Loading...
HomeMy WebLinkAboutBID - 7080 EPIC SOLAR POOL PROJECTCity of F6rt Collins �Purc�hasi�ng� ADDENDUM No. 1 SPECIFICATIONS AND CONTRACT DOCUMENTS Description of RFP 7080: EPIC Solar Pool Project OPENING DATE: 3:00 P.M. (Our Clock) November 19, 2009 Financial Services Purchasing Division 215 N. Mason St. 2nd Floor PO Box 580 Fort Collins, CO 80522 970.221.6775 970.221.6707 fcgov. com/purchasing To all prospective bidders under the specifications and contract documents described above, the following changes are hereby made. CHANGE: The bid opening date has been changed to November 19, 2009. Pre -proposal Questions and Supplemental Information 1.) Question: Is the EPIC roof under warranty? Answer. Yes. The awarded solar collection system proposer/contractor must maintain the City's manufacturers warranty intact. Roofing Contractor information is as follows: Contact — Terry Canchola @ Independent Roofing Specialists Telephone 1.303.426.8575 Cellular 1.303.901.1117 2.) Question: How much insulation does the roof have on it? Answer. 5 inches. See roof cross section attached. 3.) Structural Engineer's letter pertaining to additional roof loading capacity. (Weeks & Associates Engineering). See attached. 4.) Expanded City project manager's comment at pre -proposal meeting relative to protection of existing systems: The proposer/contractor will be responsible for protection of all interior and exterior components of the building that are adjacent to the Work such as, but not limited to; structural components, all other building constructed systems, recreational facilities systems and appurtenances, and equipment. Any systems and/or equipment damaged as a result of the Work will be replaced at the contractor's expense. Contractor will coordinate any temporary protection methods with the City's project representative and the City's on -site building manager. Any disturbance of the building normal operations must be pre -approved by the City's project representative. N UPPER LEVEL I MjgH-fflICAL ROOM PLANS jD N LOWER LEVEL MECHANICAL ROOM PLANS These as -bum drawings have been p""""'d Old by others. P.'t' On the b"s" of 111i'll and N,H .1h, e) w responsible this d . . . ent as a",LOt. h"h h. b. 1, t d —."N� IN, p t -WATCH LINE a Fla-stirgs+ChWtta Architects, Planners - V�D' S014h %rrifixI A— St LWILMW� 63105 314-863-6717 FORT COLLINS �E.=. 3 OW A ELFANB— INC. . ... .... - " a INC NATATORIUM AND ICE ARENA 4-- M--L p KEY PLAN M-8 EXHIBIT GC -A to General .Conditions of the Construction Contract Between OWNER and CONTRACTOR DISPUTE RESOLUTION ACRMIEINT OWNER and CONTRACTOR hereby agree that Article 16 of the General Conditions of the Construction Contract between OWNER and CONTRACTOR is amended to include the. followingirgeement of the parties: 16.1. All claims, disputes and other matters in question between OWNER and CONTRACTOR arising out of or relating to the Contract Documents or the breach. thereof (except for claims which have been waived by the making or acceptance of final payment as provided by paragraph 14.15) will be decided by arbitration in accordance with the Construction industry Arbitration Rules of the American Arbitration Association then obtaining, subject to the limitations of the Article 16. This agreement so to arbitrate and any other agreement or consent to arbitrate entered into in accordance herewith as provided in this Article; 16 will be specifically enforceable under the prevailing law of any court having jurisdiction 16.2. No demand for arbitration of any claim, dispute or other matter that is required to be referred to M4GDTEBR initially for decision in accordance with paragraph 9.11 will bcmade until the earlier of (a) the date on which ENGINEER has rendered a written decision or (b) the thirty-first day after the parties have presented their evidence to ENGiNEER if a written decision has.not been rendered by ENGINEER before that date No demand for arbitration of any such claim, dispute or other matter will be made later than thirty days after the date on which ENGINEER has rendered a written decision in respect thereof in accordance with paragraph 9.11; and the failure to demand arbitration within said thirty days period will result in ENGRTEER's decision being final and binding upon OWNER and CONTRACTOR If ENGINEER renders a decision alter arbitration proceedings have been initiated, such decision may entered as.evidence but will not supersede the arbitration proceedings, except where the decision is acceptable to the parties concerned. No demand Cur arbitration of any written decision of ENGINEER rendered in accordance with paragraph 9.10 will be made later than ten days after the, party making such demand has delivered written notice of intention to appeal as.provided in paragraph 9.10. 16.3. Notice of the demand for arbitration will be filed in writing with the other party to the Agreement and with the American Arbitration Association, and a -copy will be sent to ENGINEER for information The demand for arbitration will be made within the thirty -day or ten -Jay period specified in paragraph 16.2 as applicable, and in all other cases within a reasonable time after the claim, dispute or other matter in question has arisen, and in no event shall any such demand be made after the date when institution of legal or equitable proceedings based on such claim, dispute or other matter in question would be barred by the applicable statute of limitations. EXI)C: GENERAL CONDITIONS 1910.5 (,1990E(irion) w/ CITY OF FORT COLLINS MODIFICATIONS (RFV 9/99) 16.4. Except as provided in paragraph 165 below, no arbitration arising out of or relating to the Contract Documents shall include by consolidation, joinder or in any other manner any other person or entity (including ENGIr TEER- ENGINEER's Consultant and the officers, directors, agents, employees or consultants of any of them) who is not a party to this contract unless: 16.4.1. the inclusion of such other person or entity is necessary if complete relief is to be afforded among those who are already parties to the arbitration, and 16.4.2. such other person or entity is substantially involved in a question of law or fact which is common to those who are already parties to. the arbitration and which will arise in such proceedings, and 16.4.3. the written consent of the other person or entity sought to be included and of OWNER and CONTRACTOR has been obtained for such inclusion, which consent shall make specific reference to this paragraph; but no such consent shall constitute consent to arbitration of any dispute not specifically described in such consent or to arbitration with any party not specifically identified in such consent. 16.5. Notwithstanding paragraph 16.4, if a claim, dispute or other matter in question between 01UNER and CONTRACTOR involves the Work of a Subcontractor, either OWNER or CONTRACTOR may join such Subcontractor as a party to the nrbitmiion between OWNER and CONTRACTOR hereunder. CONTRACTOR shall include in all subcontracts required by paragraph 6:11 a specific provision whereby the Subcontractor consents to being joined in an arbitration between OWNER and CONTRACTOR involving the Work of such Subcontractor. Nothing in this paragraph 16.5 nor in the provision of such subcontract consenting to joinder shall create any claim, right or cause of action in favor of Subcontractor and against OWNER, ENGINEER or ENGINEER's Consultants that does not otherwise exist. 16.6. The award rendered by the arbitrators will be final, judgment may be entered upon it in any court having jurisdiction thereof; and it will not be subject to modification or appeal. I&T OWNER and CONTRACTOR agree that they shall first submit any and all unsettled claims, counterclaims, disputes and other matters. in question between them arising out of or relating to the Contract Documents, or the breach thereof ("disputes"), to mediation by the American Arbitration Association under the Construction industry, Mediation Rules of the American Arbitration Association prior to either of them initiating against the other a demand for arbitration pursuant to paragraphs 16.1 through 16.6, unless delay in initiating arbitration would irrevocably prejudice one of the parties. The respective thirty and ten day time limits within which to file a demand for arbitration as provided in paragraphs 16.2 and 16.3 above shall be suspended with respect to a dispute submitted to mediation within those same applicable time limits and shall remain suspended until ten days after the termination of the mediation. The mediator of.any dispute submitted to mediation under this Agreement shall not serve as arbitrator of such dispute unless otherwise agreed. GC -Al EJCDC GENERAL CONDITIONS 1910-3 (1990 E(liliai) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/94) GC -A 1 SE SECTION 00800 SUPPLEMENTARY CONDITIONS SECTION 00800 SUPPLEMENTARY CONDITIONS Conditions of the Contract These Supplementary Conditions amend or supplement the General Conditions of the Construction Contract (EJCDC General Conditions 1910-8, 1990 edition with City of Fort Collins modifications) and other provisions of the Contract Documents as indicated below. SC-4.2 Subsurface and Physical Conditions: A. Add the following language to paragraph 4.2.1 of the General Conditions. 4.2.1.1.1 The following report(s) of exploration and tests of subsurface conditions at the site of the Work: Contractor may rely upon the accuracy of the technical data contained in the geotechnical documents, but not upon nontechnical data, interpretations or opinions contained therein or upon the completeness of any information in the report. B. 4.2.1.2.1 No drawing of physical conditions in or relating to existing surface or subsurface structures (except Underground Facilities referred to in Paragraph 4.3) which are at or contiguous to the site have been utilized by the Engineer in preparation of the Contract Documents, except the following: SC-5.4.8 Limits of Liability A. Add the following language at the end of paragraph 5.4.8. The limits of liability for the insurance required by the paragraph numbers of the General Conditions listed below are as follows: 5.4.1 and 5.4.2 Coverage A - Statutory Limits Coverage B - $100,0001$100,0001$500,000 5.4.3 and 5.4.5 Commercial General Liability policy will have limits of $1,000,000 combined single limits (CSL). This policy will include coverage for Explosion, Collapse, and Underground coverage unless waived by the Owner. 5.4.6 The Comprehensive Automobile Liability Insurance policy will have limits of $1,000,000 combined single limits (CSL). Section 00800 Page 1 5.4.9 This policy will include completed operations coverage/product liability coverage with limits of $1,000,000 combined single limits (CSL). SC-8.10 OWNER's Project Manager A. Add the following language to ARTICLE 8: 8.10. The OWNER will provide a Project Manager. The CONTRACTOR shall direct all questions concerning Contract interpretation, Change Orders, and other requests for clarification or instruction to the Project Manager. 8.10.1 Authority: The Project Manager will be the OWNER's representative during the construction of the project. The Project Manager shall have the authority set forth in the OWNER's Capital Project Procedures Manual. The Project Manager shall have the authority to reject work and materials whenever such rejection may be necessary to ensure the proper performance of the Work in accordance with the Contract Documents. 8.10.2 Duties and. Responsibilities: The Project Manager will make periodic visits to the project site to observe the progress and quality of the Work and to determine, in general, if the Work is proceeding in accordance with the Contract Documents. The Project Manager shall -not be required to make comprehensive or continuous inspections to check the progress or quality of the Work. The Project Manager shall not be responsible for construction means, methods, techniques, sequences, or procedures, or for safety precautions or programs in connection with the Work, or for any failure of the Contractor to comply with laws and regulation applicable to the performance or furnishing of the Work. Visits and observations made by the Project Manager shall not relieve the CONTRACTOR of his obligation to conduct comprehensive inspections of the Work, to furnish materials' and perform acceptable Work, and to provide adequate safety precautions in conformance with the Contract Documents. The Project Manager shall at all times have access to the Work. The CONTRACTOR shall provide facilities for such access so the Project Manager may perform his or her functions under the Contract Documents. 8.10.3 One or more Resident Construction Inspector(s) (RCI) may be assigned to assist the Project Manager in providing observation of the Work, to determine whether or not the Work is proceeding according to the construction documents. CONTRACTOR will receive written notification from the OWNER of any RCI assignments. The RCI shall not supervise, direct or have control or authority over, nor be responsible for, CONTRACTOR's means, methods, techniques, sequences or procedures of construction or the safety precautions and programs incident thereto, or for any failure of CONTRACTOR to comply with Laws and Regulations applicable to the furnishing or performance of the Work. The RCI will not be responsible for CONTRACTOR's failure to perform or furnish the Work in accordance with the Contract Documents. The RCI's dealings in matters pertaining to the on -site work will be to keep the Project Manager properly apprised about such matters. 8.10.4 Communications: All instructions, approvals, and decisions of the Project Manager shall be in writing. The CONTRACTOR may not rely on instructions, approvals, or decisions of the Project Manager until the same are reduced to writing. SC-12.3 Add the following language to the end of paragraph 12.3. Contractor will include in the project schedule days lost due to abnormal weather conditions. Must be documented and approved by City',s Project Representative. SC-13.12 Correction Period: 13.12. llf within one year after the date of Substantial Completion or such longer period of time as may be prescribed by Laws or Regulations or by the terms of any applicable special guarantee required by the Contract Documents or by any specific provision of the Contract Documents, an Work is found to be defective, CONTRACTOR shall promptly, without cost to OWNER and in accordance with OWNER's written instructions ... 00800-3 SECTION 00900 ADDENDA, MODIFICATIONS AND PAYMENT 00950Contract Change Order 00960Application for Payment SECTION 00950 CHANGE ORDER NO. PROJECT TITLE: CONTRACTOR: PROJECT NUMBER: DESCRIPTION: 1. Reason for change: 2. Description of Change: 3. Change in Contract Cost 4. Change in Contract Time: ORIGINAL CONTRACT COST $ .00 TOTAL APPROVED CHANGE ORDER 0.00 TOTAL PENDING CHANGE ORDER 0.00 TOTAL THIS CHANGE ORDER 0.00 TOTAL % OF THIS CHANGE ORDER TOTAL C.O.