HomeMy WebLinkAboutCORRESPONDENCE - BID - 7161 COLLEGE AVENUE AND HARMONY ROAD LANDSCAPE AND URBAN DESIGN (3)College & Harmony Landscape and Urban
Design Improvement Project
Bid No. 7167
PRE -BID CONFERENCE
July 27, 2010
9:00 A.M.
281 N. College Ave.
Conference Room A
City of Fort Collins
Engineering Dept.
Capital Improvements Program
a
"•Tw--nr fs
INTRODUCTIONS
• Engineering:
Capital Projects Program:
o Rick Richter- Program Manager
221-6798
o Dean Klingner — Project Manager
218-4962
o Mark Laken - Project Engineer
222-3546
o Craig Farver - Construction Inspector
222-0854
• Purchasing:
— John Stephen -Purchasing Agent
221-6777
• Traffic
— Syl Mireles Traffic Eng. Tech
221-6815
• Consultant Engineers:
— Mike Oberlander w/ Interwest Consulting
970-674-3300
— Jeff Kroeger w/ BHA Design
970-223-7577
ADDENDUM ITEMS
• Several sections of the Specifications were not
included in the original contract. Those omitted
sections are available in Addendum #1 which was
published on Monday, July 26, 2010.
FZ�
7���xcw�x
Highlights from
Specifications
�
t
5
Submittal Procedure
• Submittals reviewed by City and BHA
• . Processing Time: 10 Days per"submittal
• Samples — 2 Samples (rock, paint finish,, colored
concrete, etc.)
• Shop Drawings — 4 copies (metal features)
• Material & Product Certificates — 4 copies (plantings,
irrigation, electrical)
z
General Requirements
• Mobilization
• Construction Control Devices
• Flagging
• Traffic Control Management
• Specialty Signs
• Portable Message Boards
Y S
Northwest Corner
Northeast Corner
Southeast Corner
1 _ 1.i.�-. _ _ Fi'.�. h'<'� ' � . ir'7�i.'!'1.S�ni d�'�..d� n�."._txu.�e+Y�k� ..iSaT•.._._a e+r_.�...,_
Yam'
I HIS
Utilities
12' Pedestrian Pole and Fixture (3 per corner)
• Pedestrian Pole Assembly and installation
• Ornamental Column Lighting and Installation
• Power Cabling and Conduits
• Junction boxes — 2 per corner (1 pullbox, 1 J-box)
• Service Cabinet
• Installation
9
��
2� Y
Site Furnishings — Metal Work
• Ornamental Panel (median)
• Ornamental Panels 6' and 8' lengths
• Installation of bollards (provided by City)
• Median Plinths
• Lighted Ornamental Columns
• Signal pole Ornamental brackets
Now—
�' a
Site Furnishings — Concrete Work
• Standard Grey Concrete Cassion
• Colored Concrete Footing
• Self Leveling Colored Concrete for Planted Pot Bases
• Self Leveling Colored Concrete Median Plinth
• Self Leveling Colored Concrete and Std Grey
Concrete Footing for Lighted Ornamental Column
• Self Leveling Colored Concrete Bases for Pedestrian
Light Pole
• Concrete Planter Pots Complete
31 �}f m r
Plant Material
• Inspected by City of Fort Collins Forestry
• Includes Common Canopy Trees, Ornamental Trees,
Deciduous Shrubs, Evergreen Shrubs, Ornamental
Grasses, and Perennials
• Warranty for 2 years
• Maintenance thru final completion date.
• Mowing, pruning weeding and all other maintenance
operations will be taken over by City or adjacent
property owner at Final Acceptance
7m,
� x
Demolition, Edger, Mulch, Sod and Misc.
• Landscape Demolition — there are no tree removals,
only shrubs, and minor planting materials
• Stacked Boulder Retaining Wall (SE corner) —
includes furnishing materials and placing in
accordance with plans — equal proportions of various
specified boulder stones will be used
• Soil Amendment — 3 CY/1000SF = throughout project
• Fine Grading / Shaping — covers all necessary grading
that is necessary to existing conditions that are
furnished by City from the roadway project
ti
iF
''v!_
s,E•p��"'s-
�� t.--- ✓ �, .MF :ear .€'"`t
k� vw
4+
{ p F
Demolition, Edger, Mulch, Sod and Misc.
• Fescue Sod
• Steel Edger
• Re -set exisitng Buff Sandstone at SE corner
• 12" deep Planters Mix at 4 corners
• Type 1 washed Cobble mulch — Y-6" Tan
• Type 2 Washed Cobble mulch — 6"-12" Tan
• Type 3 Cobble Mulch 6"-12" —'pink-white-black
• Type 1 3" deep Shredded Mulch — City's recycled material —
transport and install cost only
• Type 2 3" deep Shredded mulch — Cedar
• Weed Barrier Fabric
y 5
. 3% T •i
`'36
r:
Fort
ATTENDANCE
. Please be sure to register
• BID OPENING
— When: August 10, 2010 @ 3:00 P.M. (Our Clock)
— Where: 215 North Mason Street (2nd Floor)
CHIP RASE MAP
firm
all
ADDENDUM #1
• An Addendum for the project was posted online on
Monday, July 26, 2010 to add additional specifications.
Thanks For Attending!
