EXHIBIT "A"
WORK ORDER FORM
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
and
Connell Resource
DATED: March 15, 2011
Work Order Number: 01-400903707-11
Project Title: Linden Street Project — Driveway Installation at El Burrito
Commencement Date: February 7, 2011
Completion Date: April 10, 2011
Maximum Fee: (time and reimbursable direct costs): not to exceed $ 11,000 (quoted price plus 15%
contingency)
Project Description: Remove Fence at El Burrito on Willow Street and install asphalt driveway across railroad tracks.
Scope of Services: Install all items as priced on attached quote dated 2/2/2011.
Service Provider agrees to perform the services
identified above and on the attached forms in
accordance with the terms and conditions contained
herein and in the Services Agreement between the
parties. In the event of a conflict between or
ambiguity in the terms of the Services Agreement
and this work order (including the attached forms),
the Services Agreement shall control.
Service Provi r (3�lnna u5gJ CGe,S
By:
Date: Al A\l
Approved By:
Purchasing Agent over $60,000
The attached forms consisting of three (3) pages are
hereby accepted and incorporated herein by this
reference, and Notice to Proceed is hereby given.
City of Fort Co lins�
By:
Date: 3/1 S/ f /
Connell Resources, Inc.
7785 Highland Meadows Pkwy, #100
Fort Collins, CO 80528 M
Phone: (970) 223-3151
Fax: (970) 223-3191
Estimator: Dan Giesler QUOTATION Date: 2/2/2011
Submitted To: City Of Fort Collins - Engineering Bid Title El Burrito - Entrance Off Willow
Address: 281 North College Avenue Bid Number:
Fort Collins, CO 80522 Project Location: Linden & Willow
Contact: Craig Farver - Project City, State: Fort Collins, CO
Phone: 970-221-6605 Fax: 970-221-6378 Engineer/Architect:
We offer for your consideration the following Quotation which, if accepted, shall constitute a contract between us.
Item #
Item Description
Estimated Quantity Unit
Unit Price
Total Price
202-07
Remove Asphalt B" Avg. Depth.
44.00 SY
$8.30
$365.20
202-18
Saw Cut Asphalt More Than 6" Depth
98.00 LF
$2.40
$235.20
203-01
Unclassified Excavation
14.50 CY
$3.00
$43.50
203-04
Load, Haul And Dispose
14.50 CY
$9.80
$142.10
203-07
Borrow ABC Class 5 or 6 (CIP).
25.00 TON
$21.61
$540.25
403-02
Asphalt Hand Patching — Grading S-75 or S100 (PG
25.40 TON
$122.05
$3,100.07
58-28) (2"-3" Depth)
603-44
4" Median Underdraln Pipe Solid (2" Conduit)
30.00 LF
$17.80
$534.00
626-01
Mobilization (See Spec) - ?
1.00 EACH
$0.00
SW $0:00
630-01
Traffic Control Supervisor — /`A 4 '7a/r a
3.00 DY
$406.26
$1,218.78
999
Dismantle, Remove Fence & Piers
1.00 LS
$3,450.00
$3,450.00
Total Bid Price:
$9,629.10
Notes: • Pricing is based upon drawing provided by Mark Laken
• The following are excluded from this proposal: Construction layout and engineering; Drainage facility certification; Warrantee period in
excess of one year; Street cleaning for work performed by others; Permits: including but not limited to, city building, development
construction, construction dewatermg, wastewater discharge, storm water discharge (NPDES), air quality, etc.; Fees, including but not
limited to, for developement, inspection, utility connection, meters, etc.; Dewatering; Maintenance of erosion control devices for others;
quality control or acceptance testing; prairie dog removal, relocation, or extermination; landscaping, seeding, or revegetation.
• Pavement Drainage less than 1.5% designed or obtainable fall will not be guaranteed.
• Material Prices for pipeline Items are guaranteed for a period of 30 days from the Date shown on the top of this quote. After 30 days the
material prices may change the unit prices quoted.
• All work is contingent on the availability of construction water, access to the work, negotiation of acceptable contract terms, a mutually
agreeable schedule, and verification of financing.
• Please provide a minimum of 2 weeks advanced notification of work requests to allow for scheduling the work. No work will be completed
without a signed Contract Agreement. Work is anticipated
• Frost removal or winter protection is not included. If requested, it will be billed either on a time and material basis or lump sum amount
that is mutually agreed apon.
• Connell will install fire line to the extent agreed upon, Connell will notify the sponsor so that a certified fire protection contractor is availiable
to inspect the installation, pressure test, and blow off of the fire line, Connell will only perform these tests once.
• Asphalt Cement suppliers are not holding their prices from month to month. Therefore prices will be subject to adjustment if asphalt
cement prices change. Currently the estimate includes Tons at a Price of $430 / Liquid ton for A/C Oil.
• Environmental site assesment / Mitigation of hazardous or contaminated materials is excluded.
Performance and Payment bond is excluded but can be included for 1% of Contract value
El Burrito - Entrance Off Willow Page 1 of 2