% OF ORIGNINAL CONTRACT ADJUSTED CONTRACT COST $ 0.00 (Assuming all change orders approved) ACCEPTED BY: DATE: Contractor's Representative ACCEPTED BY: Project Manager - REVIEWED BY: Title: APPROVED BY: Title:, APPROVED BY: Purchasing Agent over $30,000 cc: City Clerk Contractor Project File Architect Engineer Purchasing DATE: DATE: DATE: DATE: Section 00950 Page 1 Section 00960 APPLICATION FOR PAYMENT PROJECT: PO# PAY ESTIMATE NO: DATE: CONTRACTOR: ADDRESS: CONTRACT FOR: PARTIAL TO. The undersigned Contractor certifies that to the best of his knowledge, information and belief the work covered by this application for Payment has been completed in accordance with the Contract Documents, that all accounts have been paid by him for Work for which previous Certificates for Payment were issued and payments received, in this current payment shown herein is now due. CONTRACTOR: By: FINAL TO In accordance with the Contract Documents, based on site observations and the data comprising the above application, the Architects Certifies to the Owner, that the Work has progressed to the point indicated; that the best of his knowledge, information and belief, the quality of the Work is in accordance with the Contract Documents, and that the Contractor is entitled to payment of the AMOUNT CERTIFIED. ENGINEER: By: Date: Date: Application is made for Payment, as shown below, in connection with the Contract. Schedule of Values is attached. The present status of the account for this Contract is as follows ORIGINAL CONTRACT AMOUNT APPROVED CHANGE ORDERS TO DATE ADJUSTED CONTRACT AMOUNT TOTAL WORK COMPLETED AND MATERIALS USED RETAINAGE (10% OF TOTAL) TOTAL EARNED LESS RETAINAGE LIQUIDATED DAMAGES WITHHELD TOTAL EARNED LESS LIQUIDATED DAMAGES LESS PREVIOUS PAYMENTS CURRENT PAYMENT DUE APPROVED BY: (Title) cc: Accounting City Clerk Contractor Engineer Project File DATE: Section 00960 Page 1 WORK CHANGE DIRECTIVE INSTRUCTIONS A. GENERAL INFORMATION This document was developed for use in situations involving changes in the Work which, if not processed expeditiously, might delay the Project. These changes are often initiated in (lie field and may affect the Contract Price or the Contract 'times. This is not a Change Order, but only a directive to proceed Nvith Work that may be included in a subsequent Change Order. For supplemental instructions and minor changes not involving a change in. the Contract Price or the Contract Times a Field Order should be used. B. COMPLETING THE WORK CHANGE DIRECTIVE FORM Engineer initiates the form, including a description of the items involved and attachments. Based on conversations between Engineer and Contractor, Engineer completes the following: METHOD OF DETERMINiNG CHANGE, IF ANY, iN CONTRACT PRICE: Mark the method to be used in detennining the final cost of Work involved and the estimated net effect on the Contract Price. If the change involves an increase in the Contract Price and the estimated amount is approached before the additional or changed Work is completed, another Work Change Directive must be issued to change the estimated price or Contractor may stop the changed Work when. the estimated time is reached. Ifthe Work Change Directive is not likely°to change the Contract Price, the space for estimated increase (decrease) should be marked "Not Applicable". Once Engineer has completed and signed the form, all copies should be sent to Owner for authorization because Engineer alone does nol have authority to authorize changes in Price or Tittles. Once authorized by Owner, a copy should be sent by Engineer to Contractor. Price and Times may only be changed by Change Order signed by Owner and Contractor with Engineer's recommendation. Paragraph 10.03,A.2 of the General Conditions requires that a Change Order be initiated and processed to cover any undisputed sum or amount of time for Work actually performed pursuant to this Work Change Directive. Once the Work covered by'thi.s directive is completed or final cost and times are determined, Contractor should submit documentation for inclusion in a Change Order. THIS IS A DIRECTIVE TO PROCEED WITH A CHANGE THAT MAY AFI7ECT THE CONTRACT PRICE OR CONTRACT TIMES. A CHANGE ORDER, IF ANY, SHOULD BE CONSiDEMD PROMPTLY. Section 00970 Page 1 No Text WORK CHANGE DIRECTIVE No. DATE OF ISSUANCE EFFECTIVE DATE OWNER CONTRACTOR Contract: Project: OWNER's Contract No. ENGINEER's Project No. You are directed to proceed promptly with the following change(s): Description: Purpose of Work Change Directive: Attachments: (List documents supporting change) If OWNER or CONTRACTOR believe that the above change has affected Contract Price any Claim for a Change Order based thereon will involve one or more of the following methods as defined in the Contract Documents. Method of determining change in Contract Price: Unit Prices Lump Sum Cost of the Work Estimated increase (decrease) in Contract Price: Estimated increase (decrease) in Contract $ Times: If the change involves an increase, the estimated Substantial Completion: days; amount is not to be exceeded without further Ready for final payment: days. authorization. RECOMMENDED: ENGINEER AUTHORIZED: OWNER, By: By: EJCDC No. 191068-F (19%Edition) Ptep oed by the Engineers Mint Cootmi Doownente Conimittee'and endorsed by The Associated Geaenl Contractors o(America and the Constntetion Specifitmio" hwhde. Section 00970 Page 2 IVAdvancement ofC of Conshvctlon Technology REQUEST FOR INTERPRETATION Project: R.F.I. Number: From: To: Date: A/E Project Number: Re: Contract For: Specification Section: Paragraph: Drawing Reference: Detail: Request: Signed by: Date: Response: ❑ Attachments Response From: To: Date Rec'd: Date RetDd: Signed by: Date: Copies: ❑ Owner ❑ Consultants ❑ ❑ ❑ ❑ []File Copyright 1994, Construction Specifications Mitutc, Page of July 1994 99 Canal Center Plaza, Suite 300 Alexandria, VA 22314 CS] Form 13.2A Section 00970 Page 3 IVofcAdvancement of Consbuetton Technology CLARIFICATION NOTICE Project: Clarification Notice Number: From: To: Date: A/E Project Number: Re: ConiractFor: This Clarification Notice is issued for the purpose of clarifying the Contract Documents based on an interpretation reasonably inferable from the Contract Documents, and therefore has no effect on the Contract Sum or Contract Time. Proceeding with Work in accordance with this Clarification Notice indicates acceptance with no change in the Contract Sum or Contract Time. Specification Section: Paragraph: Drawing Reference: Detail: Description: ❑ Attachments Signed by: Date: Copies: ❑ owner ❑ Consultants 0-0-0- Copyright 1994, Construction Specifications Institute, Page of 99 Canal Center Plaza, Suite 300 Alexandria, VA 22314 ❑ ❑ File July 1994 CSI Form 13.3A J Section 00970 Page 4 Project: To: Advancement ofC al consrn/eNon Technology FIELD ORDER Field Order Number: From: Date: A/E Project Number: Re: Contract For You are hereby directed to execute promptly this Field Order which interprets the Contract Documents or orders minor changes in the Work without change in Contract Sum or Contract Time. If you consider that a change in Contract Sum or Contract Time is required, submit a Change Order Request to the A/E immediately and prior to proceeding with this Work. Specification Section: Paragraph: Drawing Reference: Detail: Description of Interpretation or Change: ❑ Attachments Signed by: Date: Copies: Cl Owner ❑ Consultants ❑ ❑ ❑ ❑ []File Copyright 1994, Construction Specification Institute, Page of July 1994 99 Canal Center Plaza, Suite 300 Alexandria, VA 22314 CSD Form 13.4A VlIIGVVI/VV 5 e n/sn m. .f'u.ie.ic mr, env ma Z_ I,. twee, Z nAN 'LllLL9 i`� � I gK�i$ ex " wvjm INDOOR WADING POOL AND THERAPEUTIC POOL SYSTEM SCHEMATICS °) as , � tn� MAIN DRAIN DETAIL Q 0 2 r/!�};ID Y� .... ......... ... . „e ., ..«„ (A«or.e ,u�u,•/..n �^�.. «,�s..« nu k��� ,w, wwun", n« MAIN POOL AUTOMATIC LEVEL CONTROL NO $CALE . to Part, on tna basis or teee-p co .Pnee na rurotsnea by otne s. The Archt test (En'l near) Nnt 4.« eseon,ime rot any erro or Dint„ion, .m <n na.e heen tncerooratee i�co this aocmnent a smut` MAIN POOL FILTER SYSTEM SCHEMATIC IOIES: .r n,— a r��m �w uoore .xc sue (tiw .aa. Ar,n„ .era ,ue ,om rv, '°" cmrx tart Io mwrt«. y;. ar moo) FILL FITTING DETAIL NO CALE —7 r m„ «, r. r�. AUTOMATIC SURFACE SKIMMER DETAIL POOL CHEMICAL FEED SCHEMATIC NO CALA INLET FITTING DETAIL NO SCILA City Financial Services o 1 Purchasing Division N. Mason St. 2nd Floor F6rt Collins Box 580 Fo215 Fort Collins, CO 80522 �Purchasinc 970.221.6775 970.221.6707 kgov. com/purchasing REQUEST FOR PROPOSAL 7080 EPIC Solar Pool Project The City of Fort Collins is requesting proposals from qualified contractors for the installation of thermal solar heating panels to heat the main pool at EPIC recreation facility. Written proposals, four (4) will be received at the City of Fort Collins' Purchasing Division, 215 North Mason St., 2nd floor, Fort Collins, Colorado 80524. Proposals will be received before 3:00 p.m. (our clock), November 17, 2009. Proposal No. 7080. If delivered, they are to be sent to 215 North Mason Street, 2"d Floor, Fort Collins, Colorado 80524. If mailed, the address is P.O. Box 580, Fort Collins, 80522-0580. A pre -bid conference will beheld at 2:00 pm. on November 3, 2009 at the site, 1801 Riverside Avenue, Fort Collins, CO 80525. Please meet in the lobby. Questions concerning the scope of the project should be directed to Project Manager Steve Seefeld, (970)221-6227, sseefeld(@fcgov.com. Questions regarding bid submittal or process should be directed to John Stephen, CPPO, LEED-AP, Senior Buyer, (970)221-6777, jstephen(a�fcgov.com. A copy of the Proposal may be obtained as follows: 1. Download the Proposal/Bid from the BuySpeed Webpage, www.fcgov.com/eprocurement 2. Come by Purchasing at 215 North Mason St., 2nd floor, Fort Collins, and request a copy of the Bid. The City of Fort Collins is subject to public information laws, which permit access to most records and documents. Proprietary information in your response must be clearly identified and will be protected to the extent legally permissible. Proposals may not be marked `Proprietary' in their entirety. Information considered proprietary is limited to material treated as confidential in the normal conduct of business, trade secrets, discount information, and individual product or service pricing. Summary price information may not be designated as proprietary as such information may be carried forward into other public documents. All provisions of any contract resulting from this request for proposal will be public information. Sales Prohibited/Conflict of Interest: No officer, employee, or member of City Council, shall have a financial interest in the sale to the City of any real or personal property, equipment, material, supplies or services where such officer or employee exercises directly or indirectly any decision - making authority concerning such sale or any supervisory authority over the services to be rendered. This rule also applies to subcontracts with the City. Soliciting or accepting any gift, gratuity favor, entertainment, kickback or any items of monetary value from any person who has or is seeking to do business with the City of Fort Collins is prohibited. Collusive or sham proposals: Any proposal deemed to be collusive or a sham proposal will be rejected and reported to authorities as such. Your authorized signature of this proposal assures that such proposal is genuine and is not a collusive or sham proposal. The City of Fort Collins reserves the right to reject any and all proposals and to waive any irregularities or informalities. Sincerely, James B. O'Neill II, CPPO, FNIGP Director of Purchasing & Frisk Management where renewal is a way of life Solar Thermal Heating System -City of Fort Collins EPIC Pool 1801 Riverside Avenue, Fort Collins, CO 80525 The City of Fort Collins is requesting proposals from qualified contractors for the installation of thermal solar heating panels to heat the main pool at EPIC recreation facility. Definitions The terms "contractor" and "proposer' shall be synonymous in this document (RFP). The body of text in this request speaks directly to the proposer/contractor, including requirements for any specification or direction, unless otherwise specifically noted. AHJ - Authorities Having Jurisdiction. COSEIA - Colorado Solar Energy Industries Association NABCEP - North American Board of Certified Energy Practitioners 1. Building Overview EPIC recreation facility is a multiuse indoor swimming pool, indoor ice rink facility of 97,960 sq. ft. One wing of the building contains a wader pool, spa, and main pool. The main pool is 75' wide by 171 ft long (- 12,830 sq ft) and holds 580,000 gallons of water. The facility runs year round with a two week shut down period " in late August of each year. The design pool temperature is 82 deg. F. 2. Project Overview The solar heating system must be designed to address the technical and facility -use requirements of the project. The system must integrate into an existing multi -use facility to provide energy savings and minimal increase of the existing maintenance requirements of the facility. Scheduling of installation of the system must be co -coordinated to minimize disturbance of public use of the facility. The City's expectation of this system is that it provides as great a reduction of the existing pool heating load as possible given the following constraints: 1. The proposed budget for the project, 2. The available roof space, 3. The current available technologies. The existing current instantaneous heating demand of the pool has been calculated at 600,000 BTU/HR. The solar heating system is to be configured to maximize performance during the winter months as well as the spring and fall. The summer season does not require a large amount of heating. An option to expand the system to preheat domestic hot water shall be included in your proposal. 2/9/00 3. Proiect Approach The contractor will develop a design for the system in conjunction with the City of Fort Collins, materials suppliers and project engineers. The significant issue of the project involves the design of a rack system to be mounted on the existing roof structure. The two options are to provide a ballasted rack system or a system that is structurally attached to the existing metal truss system. Either system would be required to satisfy the demands of a certified independent structural engineer. Contractor will submit the final engineered design to the city of Fort Collins for approval. The integration of the plumbing and heating of the pool equipment room will be co - coordinated with the City project representative and the on -site facilities manager. The control logic of the pool heater will be adjusted to work in conjunction with the solar heating system. The proposer/contractor must outline their approach to the project in the submitted proposal. 4. Existing Site Conditions The following is a list of a few key components of the existing infrastructure at EPIC that must be addressed in satisfying the needs of the RFP. Tell us what you would do to address these elements, based upon your proposed design, in the scope of your proposal. • Roof - The existing roof is an EPDM membrane covered with protective fabric and a layer of gravel and stones. • Roof structure - A steel truss system supports the roof.. This is accessed from below via the surface of the ice rink. • Controls - The pool heating system is currently controlled by a Johnson Controls system. Maintenance staff will facilitate integration of the solar heating system. • Cooling Tower- The existing cooling tower will serve as the heat dump circuit for periods of stagnation or pool maintenance. 5. Contractor Submittals, Level of Experience, and Other Requirements Relevant Experience Contractor must demonstrate sufficient knowledge and experience in all of the building systems involved with the project including solar installation, metal fabrication, structural systems, roofing systems, mechanical and plumbing concepts and major systems equipment controls. The scale of the project must be within the capabilities of contractor. A team of professionals with required skills to complete the project must be outlined as proposer's project team in the proposal. Proiect Team and Experience Verification Contractor must be qualified in the installation of solar water heating systems and must be a licensed contractor in the City of Fort Collins, or have reciprocity in this jurisdiction. The City prefers a COSEIA or NABCEP approved solar thermal installer and please submit certifications with the proposal. Contractor will obtain all necessary permits for the project. List all members of your project team with any appropriate certifications. List all licensed contractors and/or subcontractors anticipated to be used on the project. All contractors/subcontractors must be licensed to do business in this 2/9/00 jurisdiction and must obtain all necessary permits for the work from Authorities Having Jurisdiction. • List all equipment manufacturers and model numbers of equipment to be used on the project. The following is required, but not necessarily limited to, all major equipment - collectors, mounting hardware, heat exchanger, pumps, controls, monitoring equipment, valves, pipe insulation and jacketing. • Structural Engineering — Show all attachments and structural loading in diagrammatic form with calculations. • Mechanical Engineering- Show all proposed mechanical and plumbing connections in diagrammatic form and functional control schematic. • Local, state laws and ordinances, as they pertain to solar hot water systems shall be strictly followed or a variance must be obtained from AHJ's. • Contractor must have completed three (3) similar projects of similar size and scope within the past five (5) years. • OSHA safety standards will be observed during construction. 6. Hourly rates and Guaranteed Maximum Price Include in your proposal hourly rates for your team members and a Guaranteed Maximum Price which includes all design, structural engineering, and supply of all materials, complete installation, training and any permits. 7. Payment and Performance Bonds Awarded contractor must submit payment and performance bonds per Section 00600. 