HomeMy WebLinkAboutCHANGE ORDER - BID - 7152 PRESSURE WASHING FOR DOWNTOWN AND OLD TOWN SQUARE (3)CHANGE ORDER NO.2
Project Title: 7152 Pressure Washing Downtown/OTS/Alleys
Contractor: Top Gun
Project Number: Bid 7152
Purchase Order Number -
Description: Medians and Streetscapes Maintenance Contract
1) Reason for Change: Add the. monthly cleaning of Fire House Alley and Montezuma Fuller
Alley to the downtown and Old Town Square pressure washing contract.
2).Description of Change: The addition of fire House Alley ($6,080.00) and Montezuma Fuller
Alley ($4,520.00) for.eight cleaning per year in conjunction with the downtown and Old Town
Square cleaning contract.
• Previous Cost in 20.1.0 - $74,170.b0
• Adjusted Cost for 2011 - $10,600.00
3) Change in Contract Cost:;$74,170.00 to $84,770.00
4) Change in Contract: Addition of two alleys (Fire House Alley and Montezuma Fuller Alley) to
the downtown and Old Town Square contract per Bid i17152.
ORIGINAL CONTRACT COST $74,170.00
TOTAL APPROVED CHANGE ORDER
TOTAL PENDING CHANGE ORDER'
TOTAL THIS CHANGE ORDER $10,600.00
ADJUSTED CONTRACT COST $84,770.00
(Assuming all change orders approved)
ACCEPTED BY%, P (:�. % DATE:/
ACCEPTED BY: �/4� (/ f DATE: l 11
'1)-; .t
REVIEWED BY: DATE:
Title:
APPROVED BY: DATE:
Purchasing Agent over $60,000.00