• Any Questions or concerns can be addressed to:
— Dean Klingner
• Office: (970) 221-6511
• Cell: (970) 218-4962
• Email: dklingner@fcgov.com
— Mark Laken
• Office: (970) 221-6605
• Cell: (970) 222-3546
• Email: mlaken(Jcgov.com
IMPORTANT CONTRACT DATES:
• AWARD CONTRACT
o Bid Opening August 10, 2010 at 3:00 PM
• PRE -CONSTRUCTION MEETING
o Mandatory Meeting Prior to Start of Construction
o Date to be determined after contract is awarded
• CONSTRUCTION START DATE
o Approximately September 1, 2010
o Calendar Day Contract
• SUBTANTIAL COMPLETION - 75 Calendar days
• FINAL COMPLETION -14 Days after Substantial Completion
CONTRACT DOCUMENTS FOR BID # 7127:
• PLAN SHEETS
- Prepared by BHA Design, Hines Irrigation, ESC Engineering and Interwest
Consulting Group
- Sheets 1 thru 28
• SPECIFICATION BOOK
- Prepared by BHA and City of Fort Collins Purchasing
• ADDEDNDUM #1
- Several Additional Specifications that were omitted from original contract
v---i
Harmony and Golloge. Comer Features, ,—, t- I
SUMMARY OF WORK
College Harmony Landscape and Urban Design
Improvements:
• Install Landscape Materials
• Install Irrigation Systems
• Install Columns, Plinths, Fence Panels, Planters, Lights
Install Stacked Boulder Wall
• Install Electrical System
�x �
Bidder's Qualifications
SECTION 00520
STATEMENT 03 BIDDER'S QUALI�ICATLONS
All questions must be answered and the data
given must be clear and
comprehensive. This statement must be notarized.
If necessary, questions may
be answered on separate attached sheets. The Bidder
may sab...et any additional
_..^.fo nat'_Gn he deaires.
f v
x �.,.
LT
SUMMARY OF WORK
• Survey
— Provided by City of Fort Collins
— Engineering Department Survey Staff
— 48 hour written request for survey
• Testing
— Provided by City of Fort Collins
— Thru contract with CTL Thompson
— Contractor will setup testing as required
Traffic Control
• Traffic Control — Responsibility of Contractor
— Single lane closures in each direction of traffic
— Review upcoming lane closure needs at each
Weekly Progress Meeting
Coordinate with CDOT with College Ave lane
closures requires advanced City notification —
Traffic control plans submitted to City 10 days
before closure
HIGHLIGHTS FROM GENERAL CONDITIONS AND
GENERAL REQ'S:
SUPERINTENDENTS:
o The General Contractor SHALL employ a full time Superintendent whose sole
responsibility is to monitor anff coordinate all facets of the work
LIQUIDATED DAMAGES:
o SUBSTANIAL COMPLETION:
o The contractor will need to meet substantial completion requirements within 75 days of
construction start date. Substantial completion shall be defined as the completion of all
earthwork, rock work, concrete work, metal work, landscape planting material, Irrigation
and electrical systems as required for this project. If the Contractor goes past the 75
calendar days for substantial completion, damages In the amount of One Thousand
Eighty Six Dollars ($1,066.00) for each calendar day will be assessed.
o FINAL ACCEPTANCE:
Final acceptance will be met within 14 calendar days after substantial completion. Final
completion is defined as all punchlist items and work that is defined in the contract.
Liquidated Is
in the amount of Five Hundred Dollars ($500.00) per calendar day will
be charged if this schedule has not been met.
Y
HIGHLIGHTS FROM GENERAL CONDITIONS AND
GENERAL REQ'S:
• CONSTRUCTION HOURS:
o Restricted Hours of Operation
• 9:00 A.M. thru 3:30 P.M. - Monday thru
Friday.
■ Given the scope of the proposed
improvements, the City will permit extended
working hours on a case by case basis
— Extended Hours requests must be made
in writing
HIGHLIGHTS FROM GENERAL CONDITIONS AND
GENERAL REQ'S:
• PROJECT MEETINGS:
o Onsite meeting in the field, time to be determined.
o Schedules shall be updated weekly. The Contractor
may be required to submit additional schedules
depending on the progress of the project.
• HAUL ROUTES:
o Arterial and Collector streets only. Contractor will
not be allowed to use residential streets to access
the site with trucks hauling materials.
HIGHLIGHTS FROM GENERAL CONDITIONS AND GENERAL
REQ'S:
• SITE CLEAN-UP:
o The construction work shall be kept and accomplished in a
neat, clean and orderly fashion.
o Street sweeping may be required in order to minimize
tracking and meet EPA storm water quality requirements.
o Dust control will be required as necessary.
Erosion Control - SWMP
• Contractor will transfer the existing SWMP from Lafarge — NA for the
portions of the worksite that are covered in the existing SWMP through the
Colorado Dept of Public Health and Environment (CDPHE)
• Erosion Control Devices are currently installed by Lafarge per the approved
SWMP.
• It will be the responsibility of the awarded contractor to maintain and repair
the existing erosion control devices.
• It will be the responsibility of the awarded contractor to do weekly SWMP
inspections and turn original signature copies of the SWMP Inspection
Report to the City.
• This work is incidental to the cost of the project.
b