8. Liquidated Damages Liquidated damages are $300.00 for Substantial Completion and $100.00 Final Completion 2/9/00 SCOPE OF WORK The scope of your proposal shall include the following specifications as minimum requirements: Solar Water Heating Part 1-General 1.01 Description A. The solar water heating system shall be designed for flow through a closed loop system with 50% propylene glycol solution for freeze protection. B. There shall be solar collectors mounted on the roof surface above the ice rink as noted on provided drawings. The piping shall run from the collectors along roof surface and down wall to the mechanical room. C. Refer to the site plans, floor plans and details for locations of equipment and piping. 1.02 Scope of Work Work to be completed by the contractor includes but is not limited to: A. Provides and install solar collector loop including the solar collectors, heat exchanger, pumps and all associated piping in accordance with manufacturer's instructions, and specifications provided in this document B. Mounting structure is to consist of stainless steel, galvanized steel or aluminum rack material approved for mounting collectors. C. Provide and install pool -heating system as identified in schematic drawings. D. Install and connect all control systems related to solar work including BTU monitoring and differential temperature lines. Provide line voltage and low voltage wiring of pumps and controls. Run wiring for pumps and valves to location of solar controller. City of Fort Collins shall provide a dedicated 20-amp circuit. E. Coordinate with City of Fort Collins maintenance department, HVAC division, for requirements related to solar work. F. Installing, insulating, and testing of piping shall be provided by solar contractor. G. Provide 2 years of service and maintenance upon completion of system and training for City staff for system operation and service. H. Provide a two (2) year warranty on the complete system, including materials, equipment, and labor. I. Provide a five (5) year minimum warranty on solar collector panels and associated hardware. J. Provide comprehensive training for City maintenance staff on system operation, service and maintenance. Training shall be not less than four (4) hours unless approved by City project representative. 1.03 Site Planning A. Prior to any roof penetrations or drilling, all utilities shall be located and flagged by the City of Fort Collins maintenance staff. 2/9/00 B. Installation of equipment and pipe runs shall be coordinated with City of Fort Collins maintenance department, HVAC division. Pipe run locations will be identified during the preconstruction conference. C. All work shall be coordinated to create a minimal disturbance to the public use of the facility. Work shall be performed only in hours approved by the City of Fort Collins. These times will be grouped in a small window of 2-3 days during the hours when all skating can be transferred to the East rink. D. All work debris will be cleaned up every day after each construction period ends. E. TBD (based upon design) - Access to the roof trusses will be performed by heavy equipment with a weight not to exceed 12,000 Ibs to minimize damage to ice surface. Equipment shall be skirted and wheels covered. F. Panels and equipment will be delivered to the rooftop from a location that will not impede access to the facility (EPIC). Part 2-Equipment 2.01 Solar Loop A. The collectors shall be SRCC approved solar thermal collectors. The panels will be mounted with aluminum; stainless or galvanized steel hardware to resist weather damage. Mechanical connections are to be made with stainless hardware. B. The solar domestic heat exchanger shall be a cupronickel or equivalent that can tolerate pool chemicals. C. All piping, valves and gauges will be clearly labeled and list of operating instructions will be posted. D. Type "L" or "K" Copper piping will be installed with R-6 or greater insulation and aluminum jacketing when exposed to sunlight. The piping system -including insulation must be able to withstand stagnation temperatures of 300 degrees F. E. The collectors will be mounted with the following physical limitations. A 7' maximum height above the roof deck and a 15' setback from the roof edge. Both requirements are intended to reduce the visual impact of the system. 2.02 Pool Heating A. Solar thermal collectors thru a heat exchanger utilizing a food -grade glycol solution must be used to heat the pool water. The glycol shall be rated to withstand stagnation temperatures of 300 deg F. B. The existing pool loop shall be modified to include a new heat exchanger for the solar heating system. 2.03 Piping A. All L or K type copper between collectors and storage tank shall be insulated with R6 min and protected against rainwater. B. Piping shall be elevated 3" min above roof surface on UV resistant rubber blocks similar to B-Line C ports. Piping shall be attached to blocks in a manner that reduces heat loss from piping to blocks. C. Piping shall be pressure tested to 100psi for a period of 48 hours prior to using the system. Piping shall be flushed and cleaned prior to charging with glycol and water. D. Piping shall be mechanically fastened to support structure as per local code requirements. 2/9/00 5.) Operating capacity of the proposed solar collector system is the responsibility of the proposer/contractor. The suggested design BTU generation per hour is approximately 600,000 British Thermal Units. The City will evaluate and approve the proposed design capacity and functionality of the solar collector system before acceptance and contract award. 6.) Question: What is the schedule of operations of the ice rink and other parts of the building when the pool is shut down for 2 weeks? Answer. The ice rink normal hours of operation are adhered to during a pool shut down, and visa versa for the pool hours, when the ice rink shuts down. We only close a venue (either pool or ice rink) for repair work, and only drain the pool or take down the ice for "maigf repairs to these systems. Typically we don't close both venues during same shut down period, and even if we close a venue, we may not drain the pool or take down the ice. It is common to have two shut downs annually; one in the Spring and one in the Fall. FYI... The roof directly over the main ice rink is the area designated where the solar collector panels are to be placed. See drawings. 7.) Question: Does the cooling tower provide space -cooling for the rink area - especially while the pool is down for 2 weeks? I'm.concerned about heat rejection capacity of the cooling tower for the purposes of stagnation protection. Answer. Yes, the Evapco model LSATA -5-125 provides heat rejection for both the ice rink cooling (Mcquay M# WHR060DW) as well as the building cooling (Lobby area and meeting room area) (Mcquay M# WHR050DW). 8.) Question: What about night sky heat rejection as a dump mechanism? Answer. This would be ok, but we assume you would need a day storage tank for the system. 9). Question: What is the size and age of the existing cooling tower? I don't have copies of the drawings and specs at my disposal. Answer: Existing cooling tower is EVAPCO M# LSTA-5-125. This is a replacement cooling tower that was installed in 1995. Capacity is approximately 4MMBTU/hr. 10.) Project budget range equals $180,000.00 to $220,000.00. Please contact John D. Stephen, CPPO, LEED AP, Senior Buyer at (970) 221-6777 with any questions regarding this addendum. RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT ENCLOSED WITH THE BID/QUOTE STATING THAT THIS ADDENDUM HAS BEEN RECEIVED. where renewal is a way of life E. Array piping shall be configured in a parallel reverse return configuration. The piping shall be arranged to promote equal flow thru all collectors and supply and return piping. F. Individual collector sub -arrays shall have isolation valves, circuit setters and drain valves to allow for isolation and flow balancing. An air vent shall be provided at each sub -array with an isolation valve. G. Temperature and Pressure Gauges shall be provided to allow monitoring of system performance in mechanical room. H. Two service ports shall be installed in mechanical room piping to allow connection of future equipment. These will be located on the collector supply and return piping. They will consist of a 1" T fitting and valve in the main piping loop. I. An expansion loop shall be provided as needed and specified by mechanical engineer. Calculations used to determine the expansion loop must be submitted for review. J. Piping and Insulation will be jacketed with aluminum jacketing to withstand UV degradation. Jacketing will be oriented to drain water and withstand wind damage. Jacketing will have a matte or dull finish to reduce glare. Jacketing will be secured in place with stainless steel fasteners. K. Contractor as outlined in sample schematic will provide valves, gauges and temperature wells. A premium will be placed on systems that facilitate easy service and maintenance. L. The collector loop piping to the rooftop shall be oversized by a factor of 200% to allow for future expansion of the system. The rooftop piping shall be configured to add onto the existing system with minimal disturbance. M. A corrosion resistant reservoir shall be connected to the pressure relief valve to collect the heat transfer fluid in event of high-pressure conditions. Overflow piping shall be installed from reservoir to available floor drain. 2/9/00 2.04 Controls A. A differential controller shall control solar collection. B. Wiring for the differential controller will require installation of a dedicated electrical conduit from provided 20-amp circuit. C. A BTU monitoring system shall be installed at the pool / solar heat exchanger. It shall be Johnson Controls N2 compatible thus enabling the City of Fort Collins BAS system to read it's outputs. D. Two (2) 3/" Conduit -EMT or Rigid will be run to the panel location for control wiring and monitoring. One will be reserved for future expansion. The conduit shall run from the array location to the controller. UV rated strain relief fittings shall be used in outdoor junction boxes to run cable to exterior locations. All sensor wiring shall have a UV rated jacket with stranded copper wiring of a minimum size of 24AWG. E. The controller shall be capable of the following functions- real time monitoring of 4 temperature locations, data logging and emergency fault codes. This data must be capable of being transmitted via Ethernet or phone to City of Fort Collins Maintenance department. F. The following 4 temperature sensors are required to be connected to the controller - Collector Return (Primary Sensor Location used for Delta-T operation) Pool Temperature, Collector Supply (Located after pool heat exchanger) and secondary collector return location. G. A heat dump circuit is also required as part of the control schematic. This shall consist of a separate piping loop and pump to the existing cooling tower. H. Provisions shall be made to accommodate monitoring via the existing HVAC control system at EPIC. This must consist of a number of temperature wells as specified in the sample schematic. I. Integration with the existing pool heating controls shall be co -coordinated with the City of Fort Collins HVAC maintenance staff. 2.05 Heat Dump Circuit A. During periods of stagnation or pool maintenance a heat dump circuit must be utilized. This will consist of a piping loop to the existing cooling tower. B. Piping locations are provided as part of the existing mechanical room and are noted in the RFP documents. 2.06 Documentation A. Equipment manuals and specifications for all materials used by the contractor must be delivered upon completion of the project. They must be submitted in two formats; paper copies in a 3-ring binder, and also electronically as a CD-ROM. B. A Complete set of schematics, operational procedures and emergency shut -down procedures must be posted by the contractor in the mechanical room with all signage designed to resist water damage. C. All piping and valves shall be labeled according to the plumbing schematic. Labels will be designed to resist water damage. 2/9/00 REVIEW AND ASSESSMENT Professional firms will be evaluated on the following criteria. These criteria will be the basis for review of the written proposals and interview session. The rating scale shall be from 1 to 5, with 1 being a poor rating, 3 being an average rating, and 5 being an outstanding rating. WEIGHTING . FACTOR QUALIFICATION STANDARD 2.0 Scope of Proposal Does the proposal show an understanding of the project objective, methodology to be used and results that are desired from the project? 2.0 Assigned Personnel Do the persons who will be working on the project have the necessary skills? Are sufficient people of the requisite skills assigned to the project? .5 Availability Can the work be completed in the necessary time? Can the target start and completion dates be met? Are other qualified personnel available to assist in meeting the project schedule if required? Is the project team available to attend meetings as required by the Scope of Work? .5 Motivation Is the firm interested and are they capable of doing the work in the required time frame? 3.0 Cost and Do the proposed cost and work hours compare Work Hours favorably with the project Manager's estimate? Are the work hours presented reasonable for the effort required in each project task or phase? 2.0 Firm Capability Does the firm have the support capabilities the assigned personnel require? Has the firm done previous projects of this type and scope? 2/9/00 Reference evaluation (Top Ranked Firm) The project Manager will check references using the following criteria. The evaluation rankings will be labeled Satisfactory/Unsatisfactory. QUALIFICATION STANDARD Overall Performance Would you hire this Professional again? Did they show the skills required by this project? Timetable Was the original Scope of Work completed within the specified time? Were interim deadlines met in a timely manner? Completeness Was the Professional responsive to client needs; did the Professional anticipate problems? Were problems solved quickly and effectively? .Budget Was the original Scope of Work completed within the project budget? Job Knowledge a) If a study, did it meet the Scope of Work? b) If Professional administered a construction contract, was the project functional upon completion and did it operate properly? Were problems corrected quickly and effectively? SECTION 00500 AGREEMENT FORMS 00510 Notice of Award 00520 Agreement 00530 Notice to Proceed 2/9/00 SECTION 00510 NOTICE OF AWARD Date: TO: PROJECT: 7080 EPIC Solar Pool Project OWNER: CITY OF FORT COLLINS (hereinafter referred to, as "the OWNER") You are hereby notified that your Bid dated 1 20 for the above project has been considered. You are the apparent successful Bidder and have been awarded an Agreement for 7080 EPIC Solar Pool Project. The Price of your Agreement is Dollars ($ ) Three (3) copies of each of the proposed Contract Documents (except Drawings) accompany this Notice of Award. Three (3) sets of the Drawings will be delivered separately or otherwise made available to you immediately. You must comply with the following conditions precedent within fifteen (15) days of the date of this Notice of Award, that is by 20 1. You must deliver to the OWNER three (3) fully executed counterparts of the Agreement including all the Contract Documents. Each of the Contract Documents must bear your signature on the cover of the page. 2. You must deliver with the executed Agreement the Contract Security (Bonds) as specified in the Instructions to Bidders, General Conditions (Article.5.1) and Supplementary Conditions. Failure to comply with these conditions within the time specified will entitle OWNER to consider your Bid abandoned, to annul this Notice of Award and to declare your Bid Security forfeited. Within ten (10) days after you comply with those conditions, OWNER will return to you one (1) fully -signed counterpart of the Agreement with the Contract Documents attached. By: 2/9/00 City of Fort Collins OWNER James B. O'Neill, II, CPPO, FNIGP Director of Purchasing & Risk Management SECTION 00520 AGREEMENT THIS AGREEMENT is dated as of the day of in the year of 20 and shall be effective on the date this AGREEMENT is signed.by the City. The City of Fort Collins (hereinafter called OWNER) and (hereinafter called CONTRACTOR) OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as follows: ARTICLE 1. WORK CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents. The Project for which the Work under the Contract Documents may be the whole or only a part is defined as the construction of the 7080 EPIC Solar Pool Project and is generally described in Section 01010. ARTICLE 2. ENGINEER The Project has been designed by City of Fort Collins Operation Services, who is hereinafter called ENGINEER and who will assume all duties and responsibilities and will have the rights and authority assigned to ENGINEER in the Contract Documents in connection with completion of the Work in accordance with the Contract Documents. ARTICLE 3. CONTRACT TIMES 3.1 The Work shall be Substantially Complete within 75 calendar days after the date when the Contract Times commence to run as provided in the General Conditions and completed and ready for Final Payment and Acceptance in accordance with the General Conditions within 85 calendar days after the date when the Contract Times commence to run. 3.2. Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the essence of this Agreement and that OWNER will suffer financial loss if the Work is not completed within the times specified in paragraph 3.1. above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. They also recognize the delays, expenses and difficulties involved in proving in a legal proceeding the actual loss suffered by OWNER if the Work is not completed on time. Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay (but not as penalty) CONTRACTOR shall pay OWNER the amounts set forth hereafter. 1) Substantial Completion: Section 00520 Page 1 Three Hundred Dollars ($300) for each calendar day or fraction thereof that expires after the seventy-five (75) calendar day period for Substantial Completion of the Work until the Work is Substantially Complete. 2) Final Acceptance: After Substantial Completion, one hundred dollars($100) for each calendar day or fraction thereof that expires after the ten (10) calendar day period for Final Payment and Acceptance until the Work is ready for Final Payment and Acceptance. ARTICLE 4. CONTRACT PRICE 4.1. OWNER shall pay CONTRACTOR for performance of the Work in accordance with the Contract Documents in current funds as follows: ($ ), $ Dollars, in accordance with Section 00300, attached and incorporated herein by this reference. ARTICLE 5. PAYMENT PROCEDURES CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the General Conditions. Applications for Payment will be processed by ENGINEER as provided in the General Conditions. 5.1. PROGRESS PAYMENTS. OWNER shall make progress payments on account of the Contract Price on the basis of CONTRACTOR's Application for Payment as recommended by ENGINEER, once each month during construction as provided below. All progress payments will be on the basis of the progress of the Work measured by the schedule of values established in paragraph 2.6 of the General Conditions and in the case of Unit Price Work based on the number of units completed, and in accordance with' the General Requirements concerning Unit Price Work. 5.1.1. Prior to Substantial Completion, progress payments will be in the amount equal to the percentage indicated below, but, in each case, less the aggregate of payments previously made and less such amounts as ENGINEER shall determine, or OWNER may withhold, in accordance with paragraph 14.7 of the General Conditions. 90% of the value of Work completed until the Work has been 50% completed as determined by ENGINEER, when the retainage equals 5% of the Contract Price, and if the character and progress of the Work have been satisfactory to OWNER and ENGINEER, OWNER on recommendation of ENGINEER, may determine that as long as the character and progress of the Work remain satisfactory to them, there will be no additional retainage on account of Work completed in which case the remaining progress payments prior to Substantial Completion will be in an amount equal to 100% of the Work completed. 90% of materials and equipment not incorporated in the .Work (but delivered, suitably stored and accompanied by documentation satisfactory to OWNER as provided in paragraph 14.2 of the General Conditions) may be included in the application for payment. Section 00520 Page 2 . 5.1.2. Upon Substantial Completion payment will be made in an amount sufficient to increase total payments to CONTRACTOR to 95% of the Contract Price, less such amounts as ENGINEER shall determine or OWNER may withhold in accordance with paragraph 14.7 of the General Conditions or as provided by law. 5.2. FINAL PAYMENT. Upon Final Completion and Acceptance of the Work in accordance with paragraph 14.13 of the General Conditions, OWNER shall pay the remainder of the Contract Price as recommended by ENGINEER as provided in said paragraph 14.13. ARTICLE 6. CONTRACTOR'S REPRESENTATION In order to induce OWNER to enter into this Agreement, CONTRACTOR makes the following representations: 6.1. CONTRACTOR has familiarized himself with the nature and extent' of the Contract Documents, Work, site, locality, and with all local conditions and Laws and Regulations that in any manner, may affect cost, progress, performance or furnishing of the Work. 6.2. CONTRACTOR has studied carefully all reports of explorations and tests of subsurface conditions and drawings of physical conditions which are identified in the Supplementary Conditions as provided in paragraph 4.2 of the General Conditions. 6.3. CONTRACTOR has obtained and carefully studied (or assumes responsibility for obtaining and carefully studying) all such examinations, investigations, explorations, tests, reports, and studies (in addition to or to supplement those referred to in paragraph 6.2 above) which pertain to the subsurface or physical condition at or contiguous to the site or otherwise may affect the cost, progress, performance or furnishing of the Work as CONTRACTOR considers necessary for the performance or furnishing of the Work at the Contract, Price, within the Contract Times and in accordance with the other terms and conditions of the Contract Documents, including specifically the provisions of paragraph 4.2 of the General Conditions; and. no additional examinations, investigations, explorations, tests, reports, studies or similar information or data are or will be required by CONTRACTOR for such purposes. 6.4. CONTRACTOR has reviewed and checked all information and data shown or indicated on the Contract Documents with respect to existing Underground Facilities at or contiguous to the site and assumes responsibility for the accurate location of said Underground Facilities. No additional examinations, investigations, explorations, tests, reports, studies or similar information or data in respect of said Underground Facilities are or will be required by CONTRACTOR in order to perform and furnish the Work at the Contract Price, within the Contract Times and in accordance with the other terms and conditions of the Contract Documents, including specifically the provision of paragraph 4.3. of the General Conditions. Section 00520 Page 3 6.5. CONTRACTOR has correlated the results of all such observations, examinations, investigations, tests, reports and data with the terms and conditions of the Contract Documents. 6.6. CONTRACTOR has given ENGINEER written notice of all conflicts, errors or discrepancies that he has discovered in the Contract Documents and the written resolution thereof by ENGINEER is acceptable to CONTRACTOR. ARTICLE 7. CONTRACT DOCUMENTS 7.1 The Contract Documents which comprise the entire Agreement between OWNER and CONTRACTOR concerning the Work consist of the General Conditions, Supplementary Conditions, those items included in the definition of "Contract Documents" in Article 1.10 of the General Conditions, and such other items as are referenced in this Article 7, all of which are incorporated herein by this reference. 7.2 Forms for use by CONTRACTOR in performing the Work and related actions in carrying out the terms of this Agreement are deemed Contract Documents and incorporated herein by this reference, and include, but are not limited to, the following: 7.2.1Certificate of Substantial Completion 7.2.2 Certificate of Final Acceptance 7.2.3Lien Waiver Releases 7.2.4Consent of Surety 7.2.5Application for Exemption Certificate 7.2. 6 Application for Payment 7.3 Drawings, consisting of a cover sheet and sheets numbered as follows: The Contract Drawings shall be stamped "Final for Construction" and dated. Any revisions made shall be clearly identified and dated. 7.4. Addenda Numbers to , inclusive. 7.5. The Contract Documents also include all written amendments and other documents amending, modifying, or supplementing the Contract Documents pursuant to paragraphs 3.5 and 3.6 of the General Conditions. 7.6. There are no Contract Documents other than. those listed or incorporated by reference in this Article 7. The Contract Documents may only be amended, modified or supplemented as provided in paragraphs 3.5 and 3.6 of the General Conditions. ARTICLE 8. MISCELLANEOUS Section 00520 Page 4 WLMIAS 9TRWOTURAL RNOI,NQCRR August 21, 2009 Steve Seefeld City of Fort Collins Operation Services 117 M. Mason P.O, Box 580 Fort Collins, CO 80522 Re: Edors Pool Ice Center (EPIC) 1801 Riverside Fort Collins, CO Project No. 29005 Gentlemen: As requested, we have reviewed a portion of the referenced structure to determine the structural feasiblUty of placing solar panels on the roof. It is our understanding that the panels would only be placed above the ice rink portion of the building. Our review is based on information provided on the original structural plans by Hastings & Chivetta Architects & Planners dated February 6, 1987. The existing roof structure in this area is a ballasted roofing supported by 1'/z Inch metal roof deck over 64 inch deep bar joists that span between steel beams and columns. The bar joists, which are spaced at 5'-T', span approximately 120 feet between beams that span about 21 feet.' It is our opinion that the existing bar joists and beams are adequate to support an additional load of up to 10 psf. The new panels should be not be placed on any joists that currently support mechanical equipment. Once a panel supplier is chosen, it is recommended we review the proposed panel loads and layout prior to placement. If we can be of further assistance please contact us. Sincerely, Weeks & Associates, Inc. Reviewed By: John McBride, P.E. Gary G. Weeks, P.E. Structural Engineer Structural Engineer Weeks & Associates, Inc. 4700 South College Avenue, Suite t, Fort Cottim CO 80525 Phone 9701225-2422; fax 970/ 225-2622 8.1. 'Terms used in this Agreement which are defined in Article I of the General Conditions shall have the meanings indicated in the General Conditions. . 8.2. No assignment by a party hereto of any rights under or interests in the Contract Documents will be binding on another party hereto without the written consent of the party sought to be bound; and specifically but not without limitations, moneys that may become due and moneys that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment no assignment will release or discharge that assignor from any duty or responsibility under the Contract Document. 8.3. OWNER and CONTRACTOR each binds itself, its partners, successors, assigns and legal representatives to the other party hereto, its partners, successors, assigns and legal representatives in respect to all covenants, Agreement and obligations contained in the Contract Document. Section 00520 Page 5 OWNER: CITY OF FORT COLLINS CONTRACTOR: By: By: JAMES B. O'NEILL II, CPPO, FNIGP DIRECTOR OF PURCHASING _ AND RISK MANAGEMENT Date: Attest: City Clerk Address for giving notices: P. O. Box 580 Fort Collins, CO 80522 Approved as to Form Assistant City Attorney Title: Date: (CORPORATE SEAL) Attest: Address for giving notices: LICENSE NO.: Section 00520 Page 6 SECTION 00530 NOTICE TO PROCEED Description of Work:7080 EPIC Solar Pool Project To. This notice is to advise you: That the contract covering the above described Work has been fully executed by the CONTRACTOR and the OWNER. That the required CONTRACTOR's Performance Bond and Payment Bond have been received by the OWNER. That the OWNER has approved the said Contract Documents. Therefore, as the CONTRACTOR for the above described Work, you are hereby authorized and directed to proceed.within ( ) calendar days from receipt of this notice as required by the Agreement. Dated this day of , 20_ The dates for Substantial Completion and Final Acceptance shall be 20 and 20_, respectively. City of Fort Collins OWNER By: Title: ACKNOWLEDGMENT OF NOTICE Receipt of the above Notice to Proceed is hereby acknowledged this day of 20_ CONTRACTOR By: Title: Section 00530 Page 1 SECTION 00600 BONDS AND CERTIFICATES 00610 Performance Bond 00615 Payment Bond 00630 Certificate of Insurance 00635 Certificate of Substantial Completion 00640 Certificate of Final Acceptance 00650 Lien Waiver Release (CONTRACTOR) 00660 Consent of Surety 00670 Application for Exemption Certificate 0 SECTION 00610 PERFORMANCE BOND Bond No. KNOW ALL MEN BY THESE PRESENTS: that (Firm) (Address) (an Individual), (a Partnership), (a Corporation), hereinafter referred to as the "Principal" and (Firm) (Address) hereinafter referred to as "the Surety", are held and firmly bound unto City of Fort Collins, 300 Laporte Ave, Fort Collins, Colorado 80522 a (Municipal Corporation) hereinafter referred to as the "OWNER", in the penal sum of in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, successors and assigns, jointly and severally, firmly -by these presents. THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered into a certain Agreement with the OWNER, dated the day of , 20, a copy of which is hereto attached and made a part hereof for the performance of The City of Fort Collins project,7080 EPIC Solar Pool Project. NOW, THEREFORE, if the Principal shall well, truly and faithfully perform its duties, all the undertakings, covenants, terms, conditions and agreements of said Agreement during the original term thereof, and any extensions thereof which may be granted by the OWNER, with or without Notice to the Surety and during the life of the guaranty period, and if.the Principal shall satisfy all claims and demands incurred under such Agreement, and shall fully indemnify and.save harmless the OWNER from all cost and damages which it may suffer by reason of failure to do so, and shall reimburse and repay the OWNER all outlay and expense which the OWNER may incur in making good any default then this obligation shall be void; otherwise to remain in full force and effect. Section 00610 Page 1 PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Agreement or to the Work to be performed thereunder or the Specifications accompanying the same shall in any way affect its obligation on this bond; and it does, hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Agreement or to the Work or to the Specifications. PROVIDED, FURTHER, that no final settlement between the OWNER and the CONTRACTOR shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied. PROVIDED, FURTHER, that the Surety Company must be authorized to transact business in the State of Colorado and be acceptable to the OWNER. IN WITNESS WHEREOF, this instrument is executed in three (3) counterparts, each one of which shall be deemed an original, this day of , 20 IN PRESENCE OF: Principal (Title) (Address) (Corporate Seal) IN PRESENCE OF: Other Partners By: By: IN PRESENCE OF: Surety By: By: (Address) (Surety Seal) r NOTE: DATE OF BOND MUST NOT BE PRIOR TO THE DATE OF THE AGREEMENT. If CONTRACTOR is Partnership, all partners should execute Bond. Section 00610 Page 2 SECTION 00615 PAYMENT BOND Bond No. KNOW ALL MEN BY THESE PRESENTS: that (Firm) (Address) (an Individual), (a Partnership), (a Corporation), hereinafter referred to as the "Principal" and (Firm) (Address) hereinafter referred to as "the Surety", are held and firmly bound unto the City of Fort Collins, 300 Laporte Ave., Fort Collins, Colorado 80522 a (Municipal Corporation) hereinafter referred to as "the OWNER", �in the penal sum of in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, successors and assigns, jointly and severally, firmly by these presents. THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered into a certain Agreement with the OWNER, dated the day of 1 , 20 a copy of which is hereto attached and made a part hereof for the performance of The City of Fort Collins project, 7080 EPIC Solar Pool Project. NOW, THEREFORE, if the Principal -shall make payment to all persons, firms, subcontractors, and corporations furnishing materials for or performing labor in the prosecution of the Work provided for in such Agreement and any authorized extension or modification thereof, including all amounts due for materials, lubricants, repairs on machinery, equipment and tools, consumed, rented or used in connection with the construction of such Work, and all insurance premiums on said Work, and for all labor, performed in such Work whether by