HomeMy WebLinkAboutWORK ORDER - RFP - P614 PAVEMENT MANAGEMENT PROGRAM (3)EXHIBIT "A"
WORK ORDER FORM
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
and
Deighton Associates
DATED: September 21, 2010
Work Order Number. 02-400902100-10
Project Title:
City Bridge Program
Commencement Date:
October 1, 2010
Completion Date:
March 1, 2011
Maximum Fee:
(time and reimbursable direct costs): not to exceed $67,320.00
Project Description
Create a bridge database and migration of bridge data
Scope of Services:
To have dTIMS CT generate a recommended maintenance & rehabilitation program with
supporting network and project level information as per the dTIMS CT BMS Implementation
2010-030 proposal..
Service Provider agrees to perform the services
identified above and on the attached forms in
accordance with the terms and conditions contained
herein and in the Services Agreement between the
parties. In the event of a conflict between or
ambiguity in the terms of the Services Agreement
and this work order (including the attached forms),
the Services Agreement shal control.
Date: September 21, 2010
The attached forms consisting of five (5) pages are
hereby accepted and incorporated herein by this
reference, and Notice to Proceed is hereby given.
Ci of Fo t Collin
B �•
Date: September 21, 2010
Approved By:
J
asing Agent over $60,0 .0
I ��
Deightor
dTIMS CT BMS Implementation
2010-030
Fort Collins, CO.
Prepared by: Rob Piane
rob.piane@deighton.com
Friday, August 20, 2010
Deighton Associates limited
11 Stanley Court, Unit 1, Whitby, Ontario, Canada 11N 3P9
Tel: (905) 565-6605 Fax: (905) 665-6645
www.deighton.com
Introduction
Fort Collins has requested that Deighton Associates prepare a proposal for the
implementation of a bridge management system within their current cITIMS CT framework.
This proposed project will build on the updated structures information and affect the
implementation of a series of analysis parameters within dTIMS CT to provide management
support information similar to that generated by clTIMS CT for the management of
pavements.
The objective of this proposed project is to have clTIMS CT generate a recommended
maintenance and rehabilitation program with supporting network and project level
information. The tasks required to realize this objective are described below.
Figure 1 is a summary of the tasks related to training and the associated cost of each task.
Price
.xfMIJ"-"'JE,
Mf` ., Task _ MAMnsu1t1hgREtraV0
Mt
., zM
Tota
Analysis Parameter Development
Parameter Development Meeting
$10,080.00
$2,160.00
$31,560.00
Review and Calibrate Bridge Indexes
$4,200.00
Develop Bridge Families
$3,360.00
Review and Calibrate Performance Expressions
$5,040.00
Define Treatments
$5,880.00
Define Economic Parameters
$840.00
Strategy Generation and Optimization
Generate Strategies
$6,720.00
$15,120.00
Optimize Network
$5,040.00
Review Program Recommendations
$3,360.00
Delivery and Training
Presentation and Training
$8,400.00
$2,160.00
$20 640.00
Final Report
$10,080.00
Total Proposed Cost
$67,320.00
Figure 1: clTIMS CT BMS Cost Proposal Summary
clTIMS CT BMS Implementation 2010-030
Page 2 of 6
Leighton Associates Limited
11 Stanley Court, Unit 1, Whitby, Ontario, Canada L1N SP4
Tel: (905) 665-6605 Fax: (905) 665 6645
www.&ighton.com
Task Descriptions
The above tasks that will be conducted by Deighton are described below.
Parameter Development Meeting
A parameter development meeting will be held to establish the set of parameters that will
be used to develop the foundation of the BMS. From these initial underlying parameters,
the complete management system can be mapped out and designed from the bottom up.
The parameters that will be investigated will include bridge indices, structure families,
performance models, treatments, budgets and economic parameters. Each of these
parameters is discussed below.
Fort Collins staff will play an important role in the parameter development meeting
because the goal of the meeting is to define a set of parameters that will help cITIMS CT
satisfy the bridge management desires of Fort Collins. The parameter development
meeting will be conducted over a three day period at Fort Collins. An agenda will be
produced in conjunction with Fort Collins staff prior to the meeting so that the appropriate
Fort Collins staff can be available, at the appropriate time, for their input into the parameter
development.
This project will have the benefit of having a completed set of dTIMS CT bridge analysis
parameters, developed for the City and County of Denver, as a starting point for the Fort
Collins analysis parameter development.
Review and Calibrate Bridge Indices
Condition indices are parameters in clTIMS CT that indicate the condition of a particular
element in the Fort Collins bridge network at a given time. Any number of indices can be
defined in dTIMS CT in order to establish the condition of the bridge elements. These
indices are derived from the condition data that is collected and can take the form of
individual distress indices or composite indices. Once established, a condition index is not
hard coded into cITIMS CT. They are parameters of the system that can be accessed at any
time for review or modification.
The example condition indices will be reviewed in conjunction. with Fort Collins staff and
modified accordingly.
