustments
• Xcel Energy - underground gas relocation
— Refer to all UR plan sheets
• Critical to success of project
— Maintain Service to businesses
— Coordinate outages and downtime (min. 48 Ins)
• Three week schedule, door hangers, visits
owor
Fort Collins
ditesco -� E$d1):t
Business and Tenant Coordination
Refer to Section 01010
—Accommodate multiple deliveries on multiple days
— Allow access across construction zone
• Businesse ployees;Businessdellvenesand Tenants
— Provide for trash and recycling service throughout
construction duration; include removal of existing
dumpsters
— Provide for grease trap service and removal
— Recognize residential nature of areas of work
• Noise level for tenantslresidents
• Workinghours:8amto6pm;mcningdeliveries
• CSU student coordination
rnyar
Fort Collins
ditesco '"fir` FR rwa
3
3/11/2011
Temporary Facilities
• Power and Water
Toilets
• Fencing (perimeter 6-foot chain link)
- Continuous pedestrian access - 0 weather surface
• Trash and recycling containers
- 25-30 cy roll off
- 12-15 cy, mmingied recyclables
• Phone and other services
• Transformerprotection
For!Coltins
ditesco -�— !9, I , i:,
Permits
• Permits required by Contractor
-Right of Way Construction - Gty of Fort Collins
• $7,000includedin bid schedule
- Construction Dewatering - if needed
-SWNIP
- Building Permit
- Irrigation Backflow Preventer Permit/Inspection
• Permits by Owner
- Floodplain Use
Fo"rt'•Collins
ditesco ��— 11 C111
Technical Specifications
• Divisionl
- Quality Control testing by Owner
• Failing tests/retests by contractor
• Division
- Interlocking concrete pavers - Pavestone, Inc.
• Notesparepatslmaterials
- Irrigation service taps by City
- Site Furnishings
• No substitutionsto specified products
ditesco F°rs
rd
3/11/2011
Technical Specifications
• Division
— Concrete: one primary mix design
• 4,000 psi flatwodc, paxng, cmb end seal walls
• Division
— Brick (Robinson - no substitutions)
• Division 16
— light Poles - Holophane (early submittal)
— 72 hour operational test; 14 day performance test;
night test
— 5%spare parts/extra materials (ballasts)
c por
Fo'HCollins
ditesco -�— €0
Site Walk Through
• Start at north end of West Myrtle Alley
otyof
ditesco '�ortr s €R d'i:,