subcontractor or otherwise, then this obligation shall be void; otherwise to remain in full force and effect. Section 00615 Page 1 PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Agreement or to the Work to be performed thereunder or the Specifications accompanying the same shall in any way affect its obligation on this bond; and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Agreement or to the Work or to the Specifications. PROVIDED, FURTHER, that no final settlement between the OWNER and the CONTRACTOR shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied. PROVIDED, FURTHER, that the Surety Company must be authorized to transact business in the State of Colorado and be acceptable to the OWNER. IN WITNESS WHEREOF, this instrument is executed in three (3) each one of which shall be deemed an original, this day of 20 — — IN PRESENCE OF: (Corporate Seal) IN PRESENCE OF: IN PRESENCE OF: (Surety Seal) Principal By: (Title) (Address) Other Partners Surety By: By: (Address) counterparts, NOTE: DATE OF BOND MUST NOT BE PRIOR TO THE DATE OF THE AGREEMENT. If CONTRACTOR is Partnership, all partners should execute Bond. Section 00615 Page 2 SECTION 00630 CERTIFICATE OF INSURANCE CONTRACTOR shall insert his own standard form for Certificate of Insurance. Section 00630 Page 1 SECTION 00635 CERTIFICATE OF SUBSTANTIAL COMPLETION TO: CITY OF FORT COLLINS (OWNER) DATE OF SUBSTANTIAL COMPLETION: PROJECT TITLE:7080 EPIC Solar Pool Project PROJECT OR SPECIFIED PART SHALL LOCATION: Fort Collins, Colorado INCLUDE:. OWNER: City of Fort Collins CONTRACTOR: CONTRACT DATE: The Work performed under this contract has been inspected by authorized representatives of the OWNER, CONTRACTOR, and the ENGINEER and the project (or specified part of the project, as indicated above) is•hereby declared to be substantially completed on the above date. A tentative list of items to be completed or corrected is appended hereto. This list may not be exhaustive, and the failure to include an item on it does not alter the responsibility of the CONTRACTOR to complete all the Work in accordance with the Contract Documents. ENGINEER AUTHORIZED REPRESENTATIVE DATE The CONTRACTOR accepts the above Certificate of Substantial Completion and agrees to complete and correct the items on the tentative list within the time indicated. By: CONTRACTOR AUTHORIZED REPRESENTATIVE DATE The OWNER accepts the project or specified area of the project as substantially complete and will assume full possession of the project or specified area of the project at 12:01 a.m., on The responsibility for heat, utilities, security, and insurance under the Contract Documents shall be as set forth under "Remarks" below. CITY OF FORT COLLINS, COLORADO By: OWNER AUTHORIZED REPRESENTATIVE DATE REMARKS: Section 00635 Page 1 EXISTING STL DECK 5 STL. ANGLE COLLAR AT 5TL, DECK 1 EN(5 0PJN 15TIN6 DRAM CLAMP STING DRAM LEADER, rc:-2ROOF DRAIN DETAIL 1/-2*=l'-O' VA �� BMTEK V, It (OVER RBNSTALL D*T. ROCK BALLAST Oven SLP SHEET OVER apm MEMBRANE ROOF SYSTEM OVER 150 CC,/ER BOARD NBN P.T. MOOD BLOC-'eA" 0 ROOF EASTINC7 ROOF 5TRX—nRE EDGE, F RECURED BY M~ (i2) PIPE VENT bE AIL 2 L4YEKS of .r_ -T- so. roP- 4 jo-rAL- oF I 'T "I rp:r6r_ NEA (SALV. SHT. Mn. RE6127 4 iu WUN'aR FLASHING ExrnNs BRICK it REDIeTALL EMST. ROCK BALLAST SECTION 00640 CERTIFICATE OF FINAL ACCEPTANCE TO: Gentlemen: 20 You are hereby notified that on the day of , 20_, the City of Fort Collins, Colorado, has accepted the Work completed by for the City of Fort Collins project, 7080 EPIC Solar Pool Project. A check is attached hereto in the amount of $ as Final Payment for all Work done, subject to the terms of the Contract Documents which are dated 20 In conformance with the Contract Documents for this project, your obligations and guarantees will continue for the specified time from the following date: 20 Sincerely, OWNER: City of Fort Collins By: Title: ATTEST: Title: Section 00640 Page 1 SECTION 00650 LIEN WAIVER RELEASE (CONTRACTOR) TO: City of Fort Collins, Colorado (OWNER) FROM: PROJECT:7080 EPIC Solar Pool Project (CONTRACTOR) 1. The CONTRACTOR acknowledges having received payment, except retainage from the OWNER for all work, labor, skill and material furnished, delivered and performed by the CONTRACTOR for the OWNER or for anyone in the construction, design, improvement, alteration, addition or repair of the above described project. 2. In consideration of such payment and other good and valuable consideration, the receipt and adequacy of which are hereby acknowledged, the CONTRACTOR voluntarily waives all rights, claims and liens, including but not limited to, mechanic's liens, Miller Act claims (40 U.S.C.A. 270 a and b), stop notices, equitable liens and labor and material bond rights which the CONTRACTOR may now or may afterward have, claim or assert for all and any work, labor, skill or materials furnished, delivered or performed for the construction, design, improvement, alteration, addition or repair of the above described project, against the OWNER or its officers, agents, employees or assigns, against any fund of or in the possession or control of the OWNER, against the project or against all land and the buildings on and appurtenances to the land improved by the project. 3. The CONTRACTOR affirms that all work, labor and materials, furnished, delivered or performed to or for the construction, design, improvement, alteration, addition or repair of the project were furnished,, delivered or performed by the CONTRACTOR or its agents, employees, and servants, or by and through the CONTRACTOR by various Subcontractors•or materialmen or their agents, employees and servants and further affirms the same have been paid in full and have released in full any and all existing or possible future mechanic's liens or rights or claims against the project or any funds in the OWNER'S possession or control concerning the project or against the OWNER or its officers, agents, employees or assigns arising out of the project. 4. The CONTRACTOR agrees to defend and hold harmless the OWNER,.the lender, if any, and the Surety on the project against and from any claim hereinafter made by the CONTRACTOR'S Subcontractors, materialmen, employees, servants, agents or assigns against the project or against the OWNER or its officers, employees, agents or assigns arising out of the Section 00650 Page 1 project for all loss, damage and costs, including reasonable attorneys fees, incurred as a result of such claims. 5. The parties acknowledge that the description of the project set forth above constitutes and adequate description of the property and improvements to which this Lien Waiver Release pertains. It is further acknowledged that this Lien Waiver Release is.for the benefit of and may be relied upon by the OWNER, the lender, if any, and Surety on any labor and material bonds for the project. Signed this day of CONTRACTOR By: Title: ATTEST: Secretary STATE OF COLORADO ) ) ss. COUNTY OF LARIMER ) Subscribed and sworn to before me this day of 20_, by Witness my hand and official seal. My Commission Expires: Notary Public 20 Section 00650 Page 2 SECTION 00660 CONSENT OF SURETY TO: City of Fort Collins, Colorado (hereinafter referred to as the "OWNER") CONTRACTOR: PROJECT: 7080 EPIC Solar Pool Project CONTRACT DATE: In accordance with the provisions of the Contract between the OWNER and the CONTRACTOR as indicated above, for (Surety) on bond of hereby approves of the Final Payment to the CONTRACTOR, and agrees that Final Payment to the CONTRACTOR shall not relieve the Surety Company of any of its obligations to the OWNER, asset forth in the said Surety Company's Bond. 1 IN WITNESS WHEREOF, the Surety Company has hereunto set its hand this day of , (Surety Company) By ATTACH: Power of Attorney and Certificate of Authority of Attorney(s)-in- Fact. Section 00660 Page 1 SECTION 00670 Section 00670 Page 1 DR 0172 (12/98) COLORADO DEPARTMENT OF REVENUE DENVER CO 80261 (303) 232-2416 CONTRACTOR APPLICATION FOR EXEMPTION CERTIFICATE Pursuant to Statute Section 39-26.114(1)(a)(XIX) A DO NOT WRITE IN THIS SPACE The exemption certificate for which you are applying must be used only for the purpose of purchasing construction and building materials for the exempt project described below. This exemption does not include or apply to the purchase or rental of equipment, supplies, and materials which are purchased, rented, or consumed by the contractor and which do not become part of the structure, highway, road, street, or other public works owned and used by the exempt organization. Any unauthorized use of the exemption certificate will result in revocation of your exemption certificate and other penalties provided by law. A separate certificate is required for each contract. Subcontractors will not be issued Certificates of Exemption by the Department of Revenue. It is the responsibility of the prime contractor to issue certificates to each of the subcontractors. (See reverse side). FAILURE TO ACCURATELY COMPLETE ALL BOXES WILL CAUSE THE APPLICATION TO BE DENIED. . Registration/Account No. (to be assigned by DOR) Period 89 - 0170-750 (999) $0.00 ' CONTRACTOR INFORMATION , Trade name/DBA: Owner, partner, or corporate name: Mailing address (City, State, Zip): Contact Person E-Mail address: Federal Employer's Identification Number: Bid amount for your contract: Fax Number: Business telephone number: Colorado withholding tax account number: EXEMPTION INFORMATION Copies of contractor agreement pages (1) identifying the contracting parties and (2) containing signatures of contracting parties must. be attached. Name of exempt organization (as shown on contract): Exempt organization's number: 198- Address of exempt organization (City, State, Zip): Principal contact at exempt organization: Principal contact's telephone number: Physical location of project site (give actual address when applicable and Cities and/or County (ies) where project is located) Scheduled Month Day Year Estimated Month Day Year construction start date: completion date: l declare under penalty of perjury in the second degree that the statements made in this application are true and complete to the best of my knowledge. Signature of owner, partner or corporate officer: Title of corporate officer: Date: DO NOT WRITE BELOW THIS LINE Section 00670 Page 2 Special Notice Contractors who have completed this application in the past, please note the following changes in procedure: The Department will no longer issue individual Certificates of exemption to subcontractors. Only prime contractors will receive a Contractor's Exemption Certificate on exempt projects. Upon receipt of the Certificate, the prime contractor should make a copy for each subcontractor involved in the project and complete it by filling in the subcontractor's name and address and signing it. The original Certificate should always be retained by the prime contractor. Copies of all Certificates that the prime contractor issued to subcontractors should be kept at the prime contractor's place of business for a minimum of three years and be available for inspection in the event of an audit. Once an 89# has been assigned to you, please use the next five numbers following it for any applications submitted for future projects. This should be your permanent number. For instance, if you were assigned 89-12345-0001, every application submitted thereafter should contain 89-12345 on the application. The succeeding numbers will be issued by the Department of Revenue. DO NOT enter what you believe to be the next in sequence as this may delay processing of your application. Section 00670 Page 3 SECTION 00700 GENERAL CONDITIONS GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT These GENERAL CONDITIONS have been developed by using the STANDARD GENERAL. CONDITIONS OF THE CONSTRUCTION CONTRACT prepared by the Engineers Joint Contract Documents Committee, EJCDC No, 1910-5 (1990 Edition), as a base. Changes to that document are shown by underlining text that has been added and striking through text that has been deleted. EJCDC GENERAL, CONDITIONS 1910-8 (1990 EDITION WITH CITY OF FORT COLLINS MODIr'ICATIONS (REV 9/99) Article or Paragraph Number x Titic DEFINITIONS TABLE .OF CONTENTS OF GENERAL, CONDITIONS Page Article or Paragraph Number Number & Title 1.1 Addenda....................................:........1 .1.2 Agreement..........................................1 1.3 Application for Payment.......................1. 1.4 Asbestos ..._......................... ...:........1 1.5 Bid............................................:........1 1.6 Bidding Documents ..........................,._1 1.7 Bidding Requirements .......................... j 1.8. Bonds... ........................ ............... 1.9 Change Order...,,,, 1 1.10 Contract Documents,.,..„ ........ _..1. 1.11 Contract Price 1 1.12 Contract Times 1 1.13 CONTRACTOR 1.14 defective ..................... ........................ 1 1.15 Drawings............................................1 1.16 Effective Date of the Agreement.,..,.___- I 1.17 ENGINEER 1 1.18 ENGIlNER's Consultant I 1.19 Field Order I L20 General Requirements ........................2 1 21 Hazardous Waste ................................. 2 1 .22.a Laws and Regulations; Laws or Regulations. _... 2 I:22.b ................................... Legal Holidays, ............ ................... . _2 1.23 Liens 2 1.24 Mileston.'.......................................2 e 1.25 Notice of Award 1.26 Notice to Proceed 2 1.27 OWNER 1.28 .......:.....................................? Partial Utilization„ .............................:2 1.29 PCBs .......................... 1.30 Petroleum...........................................2 1.31 Project.. .......................................- L32.a Radioactive Material ............................:� 1.3-ib Regular Working Hours,,,,,.. 1.33 Resident Project. Representative,...........2 1.34 Samples__ ................... 1.35 Shop. Drawings._......... ............ ..........2 1.36 Specifications.....................................2 1.37 Subcontractor....,,,.,,, ........................... 2 1.38 Substantial Completion 1.39 ......... I ....... Supplementary Conditions„ .................^ 1.40 Supplier., ............................................ 2 1.41 Underground Facilities ---------------- - ---- 2-3 1.42 Unit Price Work ........................ ..3 1.43 1N'ork..................................................3 1.44 Work Change Directive ................:.....:3 1.45 ii Written Amendment Page Number 2. PRELIMINARY MATTERS _........._...................3 =. I Delivery of Bonds .............................3 2.2 Copies of Documents ........................3. 2.3 Corn mencement.ofContract Times; Notice to Proceed.,_.,_...._.,. 3 2.4 Starting the Work ............................ 2.5-2.7 Before Starting Construction; CONTRACTOR'S Responsibility to Report; Preliminary Schediles; Delivery of Certificates of Insurancq„...,-..„ 3-4 2.8 Preconstruction Conference..............4 2.9 Initially Acceptable Schedules_... ...... 4 3. CONTRACT DOCUMENTS: INTENT, . %4ENDING, REUSE..........................................4 3.1-3.2 Intent__. ......... 3.3 Reference to Standards and Speci- fications of Technical Societies; Reporting and Resolving Dis- crepancies ................................. 4-5 3.4 Intent of Certain Terms or Adjectives .........................:........... 5 3.5 Amending Contract Docunents,,,,..... 5 3.6 Supplementing Contract Documents 5 3.7 Reuse of Documents ................ 4, AVAI.LABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS: REFERENCE POINTS 5 4.1 Availability of Lands,,,,,,,,,,,,,,,,,,, 5-6 4.2 Subsurface and Physical Conditions .................................... 6 4.2.1 Reports and Drawings.....................6 4.2.2 Limited Reliance by CONTRAC- TOR Authorized: Technical Data 6 4.2.3 Notice of Differing Subsurface or Physical Conditions ,,,,,,,,,,,,,,,,,,6 4.2.4 ENGINF.ER's Review ........................ 6 4.2.5 Possible Contract Documents Change.........................................6 4.2.6 Possible Price and Times Adjustments: ......... ....... ...... 0-7 4.3 Physical Conditions --Underground Facilities ................................ 4.3.1 Shown orlndicated .._ ................,_.,.7 4.3.2 'Not Shown or Indicated7 4.4 Reference Points ................................ 7 E1CDC GENERAL CONDMONS 1910-8 (1990 L'L)MON) wl CITY OF FORT COLT -INS MODIFICATIONS (RF.V 9199) 104 15 18 -T7 8 -b ILI UPPER P60.7 of JC& ARENA PkFTIAL SECOND FLOOR PLAN QCE MENAD - `� —� � �., G A d CORNER I—IMW DETAIL c0a0lseE and Nrnt shad by others. iha Arsht test (Fngi nee.) It 11 1111*111bl, 1- ...... I.d J, At4 KEY FLAN Article or Paragraph Page Number :Y 'Title Mum ber 4.5 Asbestos, PCBs, Petroleum, Fazardous Waste or Radioactive Material 7-8 5. BONDS AND INSURANCE ................................. 