Develop Bridge Families
In cITIMS CT all inventory items to be analyzed are organized into groups with anticipated
similar behavior. Groupings, or families, can be based on any attribute including, but not
limited to, structure type, traffic loading or geographic location. These families
accommodate the development of performance -curves that are applicable to distinct sets
of inventory items.
clTINIS CT BMS Implementation 2010-030
Page 3 of 6
Deighton associates Limited
11 Stanley Court, Unit 1, Whitby, Ontario, Canada LIN 8F9
Tel: (905) 665-6605 Fax: (905) 665-6645
www.deigliton..com
Review and Calibrate Performance Expressions
Performance expressions are mathematical models that describe the way in which
condition indices change with respect to some independent variable. Any form of
empirical, deterministic performance equation can be accommodated in cITIMS CT.
Deighton and Fort Collins staff will work together to define an initial set of performance
expressions from the basis that is provided by the Denver setup. A combination of
reviewing historical data and local opinion is used to develop both pavement families and
performance expressions. The equations for performance curves are not hard coded into
cITIMS CT and can be reviewed and revised at any time.
Define Treatments
Fort Collins staff will be surveyed to determine the list of treatment alternatives that have
historically been used in Fort Collins and performed favorably. After discussion the list will
be finalized and defined in cITIMS CT with respect to applicability, cost and the impact the
treatment has on the bridge inventory.
This list of treatments is used by cITIMS CT to generate multi -year treatment strategies for
the bridge elements defined in the BMS.
In cITIMS CT treatments are initiated according to trigger zones that are set for each
condition index. That is, if a bridge element's condition falls into a treatment trigger zone
the treatment is considered as a feasible treatment.alternative. It is then up to the
economic analysis in cITIMS CT to select the "best" feasible treatment based on the money
available in a particular year and the network benefit that is derived from the treatment
application. Treatment triggers are often referred to as decision trees.
The list of treatments and treatment triggers can be modified by the user at any time
following implementation.
Define Economic Parameters
Economic parameters in dTIMS CT include the definition of Budget Scenarios, Budget
Categories, Inflation Rate and Discount Rate. These parameters allow clTIMS CT to apply
economic judgment to the engineering based generated treatment alternatives.
Budget scenarios are different budget regimes that will be expected over the analysis
period and can range from no funding to unlimited funding. Any number of budget
scenarios can be defined for an analysis in cITIMS CT.
Budget categories can be defined to represent sources of funding for different types of
treatments within a given budget scenario.
Fort Collins staff will be consulted regarding appropriate budget information.
cITIMS CT SMS Implementation 2010-030
Page 4 of 6
Deighton Associates Limited
11 Stanley Court, Unit 1, Whitby, Ontario; Canada i IN 8P9
Tel: (905) 665-6605 Fax: (905) 665-6645
www.deighton.corn
Generate Treatment Strategies
clTIMS CT will take the calculated condition indices, apply performance parameters to
project the condition of each bridge element and generate a list of feasible treatment
strategies for each structure in the Fort Collins bridge network. This may include several
treatment strategies for each structure in each year of the analysis period.
Deighton and Fort Collins staff will review the results of the treatment strategy generation
to determine the reliability of the analysis parameters in clTIMS CT.
Optimize Network
Optimization selects a treatment strategy for each structure based on economic constraints
and the objective function in the analysis. A different set of optimum treatment strategies
may be selected by clTIMS CT for each budget scenario defined in the BMS.
Review Recommended Program
The recommended construction program will be reviewed by Deighton and the Fort Collins
staff against realistic conditions in the field. Findings may result in having to revisit some of
the analysis parameters that were defined in the BMS to "debug" them. The strategy
generation and optimization will be run again following any changes and the results
reviewed again.
Following two iterations, it will be agreed that the BMS is generating realistic maintenance
and rehabilitation recommendations for the available data and the verification of the
analysis and parameters is complete and the system can be released to Fort Collins.
The multi -year, recommended maintenance and rehabilitation program generated by
clTIMS CT can now be used to accomplish a number of different tasks. At an operational
level the output can be used to nominate candidate structures for treatment interventions.
At a planning level, the clTIMS CT output can be used to predict future funding
requirements that will deliver a specified level of service. At a strategic level, clTIMS CT
output can be used to determine the appropriate amount of resources required to
distribute across geographic boundaries to ensure equitable political and social
considerations.
Presentation and Training
The typical training Deighton provides consists of 3 days of specialized on -site training
following the installation of the customized system. The specialized course is intended to
review the operation of clTIMS CT with selected Fort Collins personnel (namely the internal
specialists). The system will be fully functional when delivered and will allow training to be
accomplished using Fort Collins data and a Fort Collins specific recommended
maintenance and rehabilitation program.
dTIi,'1S CT BMS Implernentation 2010-030
Page 5 of 6
Deighton Associates Limited
11 Stanley Court, Unit 1, Whitby, Ontario, Canada L11`1 8P9
Tel: (905) 665-6605 fax: (905) 665-6645
www.deighton.com
A short presentation to upper management is often incorporated as part of the training
session and gives an executive summary of the BMS development and the results of the
analysis.
Final Report
Deighton will deliver a final report that describes the project in detail and summarizes
important findings of the research completed including how the BMS software was set up,
as well as, the conclusions and any recommendations to Fort Collins.
Please review the above proposal and provide comments. We look forward to the
opportunity to working with Fort Collins on this project.
Sincerely,
Robert Piane, P. Eng.
dTIIVIS CT BMS Implementation 2010-030
Page 6 of 6