8 5.1-5.2 Performance. Payment and Other Bonds.............................................. S 5.3 Licensed Sureties and Insurers; Certificates of Insurance. ................... 8 5.4 CONTRACTOR's Liability Insurance 9 5.5 OWNER's Liability Insurance..............9 5.6 Property Insurance ................ .......... 9-10 5.7 Boiler and Machinery or Addi- tional Property Insurance..................10 5.8 Notice of Cancellation Provision 10 5.9 CONTRACTORs Responsibility for Deductible Amounts .................... 10 5.10 Other Special Insurance, ..................... 10 5.11 Waiver of Rights ...... .......................... I 1 5.12-5. 13 Receipt and Application of insurance Proceeds 10-11 5.14 Acceptance of Bonds and Insa- ance; Option to Replace. ................... 11 5.15 Partial Utilization --Property Insurance........................................1 1 6. CONTRACTOR'S RF.SPONSIBILITIF.S ...............11 6.1-6.2 Supervision and Superintendence_ .... 11 6.3-6.5 Labor, Materials and Equipment.,_ 11-12 6.6 Progress Schedule .............................12 6.7 Substitutes and "Or -Equal" Items; CONTRACTORs Expense;. Substitute Construction Methods or Procedures; ENGINF..ER's Evaluation.............12-13 6.8-6.11 Concerning Subcontractors, Suppliers.and Others; Waiver of Rights .........................13-14 6.12 Patent Fees and Royalties....................14 6.13 Permits .............. ............................... 14 6.14 Laws and Regulations.,__...,_..............14 6:15 Taxes...........................................14-15 6.16 Use of Premises,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, 15 6.17 Site Cleanliness,,._ 15 6.18 Safe Structural Loading;15 6.19 Record Documents .............................15 6.20 Safety and Protection,,.__,,,,,,,,,,,,, 15-16 6.21 Safety Representative ......................... J6 6:22 Hazard Communication Programs ...... 16 6.23 Emergencies.....................................16 6.24 Shop Drawings and Sam ples:.............16 Article or Paragraph Number & Titic Page Number 6.25 Submittal Proceedures; CON- TRACTOR's Review Prior to Shop Drawing or Sample Submittal ..................................... 16 6.26 Shop Drawing Sample Submit - talc Review by ENGINEER ...... 16-17 6.27 Responsibility for Variations From Contract Documents ............ 17 6.28 Related Work Performed Prior to ENGINEER's Review and Approval of Required Submittals..... .......... ........... _ 17 6.29 Continuing the Work....................17 6.30 CONTRACTOR's General Warranty and Guarantee..............17 6.31-6.33 Indemnification .......................... 17-19 6.34 Survival of Obligations ................... 18 7. OTHER WORK ................................................. IS 7.1-7.3 Related Work at Site,;,,,,,,,,,,,,,,,,,,,„ l8 7A Coordination....._..........................18 8: OWNER'S RESPONSIBILITIES .........................1 S S.1 Communications to CON- TRACTOR.................................18 8? Replacement of ENGINEER ............ IS 8.3 Furnish Data andPay Promptly When Due..................................18 8.4 Lands and Easements; Reports and Tests 18-19 8.5 Insurance..... .......... 19 8.6 Change Orders.............................. 19 8.7 Inspections, Tests and Approvals...................................19 8.8 Stop or Suspend Work; Terminate CONTRACTOR's Services ..:..................:................ l9 8.9 Limitations on OkVNER'S Responsibilities ...........................19 8.10 Asbestos, PCBs, Petroleum, Hazardous Waste or Radioactive Material ............. ...... 19 8.11 Evidence of Financial Arrangements.... 9. ENGINEERS STATUS DURING CONSTRUCTION.............................................19 9.1 OWNFR's Representative...............J9 9.2 Visits to Site..................................19 9.3 Project Representative ,,,,,,,,,,,,,,,19-21 9.4 Clarifications and Interpre- tations, ........................................ 21 9.5 Authorized Variations in kWk........ 21 fUCDC GENERAL CONDITIONS I910.8 (1990 Wrnom w/ CITY OF FORT COLLINS MODIFICATIONS (RF.V 9/99) Article or Paragraph Page Article or Paragraph Page Number [i Title Number Number JL Titic Number 9:6 Rej'ectingDefective Work ,,,,,,,,,,,,,,,,„.21 13.8-13.9 Uncovering Work at ENGI- 93-9.9 Shop Drawings, Change Orders NEER's Request,,,,,,,,,,,,,,,,,,,,, 27-28 and Payments....................................21 13.10 OWNER May Stop the Work .......... 28 9.10 Determinations for Unit Prices 21-22 13,11 Correction or Removal of 9.11-0.12 Decisions on Disputes, ENGI- Defective Work ;,;,r8 NEERasInitial Interpreter..............22 13,12 Correction Period,,,,,.,,,,,,,,,,,_.,_.,.�8 9.13 Limitations on ENGINEERS 13.13 Acceptance'ofMfeclive Wort ......28 Authority and Responsibilities,,,, 22-23 13.14 OWNER May Correct Defective Work.......... .................. 28-29 CHANGES fN THE WORK 23 _.......... 16.1 OWNER's Ordered Change................23 14. PAYMENTS TO CONTRACTOR AND 10.2 Claim for Adjustment,,,.,.,,, ., 23 COMPLETION,..,,..,,.. ......... .,29 10.3 Work Not Required by Contract 14.1. Schedule of Values,,,,,,;,,,,,,,,,,, 29 Documents ..................................... 23 14.2 Application for Progress 10.4 Change Orders...................................23 Payment. ....... ....... ............. ........29 10.5 Notification of Surety ........................,?3 14.3. CONTRACTOR's Warranty of Title 29 CHANGE OF CONTRACT PRICE ............................ 23 14.4-14.7 Review of Applications for 1 i.1-1 L3 Contract Price; Claim for Progress Payments,,,,,,,,,,,,,,,,, 29-30 Adjustment; Value of 14.8-14.9 Substantial Compleiion........... 30 the Work ........ ........................... .23-24 14.10 Partial Utilization .............. ........ 30-31 11 A Cost of the Work...........................;4-25 14.11 Final lnspectioq ........ :........ ............ 31 11.5 Exclusions to Cost of the Work,,,,,,,,,, 25 14,12 Final Application for Payment ........ 31 11.6 CONTRACTOR'S Fee,,,,,,,,,,,,,,,,,,,,,,,, 25 14.13-14.14 Final Payment and Acceptance ....... 31 11.7 Cost Records................................. 25-26 14.15 Waiver of Claims 31-32 11.8 Cash Allowances.. .... ....... ...... 26 11.9 Unit Price Work................................26 15, SUSPENSION OF WORK AND TERMINATION ............................................... 32 CHiVWE OF CONTRACT TIMES ,,,,,,,,,,,,,,;,,,,;,,,,,,,, 6 15.1 OWNER.May Suspend Work,,,,,,,,,32 12.1 Claim for Adjustment ....... *.._..._.._..__.26 15.2-15.4 OWNER May Term inate ............._.32 12.2 Time of the Essence ,,,,,,,,, .... _6 15.5 CONTRACTOR May Stop 12.3 Delays Beyond CONTRACTOR's Work or Terminate,,,,,,,,,,,,,,,,, 32-33 Control .......... .............. . .......... . . . 26-27 12A Delays Beyond OWNER's and I& D15PUTF.,RESOLUTION ..................................33 CONTRACTORS Control �7 17- N41SCELLANEOUS...........................................33 TESTS AND INSPECTIONS: CORRECTIOAt, 17.1, Giving Notice„..............................33 REMOVAL OR ACCEPTANCE OF 17.2 Computation ofTimes ......... ....... 33 DEFECTIVE WORK ............27 17.3 Notice of Claim.,.,,,,,,, 33 13.1 Notice ofDefects............................... F7 17.4 Cumulative Remedies .............. ...... ;13 13.2 Access to the Work ............................ 7 17.5 Professional Fees and Court 13.3 Tests and Inspections,, Costs Included... ............ -- .. 33 CONTRACTOR's Cooperation,.,,,.,,, 27 17.6 Applicable State Laws„ ............. 33-34 13.4 OWNER's Responsibilities: Intentionally left blank.......................................35 Independent Testing L.aboratory_......27 13.5 CONTRACTOR's EXHIBIT GC -A: (Optional) Responsibilities...............................r7 Dispute Resolution Agreement ............. _.... ,..GC -AI 13.6-13.7 Covering Work Prior to lnspce- 16.1-16.6 Arbitration.............................GC-A1 Lion, Testing or Approval................27 16.7 Mediation, ,,,..,,,,,,,.,,,,...,,,,,GC -AI EJCDC GENERAL CONDITIONS 1910.8 (1990 EDITION) w/ CITY OF FORT COLIANS MOMFiCAMNS (RFV 9/99) INDEX TO GENERAL CONDITIONS City of Fort Collins modifications to the General Conditions of the Construction Contract are not shown in this index Article or Paragraph Number Acceptance of - Bonds and Insurance........................................5.14 defective Work............................10.4.1, 13.5, 13.13 ,final payment ........................................9.1Z 14.15 insurance......................................................... 5.14 other Work by CONTRACTOR ..........................7.3 Substitutes and "Or -Equal" Items.....................$.7.1 Work. by OWNER .............................. 2.5, 6.30, 6.34 Access to the -- Lands, OWNER andCON1'RACTOR resporisibililies............................................. 4.1 site. related Work., ........................ ..................7.2 Work...........................................13.2, 13.14, 14.9 Acts or Omissions--, Acts and Omissions— CONI'RAC1'OR:.........................._.......6.9.1, 9.13.3 ENGINEER...........................................6i.20, 9,13.3 OWNER ... .. ........................ ............. ......... 6.20. 8.9 Addenda --definition of (also see definition of Specifications) ....... (1.6, 1.10, 6.19), 1.1 Additional Property Insurances ................................. 5.7 Adjustm ents-- Contract Price or Contract '1'imas.,._......................1.5. 3.5, 4.1. 4.3.2, 4.5.2. ...... .....................4.5:3, 9.4, 9.5. 10.2-10.4, .........................................11, 12, 14. 8, 15.1 progress schedule.. .............................................6.6 Agreement -- definition of......................................................1.2 "All -Risk" Insurance, policy form .... -.. ........ I ......... I5.6.2 Allowances, Cash....................................................11.8 Amending Contract Documents ................................ 3.5 Amendment, Written— in.general ................1.10, 1.45, 3.5, 5.10, 5.12, 6.6.2 .......................G.8.2, 6.19. 10.1, 10.4, 11.2 .....1.2.1, 13.12.2, 14.7.2 Appeal, OWNER or CONTRACTOR intent to ..........................9.10, 0.11, 10.4, 16.2, 16.5 Application for Payment -- definition of......................................................1.3 ENGINF.F.R's Responsibility ............................... 9.9 final payment ................. 9.13.47 9.13.5, 14.12-14.15 in general ..........................2.8, 2.9, 5.6.4, 9.10, 15.5 progress payment .... ..:................... I ............ 14.1-14.7 reviewof ....................................... ............ 14.4-14.7 Arbitration ........................................ ............. 16.1-16.6 Asbestos -- claims pursuant thereto............................5.2, 4.5.3 CONTRACTOR authorized to stop Work .... _.......5.2 definition of.......................................................1.4 tlrticle or Paragraph Number OWNER responsibility for ..... ......................... 4:5.1, 8.10 possible price and times change....,,_ ................4.5.1 Authorized Variations in Work ........... 3.6. 6.25. 6.27. 9.5 Availability of Lands..........................................4.1, 8.4 Award, Notice of--defined.........................................1.25 Before Starting Construction ....... ....................... 2.5-2.8 Bid --definition of ..... ............... ... 1.5 (1.1, 1.10, 2.3, 3.3,. ...................... 4.1.6.4, 6.13, 1 1 A.3, 11.9.1) Bidding Doctunents-definition of 1.6 (6.8-2) Bidding Requirements--defmition of.....................................I...1.7 (1.1, 4.2.6.2) Bonds -- acceptance of ... ............ 5.14 additional bonds .............................:.... 10.5. 11.4.59 Cost of the Work............................................11.5.4 definition of.......................................................k.8 delivery of....................................................2.1, 5.1 final Application for payment' _... .,,, ... ,.... 4.12-14.14 general ...................................... 1.10, 5.1-5.3, 5.13, I ........................... 9.13. 10.5, 14.7.6 Performance, Payment and Other,........... ......5.1-5.2 Bonds and Insurance --in general................................5 Builder's risk "all-risk" policy form .........................5.6.2 Cancellation Provisions, insurance ..... ,,5.4.11, 5.8, 5.15 Cash Allowances . ............ ....................................... I L8 Certificate of Substantial Completion ....... ;1.38, 6.30.2.3, ......14.8, 14.10 Certificates of Inspection ...................9.13.4, 13.5, 14.12 Certificates of Insurance........ 2.7, 5.3. 5.4.11, 5.4.13, _.._.........5.6.5; 5.8, 5.14, 9.13.4, 14,12 Change in Contract Price -- Cash Allowances....................„„_..,,,,_,..,,,.,-.._„11.8 claim for price adjustment............ 4.1, 4.2.6, 4.5, 5.15, 6.8.2, 9.4 ..._.:...........9.5.9.11, 10.2. 10.5. 11.21 13.9, ............ I ..........13.13, 13.14, 14. 7, 15.1, 15.5 CONTRACTOR's fee.........................................11.6 Cost of the Work general ................... .................. ........... 11.4-11.7 Exclusions to ............................................. ...1I:5 Cost Records, ........... I., ...... I ................................ 11.7 in general.............j.19, 1.44, 9,11, 10.4.2, 10.4.3, 11 Ltuup Sum Pricing ................ .......................... 11.3:2 Notification of Surety........................................10.5 Scope of....................................................10:3-1G.4 Testing and Inspection. Uncovering the Work, ..................... ........... 13.9 umc c&NERAL coi DIT1ONS 1910-8 (1990 EDITION) wf CITY OF FORT COLLIM MODIFICATIONS (REV 9(99) Unit Price Work 11.9 Article or Paragraph Number Value of Work ................................................ P.:11.3 Change in Contract Times -- Claim for times adjustment ......... 4,1, 4.2.6, 4.5, 5.15, ........... 6.8.2, 9.4. 9.5. 9.11. 10.2, 10.5. 12.1, ,,,,,....... ".13.9, 13.13, 13.14, 14.7, 15.1, 15.5 Contractual tim a lim its.:..................................:12 2 Delays beyond CONTRACTOR's control........................................................12.3 Delays beyond OWNERS and CONfRACTOR's control ........ ......... _..... „ 12.4 Notification of surety :.... .......... ..... I .... I ........ I ...... 10.5 Scope of change .............. ....................... ...10.3-10.4 Change Orders -- Acceptance of Defective Work,,,,,,,,,,,,,,,,,, 13.13 Amending Contract Documents ....................... 3.5 Cash Allowances ...............................:............... 11.8 Change of Contract Price...................................1.11 Change of Contract Times...................................12 Changes in the Work...........................................10 CONTRACTOR's fee 11.6 Cost of the Work... ..... I .............................. 11.4-11.7 Cost Records... ........ ......... ......................... 11.7 definition of.......................................................1.9 emergencies,.,;,,,., 0.23 ENGINEER's responsibility,,.„-.9.8, 10.4, 11.2, 12.1 execution ot..................................................::..10.4 Indemniticfion .........................0 12, 6.10, 6.31-6.33 Insurance, Bonds and .,__,_.---- .--- 5.10, 5.13, 1Q5 OWNER may terminate ,., ...., I .............. 1.5.2-15.4 OWNER's Responsibility. . .... . ..................... $4 10.4 Physical Conditions— Subsurface and.:............................................4.2 Underground Facilities--............................4.3.2 Record Documents ..........................................: 6.19 Scope of Change ....... .:.............................. 10.3-10.4 Substitutes ............................................. 6.7.31, 6.8.2 Unit Price Work ................................................ 11.9 value of Work, covered by.................................11.3 Changes in the Work..............................................10 Notification ofsurety................................ ........ 10.5 OWNER's and CONTRACTOR's responsibilities......................................I.....10.4 Right. to an adjustment......................................10.2 Scope of change ......... ............................... 10.3-10.4 Claims -- against CONTRACTOR....................................¢.16 against ENGIATEER..:......:....::.„.,.,....,,,,.,..,,,;.,,; 6.32 against OWNER„.......... „6.32 .................................. Change of Contract Price,,,,,;,,,,,,,,,,,,,,,,,,,„ 9.4. 11.2 Change of Contract Times ....................... 9.4, 12.1 CONTR4CTOR's...... _.....4. 7.1, 9.4. 9.5. 9.11, 10.2; ...........................11.2, 11.9, 12.1, 13.9,.14.8, 15.1. I5:5, 17.3 CONTRACI'OR's Fee 1 L6 Article or Paragraph Number CONTRACTOR's liability ........... 5.4, 6.12, 6.16, 6.31 Cost of the Work, ..... -..............................11.4, 11.5 Decisions on Dispute4....... I ....................... 9,11-, 9.12 Dispute Resolution ........................ .................... 16.1 Dispute Resolution Agreement .................... 16.1-16.6 ENGINEER as initial interpretor .......................9.11 Lump Sum Pricing-, ........................................ 10.2 Notice of ....................................... 17.3 OWNF..R's................... 9.4, 9.5, 9.11, 10.2, 11.2, 11.9 ................ .......„ 12.1, 139. 13.13. 13.14. 17.3 OWNERS liability ...... ......................................... 5-5 OWNER may refuse to make payment.................14.7 Professional Fees and Court Costs Included 17..5 request for formal decision on„,,,,,,,,,*%11 Substitute Items.............................................6..1.2 7 Time Extension.................................................12.1 Time requirements....................................9.11, 12.1 Unit Price Work ......... ........... :........................11.9.3 Valueof...........................................................1,1.3 Waiver of ---on Final Payment .................. 14.14, 14.15 Work Change Directive......................................10.2 written notice required ......................9.11, 11:2, 12.1 Clarifications and Interpretations,..;,,.,,,:, 3.6.3, 9.4. 9.11 Clean Site ................... 6.17 Codes of Technical Society, Organization or Association ........................... 3.3.3 Commencement of Contract Times__,.. „ ......... , ........ 2 3. Communications— .. general ............. ................................. 6.2. 6.9.2. 8.1 Hazard Communication Programs, .................... .6_222 Completion -- Final Application for Payment .........................14.12 Final Inspection,.,.,.,,,_.,,,, ................,._14.11 Final Payment and Acceptance, ........... * 14.13-14,14 Partial Utilization Substantial Completion ......................1.38, 14.8-14.9 Waiver of Claims : .... ....................................... 14A 5 Computation of Times .................... ........... 17.2.1-17.2.2 Concerning Subcontractors, Suppliers and Others................:................................6.8-6.11 Conferences -- initially acceptable schedules...,,,,_,... I ................. 2:9 preconstruction ................... 2.8 Conflict, Error, Ambiguity, Discrepancy-- CONIRACTOR to Report .......................... Construction, before starting by CONTRACTOR,............ 2 5-2:7 Construction Machinery, Equipment, etc,;,,,,,,,,,,,,,,,, 6.4 Continuing the Work ..................................... 6.29, 10.4 Contract Documents -- Amending..........................................................3.5 Bonds...........................:.. ................. 5.1 EJCDC GENERAL CONDMONS 1910.8 (1990 ED1110N) w/CITY OF FORT'COLLINS MODIFICATI NS (RF,V 909) Cash Allowances................................_............11-8 Article or Paragraph Number Change of Contract Price. .................................... 11 Change of Contract -times .................. „ ._. 12 Changes in the Work................................10.4-10.5 check and verify ......................... I......................:2.5 Clarifications and Interpretations ........................3.2, 3.6, 9.4, 9.11 definition of...................................................J.10 ENGINEER as initial interpreter of..................9.11 ENGINEER as OWNER's representative..............9,1 genera13 Insurance...........................................................5.3 Intent........................................................3.1-3.4 minor variations in the Work ........:...............__..3.6 OWNER's responsibility to furnish data_._„-_,._., 8.3 OWNER.'s responsibility to make prompt payment ..........................8-3, 14:4, 14.13 precedence... ... ......................................... 3-1,3.3.3 Record Documents ............................................. 6.19 Reference to Standards and Specifications of Technical Societies 3.3 Related Work ..................................................... 7.2 Reporting and Resolving Discrepancies;,.•,,., 2.5, 3. 3 Supplementing ...................... ........................... : 3.6 Termination of ENGINEER's Employment .......... 8.2 Unit Price Work. ................................................. 11.9 variations, .........................................3.6, 6.23, 6.27 Visits to Site, ENGINEER's.............._-------------- 9.2 Contract Price -- adjustment of,,,,,,,,,,,,,,,, 3.5, 4.1, 9.4. 10.3, 1 L2-11.3 Changeof..........................................................11 Decision on Disputes........................................9.11 definition of.....................................................1.11 Contract Times -- adjustment of .......................... 3.5. 4.1, 9.4, 10.31 12 Change of .......:............... ........ ................. 12.1-12.4 Commencement of 2.3 definition of.....................................................1.1'2 CONTRr1CTOR- Acceptance of Insurance .......... ... .14 Communications, 6.-1 6.9.2 Continue Work ........................................ 6.29. 10.4 coordination and scheduling ...................... .....6.9.2 definition of....................................................1.13 Limited Reliance on Technical Data Authorized................„,„.,.,_..._,_,„_..,.,4.2.2 May Stop Work or Terminate...._„_.....,,,,_„__..,,,,15.5 provide site access to others ..., 7.21 13.2 Safety and Protection ....................3.1 2, 6.16, 6.18, ...................................... 6.21-6.23, 7.2, 13.2 Shop Drawing and Sample Review . Prior to Submittal........................................6.25 Stop Work requirements..................................4.5.2 CON1'RACCOR's- Article or Paragraph Number Compensation.,,_..., ................. .._.....,11.1-11.2 ....... Continuing Obligation„...................................14.15 Defective Work 9.6. 13.10-13.14 Duty to correct defective Work ..........................13.11 Duty to Report -- Changes in the Work caused by Emergency............................. _............:6.23 Defects in Work of Others............................. 7.3 Dit%ring conditions .......................... ......4.2.3 ... Discrepancy in Documents...,._„ 2.5, 3.3.2, 6.14.2 Underground Facilities not indicated.... ... "_.4.3.2 Emergencies . .................................................... 6.23 Equipment and &4achinery Rental, Cost of the Work...........................................11.4.5.3 Fee --Cost Plus_.•_,..,,,,,,.„.„.,,,,,11.4.5.6, 11.5.1, 11.6 General Warranty and Guarantee,,,,,,,,,,,,,,,,,,,,,,,6:3f1 Hazard Communication Programs 6.22 Indemnification .........................6.12, 6.16,.6.31-6.33 Inspection of the Work....: .......................... 7.3, 13A Labor, Materials and Equipment ....................6.3-6.5 Laws and Regulations, (compliance by,,.,.„•.,,, 6.14,1 LiabilityInsurance............................................. 5.4 Notice of Intent to Appeal,_... ..... I ... ,.,;,•,,,,9.19, 10.4 obligation to perform and complete the Work,.....................................I.............6.30 Patent Fees and Royalties, paid for by................5.12 Pcrformanceand Other Bonds 5.1 Permits, obtained and paid for by.......................6.13 Progress Schedule ........................._.2.6. 2.8. 2.9, 6.6. .......... .............................. 6._9, 10.4,.15.2:1 Request for formal decisionon disputes,,,,,•,,,,,,,, 9.11 Responsibilities -- Changes in the Work ..................... ............. * 10'A Concerning Subcontractors, Suppliers and Others..........:......................-„_,6.8-6.11 Continuing the Work ..........................6129, 10.4 CONTRACTOR's expense .......................... 6.7.1 CONTRACTOR's General Warranty and Guarantee 6:30 CONTRACTOR'S review prior to Shop Drawing or Sample submittal,................6.25 Coordination of Work............................I...6.9.2 Emergencies ............................................... 6.23 ENGINEER's evaluation, Substitutes or "Or -Equal" Items.............................6.7.3 For Acts and Omissions of0thers.............................6.9.1-6.9.2, 9.13 for deductible amounts, insurance, ,,,,,,,,,,,,,,,,,, i.9 general........................................6, 7.2, 7.3, 8:9 Hazardous Communication Programs ........... 6.22 Indemnification 6.31-6.33 vii EicDC GENEm CONDiTiONS 19,10-3 (1990 EDITION) w/ C[TY OF FORT COLLINS MODIFICATIONS (PS V 9/99) Labor, Materials and Equipment..............6.3-6.5 Laws and Regulations,.._,. ........ Liability Insurance, .................... _ ......... _... _5.4 Article or Paragraph Number Notice of variation from Contract Documents.......................................... 6. 27 Patent Fees and Royalties............................6.12 Permits.......:...........:..... ......_...................... 6.13 Progress Schedule ......................................... 6.6 Record Documents 6,19 related Work performed prior to ENGINEER's.approval ofrequirod subm ittals....................:........................ 6:28 safe structural loading..,_ ...........................6.18 Safety and Protection,..,,_ ............. ti.20, T2, 13.2 Safety Representative:.................................6.21 Scheduling the Work..................................6.9.2 Shop Drawings and Samples ....................... 6:24 Shop Drawings and Samples Review by ENGINEER......................................6.26 Site Cleanliness ......... :......... ........................ ,17 Submittal Procedures ................................... 6.25 Substitute Construction Methods and Procedures ................................... 6.7.2 Substitutes and "Or -Equal" Items................0.7.1 Superintendence_, ........ ............ ..:................ 6.2 Supervision....................................... ............6.1 Survival of Obligations................................6.34 Taxes.............................................:...........6.15 Tests and Inspections,__._ ........ ......__...,__... 13.5 ToReport. . ................. ...... .......................... 2.5 Use of Premises 6.16-6.18, 6.30.2.4 Review Prior to Shop Drawing or Sample Submittal ............... I ......................... .25 Right to adjustment for changes in the Work 10.2 right to claim ............. , 7.1, 9.4, 9.5, 9.11, 10.2,11.2, .,........12.1. 13.9, 14.8, 15.1, 15.5, 17.3 Safety and Protection,,,,,,,,,,,,,,,,,, 6.20-6.22, 7.2, 13.2 Safety Representative.., ..... ­ ...... ... ­ I ._..I.....I... 6.21 Shop Drawings and Samples Submittals, .... 6.24-C,.28 Special Consultants ................. ...... . ............... ...11.4A Substitute Construction Methods and procedures_6.7 Substitutes and "Or -Equal" Items. Expense.......................................... 6.7.1, 6.7.2 Subcontractors, Suppliers and Others.......... 6.8-6.11 Supervision and Superintendence ......... 6.1, 6.2, 6.21 Taxes, Payment by ................................ I ...... ....ti.15 Use of Premises 6.16-6.18 Warranties and guarantees ........ ....... ....... .6.5, 6.30 Warranty of Titie........................................14.3 Written Notice Required— CONTRACTORstop Work or terminate.......15.5 Reports of Differing Subsurface and Physical Conditions ....................... 4.2.3 Substantial Completion................................14.8 viii CONTRACTORS --other 7 Contractual Liability Insurancc,,.......... ..................S.A.10 Contractual Time Limits 12.2 .......................................... Article or Paragraph Number Coordination— CONPRACTOR's responsibility ........................ 6.9.2 Copies of Documents ............................................... 2 2 Correction Perial,,,,,,,,,,,,,; ..................... . . 13.12 Correction, Removal or Acceptance of Defective Work-- in general, .................................. 10-4.1, 13:16-13.14 Acceptance of Defective Work .... ................. ...... 3.13 Correction or Removal of Defective Work ........ .................. ....... 6:30, 13.11 Correction Period........................._...,..,....,,._..,13.12 OWNER May Correct Defective Work,,,._ 13.14 OWNER May Stop Work.................................13.10 Cost -- of Tests and Inspections,,,,,,,,,,,,,,, ...................... 13.4 Records11.7 Cast of the Work — Bonds and insurance, additional ...................11.4.5.9. Cash Discounts ................................................ 11.4.2 C,'ONTRACTOR's Fee 11.6 Employee Expenses., .... ... I .... I ...... Exclusions to :. .............. *...... :..................... .... . Genera I11.4-11.5 Home office and overhead expenses,,,.., .............. 1 1 5 Losses and damages .....................................11.4.5.6 Materials and equipment._.,____. I ......... _.,-_. --- 11.4.2 Minor expenses,.,, ........... ...................... ....11.4.5.8 Payroll costs on changes.................................11.4.1 performed by Subcontractors ,,,,,,,,,,,,,,,,,,,,,,,,,„11A.3 Records 11.7 Rentals of construction equipment and machinery.....................................11.4.5.3 Royalty payments, permits and license.fees.........................„.„..,,;._,,,,,.,11.4.5.5 Site office and temporary facilities,,,,,,,,,,1 1.4.5.2 Special Consultants,.CONTRACTOR's..._......._ 11.4.4 Supplemental.................................................1 L4.5 Taxes related to the Work Tests and Inspection.........................................13.4 Trade Discounts .:.......................„..„:.,,,,..,,,_„ 11.4? Utilities, fuel and sanitary facilities ........... 11 A.5.7 Work after regular hours................................11.4.1 Covering Work. . --- ........................_ ,13.6-13.7 Cumulative Remedies .................._,.,,,..,,,,,...._ 17.4-17.5 Cutting, fitting and patching ......................_............. 7? - Data, to be furnished byOWNER..............................8.3 Day --definition of.................................................17.2.2 Decisions on Disputes ....... ............... .............. 9,11, 9.12 defective --definition of...........................................1.14 defective Work-- Acceptance. o f.....................I.................10.4.1. 13.13 EJCDC GENERAL CONDrrIONS 1910.8 (1990 EDITION) w/ CITY OF FORT COL UNI S MODIFICATIONS (REV 9199) Correction or Removal of ..................10.4.1, 13.11 Correction Period ..:..... .. ..... ........... ..........._,_..... 13.12 in general ................... I....,............1.13. 14.7. 14.11 Article or Paragraph Nu ber 'Observation by ENGINEER ................................ 9.2 OWNER May Stop Work ...... ........................... 13.10 Prompt Notice of Defects ,,,,,,,,,,................... ,•,,,13.1 Rejecting:................:.........:..........................:....9.6 Uncovering the Work ............. 13.8 Definitions.....:.....:.........._................................._..... 1 Delays......................................4.1, 6.29, 12.3-12.4 Delivery of Bonds ............... ........... ........................... '2.1 Delivery of certificates of insurance ............................2.7 Determinations for Unit Prices,,,,,,,,,,,,,,,,,,,,,,,,,,,,,; 9.10 Differing, Subsurface or Physical Conditions -- Notice of ................ ............................................ 4.2.3 FNGINF.ER's Review ...................................... a.2.4 Possible Contract Documents Change ............... Possible Price and Times Adjustments ,,,,,,.,;,•„•4-2.6 Discrepancies -Reporting and Resolving ....... ........................ 2.5. 3.3.2, 6.14.2 Dispute Resolution-- Agreement................................................16.1-16.6 Arbitration 16.1-16.5 general16 Mediation........................................................ 16.6 Dispute Resolution Agreement ........... .............. 16.1-16.6 Disputes, Decisions by ENGINEER ................. . 9.11-9.12 Documents -- Copies of... ...... ...... Record 6.19 Reuse of............................................................. 3.7 Drawings--detinition of.,,,,,.,,,,, ........................... ...1.15 Easements............................................................. 4.1 Effective date of Agreement -- definition of ............. 1.16 Fin ergencies...........................................................6.23 ENGINEER-- initial interpreter on disputes,•,•_,•,,,•,;,,_ 9.11-9.12 definition of .................................................... 1.17 Limitations on authority and. responsibilities..,,, 9,13 Replacement of ................. .._......................_-...8.2 Resident Project Representative..•........................9.3 ENGINEER's Consultant -- definition of ............... 1 ..18 ENGfNEER's-- authority and responsibility, limitations on ........ 9.13 Authorized Variations in the Work .,,,,•,,,,,•,,,•„•..9.5 Change Orders, responsibility for.,..... 9.7, 10, 11, 12 Clarifications and Interpretations,.,.._..•._. 3.6.3, 9.4 Decisions on Disputes., ........................... _9.11-9.12 defective Work, notice of .... ........................ ....... 13-1 Evaluation of Substitute Items .......................... 6.7.3 Liability ................................................... 6.32, 9.12 Notice Work is Acceptable._ . .... ......... - ... I --------- I4.13 Observations...........................................6.30.2, 9.2 OWNER's Representative ...... ..-.._.___.,_..............9.1 Payments to the CONTRAC-rop, Responsibility for... la Recommendation of Payment. ................... 14.4, 14.13 Article or Paragraph Number Responsibilities --Limitations on ... ,.•.........._9.11-9.13 Review of Reports on Differing Subsurface and Physical Conditions-, .........................4.2:4 Shop Drawings and Samples, review responsibility ............................................... 6.26 Status During Construction -- authorized variations in the Work9.5 Clarifications and Interpretations •.__..... •........9.4 Decisions on Disputes ................... 9.11-9.12 Determinations on Unit Price 9.10 ENGINEER as Initial Interpreter,._,___„ 9,11-9.12 ENGMER's Responsibilities ................9.1-9.12 Limitations on ENGINEER's Authority and Responsibilities .............................. 9.13 OWNER's Representative., ............................9.1 Project Representative..................................19.3 Rejectingective Work..............................9.6 Shop Drawings, Change Orders and PaymenLs....................................9.7-9.9 Visits to Site .................................................. 9.2 Unit.Price determinations., ..........................•,_,,, 9.10 Visits to Site.......................................................9.2 Written consent required, ......... .................. 7.2, 9.1 Equipment, Labor, Materials and,.......................0.3-6.5 Equipment rental, Cost of the Work ................... 11.4.5.3 Equivalent Materials and Equipment, ....................... 6:7 error or omissions... .............. .......................... 6.33 Evidence of Financial Arrangements, ...................... 8.I 1 Explorations of physical conditions ........................ 4.2.1 Fee, CONTRACTOR's--Costs Plus ...........................11.6 Field Order -- definition of, ........... : ........................................ JI. 19 issued by ENGINEER ,,.,•.,...,.......... •.... •..... 3.6.1, 9.5 Final Application for Payment........................•„•.•.14.12 Final Inspection...................................................14.11 Final Payment -- and Acceptance ............. „.,,...:_...,;_.,.:,„ 14,13-14.14 Prior to, for cash allotences............................... 1 1.8 General Provisions,,,,,.,,,,•,•,,,,,,,,,,,,,,,,,,,,,,,,,,,,,17.3-17.4 General Requirements - definition of.....................................................1.20 principal, references t4...............2.6, 6.4, 6.6-6.7, 6.24 Giving, Noticc.........................................................17.1 Guarantee of Work -by CONTRACTOR;,..,.,, 6.30, 14:12 Hazard Communication Programs,,,,,,,,,,,,,, .......... - 6.22 I•Iazardous Waste-- definitionof.21 ..................................... .................1 general .........___....................................... ..... 4.5 OWNER's responsibility for .............................. 8.10 EJCDC GENERAL CONDITIONS 19I0.8 (1990 EDITION) wf CITY OF FORT COLLINS MODIFICATIONS (REV 9199) Indemnification, ...... ....... ..... _ ..... . fi.12, 6,16, 6.31-6.33 Initially Acceptable Schedulcs;;,,,,,,,,,,,,,,,•_ Inspection -- Certificates of ............. ......... ........ 9.13A,.13.5, 14.12 Final............. .............................................. 14-11 Article or Paragraph Nunn ber Special, required byENGfNEER 9.6 Tests and Approval ............................ 5.7, 13.3-13.4 Insurance -- Acceptance of, by OWNER .:... .......................... 5,14 Additional, required by changes in the Work...........:................................11.+5.9 Before:starting the Work_...., .... .............•............2.7 Bonds and --in general..........................................5 Cancellation Provisions ... ........... •....... , ... ,... ...... 5.8 Certificates of,,,,_„ •.....,.. 2.7, 5, 5.3, 5.4.11, 5.4.13, ........................5.6:5, 5.8, 5.14, 9,13.4, 14.12 completed operations ........ ... ....................... 5A I3 CONTRACTORS Liability..................................5.4 CONTR.ACTOR's objection to coverage,,,,,,,,,,,,, 5.14 Contractual Liability ......................................5A.10 deductible amounts, CONTRAcTOR's responsibility ................................................5.9 Final Application for Payment, ......................... 14,12 Licensed Insurers .......... ..:.......... .. ..................... 5.3 Notice requirements, material changes,5.8, 10.5 Option to Replace,-,-..-_...................................5,14 other special insurances ... ........ .........................5,10 OWNER as fiduciary for insureds,,,,,,,, ....5.12-5.13 UWNER's Liability..... - .�5 OWNER'S Responsibility_ Partial Utilization. Property Insurance ,-,,,..,,,•,...S-Is Property........... ..........................................5.6-5.10 Receipt and Application of Insurance Proceeds, ................... ......................... 5,12-5, 13 Special Insurance„- ...,.... 5110 Waiver of Rights .... ......... __.... .... .................. .5.11 Intent of Contract Documents,,,•,,,,,,,,,,,,,,,,,,,,,,,;,,3.1-3.4 Interpretations and Clarifications ....I...............3.6.3, 9.4 Investigations of physical conditions 4.2. Labor, Materials and Equipment,,,,,,,,,,,,,,,, ,,_,.....6.3-6.5 Lands -- and Easements...................................................$.4 Availability of ............................................. 4.1, 8,4 Reports and Tests .......... ........................ ............:g.4 Laws and Regulations --Laws or Regulations-- Bonds........................................................5.1-5.2 Changes in the Work, ........ .............................1(1.4 Contract Documents.:...:.....................•,-„.,,;,••.„3.1 CONTRACTOR's Responsibilities ........... .......••.6-14 Correction_ Period, defective Work ........ ,........... 13.12 Cost of the Work, taxes ........... ......... ......11.4,5:4 definition of......... - •............_.......-...._....1.22 general6.14 Indemnification ........................................ 6.31-6.33 Insurance 5.3 1'rccedence .......:..................... 3.1, 3.3.3 Reference to....................................................3.3.1 Safety and Protection................................6 20, 13.2 Subcontractors, Suppliers and Others ........... 6.8-6.1I Article or Paragraph Number Tests and Inspections...................................13.5 Use of Premises ............: ... 6.16 Visits to Site_.,,,.,,, ............................................ „9.2 Liability Insurance— CONTRACTORs ............................................... . 5.4 OWNERS:...............................:..........................5.5 Licensed Sureties and Insurers;,,,,•,• ........... ............. 5.3 Liens -- Application for Progress Payment ....................... 14,2 CON IZAC'I'OR's Warranty ofTitie .... ..... ,, , 14.3 Final Application for Payment ........ ,...... .......... 4.12 definition ... of.................................................. 1 23 Waiver of Claim's„•,,,,,,,,,,,,,,,,,„.,,,,,,,-,,,,,,,,,-.,,14.15 Limitations on ENGNEER's authority and responsibilities ................................................. 9.13: Limited Reliance by CONTRACTOR Authorized...................................................... 4.2.2. Maintenance and Operating Manuals -- Final Application for Payment ..........................14.12 Manuals (of others)-- Precedence....................................................i.3.3.1 Reference to in Contract Documents.,,,,,,•,,,,,,,,-3.3.1 MateriaWand equipment -- furnished by CONTRACTOR..,-- ----------- *....... ...... .3. not incorporated in Work ,,,,,,,,,,,,,,,,,,•,,,,•,.......... 14.2 Materials or equipment --equivalent ......................I....6.7 Mediation (Optional)..............................................16.7 Milestones --definition of .......................................... 1.24 Miscellancous-- . Computation of Times............................I...........17.2 Cumulative Remedies 17.4 Giving Notice....................................................17:1 Notice of Claim ......17.3 Professional Fees and Court Costs Included,-,,,,, 17.5 Multi -prime contracts..... ........... ... 7 Not Shown or Indicated..............:..........................4.3.7 Notice of -- Acceptability of Pr'oject.....................................14.13 Award, definition of.......,.......... . ................1.25 ...... Claim ...................... ...................................... 17.3 . Defects,13:1 Differing Subsurface or Phvsical Conditions,_„_4,2.3. Giving.................................... ........................ 1,7.1 Tests and Inspections ,,,,,,,,,,,,,,,,• 13.3 Variation, Shop Drawing and Sample ;,,,,,•,,,,,,,,, G:27 Notice to.Proceed-- definition of.....................................................1.26 givingof ............ ........ ........................................=,3 E1CDC; GENERAL CONDITIONS 1910.8 (1990 ED111ON) w/ CITY OF FORT COLLINSh10DIFICA110NS (REV 9191) Notification to Surety.. .... ....................................... jO.5 testing, independent .............................. .......... 13.4 Observations, ons, by ENGINEER ... ................ 6.30, 9.2 use or occupancy Occupancy of the Work .... 5.15. 6.30.2.4. 14.10 of the Work.......,,.,,,,,.......... 5.15. 6.30.2.4, 14.10 Omissions or acts byCONTRACTOR...... ........ 6.9,9.13 written consent or approval Open Peril policy form, Insurance ..........................5.6.2 required .................... .................... 9.1, 6.3, 11.4 Option to Replace .................................................... 5, 14 Article or Paragraph Number "Or Equal" Items ................ ...................................... 6.7 Other work 7 Overtime Work --prohibition of .................................. 6.3 OWNER- - Acceptance ofdefecfive Work .......................... ............... 113.13 appoint -an ENGINEER.... ................................... 8.2 as fiduciary .............. ........................... 5.12-5.13 Availability of Lands, responsibility ....... ; ............ 4.1 definition o( ........ ___ ..........................­ ........ * 1.27 data, furnish ......................................................8.3 May Correct Defective Work ... ......... .............. 13.14 May refuse to make payment .............................14.7 1.4.7 May Stop the Work .......................... I ....... May Suspend Work, Terminate...,...._-_.............A.S, 13.10, 15.1-15.4 Payment, make prompt ................... _ 83, 14.4, 14.13 performance of other work ............................ 7.1 permits and licenses, requirements,,,,,,,,,,,,,,,,,,, 6..13 purchased insurance requirements ............... 5.6-5.10 OWNTER!s-- Acceptance of the Work ............................... 6.30.15 Change Orders, obligation to execute ........... 8.6, 10.4 Communications,....... ......................... ............ 8.1 Coordination of the Work 7.4 Disputes, request fordecision ............................9.11 Inspections, tests and approvals .............. ... $3. 13.4 Liability Insurance ..............................................5.5 Notice of Defects ..............................................13.1 Representative --During Consmuction, ENGINEFR's StatiL 9.1 Responsibilities -- Asbestos, PCBs, Petroleum. Hazardous Waste or Radioactive Material ................ 8.10 Change. Orders..............................................8.6 Changes in the Work .................... ......... 10.1 communications 8.1 CONTRACTORs responsibilities .................. 8.9 evidence of financial arrangements ............... $AI inspections, tests and approvals.,, ................... 8.7 insurance �.5 lands and easements .......... ­ ................. 8.4 prompt payment by .......................................8.3 replacement of ENGENEER.._.... .................. $.2 reports and tests ............................................ 8:4 stop or suspend Work ................... 8.8, 13.10, 15.1 terminate CONTRACTORs services., ............. : ....... .......... J.8. 15.2 separate representative at site ..............................9.3 Xi EJCDC GENERAL CONDITIONS 1910-3 (1990 El)fflom w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9199) Article or Paragraph Num ber written notice required ......................... 71-1, 9.4, 9.11, ...........................11.2, 11.9, 14-7, 15.4 PCBs -- definition of.............:_......................................1,29 general................................. .................... ....... 4.5 OWNER's responsibility for ...............................5.10 Partial -Utilization-- definition of.......................................................1.28 general 6. 30.2.4, 14.10 Property Insurance,_,,,_ ................... ..5.15 Patent Fees and Royalties ........................................6.12 . Payment Bonds ........... ­­11­...1­­ .................... 5.1- 15.2 Payments, Recommendation of .............. 14.4-14.7, 14.13 Payments to CONTRACTOR and Completion - Application for ProgressPayments .............. ....... 14. 2 •CONTRAi7rOR`s Warranty ofTitic .......... .... *14.3 Final Application for Payment.........................14.12 Finn I Inspection ...... .................. ............. I ....... 14.11 Final Payment and AcceptHnc I e .... _ _:__1 4,13-14,14 general ......................... ..................... 8.3, 14 Partial Utilization .................. _ 14.10 Retainage..........................................................14.2 Review of Applications ror Progress Payments ............................ ... 14,4-14.7 prompt payment.... .................... .......... ...... $3 Schedule of values ...... z..; ....... _ .......... _ � �: ... 14.1 Substantial Completion,,,,,,,,,,, .................. 14.8-14.9 Waiver of Claims 14.15 when payments due ................................ 14.4, 14.13 withholding payment.---..-..- .... ............ ..... _ 14.7 Performance Bonds ..................................... I ...... Perm itsI ............ ............... ...... 6.13 Petroleum -- definition of.....................................................1.30 general........... .................................................. 4.5 OWNER's responsibility f4 ...............................8.10 Physical Conditions -- Drawings ofin or relating to ............. ..... 4.2.L2 ENOrNEER!s review, ..................................... -A.2.4 existing structures.... .......... I ...... ....................4.2.2 general4.2.1.2 .............. .......... I .... I ............. - Notice of Differing Subsurface or. ............ ........ 4.2.3 Possible Contract Documents Change...............4.2.5 Possible Price and Times Adjustments .............. :4.2.6 Reports and Drawings......................................4.2.1 Subsurface and ................. _ ................................ 4.2 Subsurface Conditions ......... I ............. _ ...... Technical Data, Limited Reliance by CONTRACTOR Authorized ........... ....... 4.2.2 Underground Facilities -- general..... ............................ M ............. ... 4.3 Not Shown or Indicoted .......... __ ...... :__ --- 4.3.2 Protection o( ........................................ 4.3,6.20 Article or Paragraph Number Shown or Indicated Technical Data 4,2.2 Preconstruction Conference 2.8 Preliminary Matters..,_...__, ....... I ......... ... 2 Preliminary Schedules ........................ ...................... 16 Premises, Use of ............ ­­­­ ...... 6.16-6.18 Price, Change of Contract ... ................... ....... I I Price, Contract --definition of.................................. 1.11 Progress Payment, Applications fq ....... ............ i 4.2 Progress Payment---rctainagq,, .... I ...... ...... ........ 14.2 Progress schedule, CONTRACTMs ........... 2,6,.2.8, 2.9, ........ ................ 6.6. 6:29. 10.4, 15.2.1 Project --definition of ...............................................1.31 Project Representative— ENGINEERs Status During Construction ............. 9.3 Project Representative, Resident --definition o - f ......... 1.33 prompt payment by OWNER ..................................... 8.3 Property Insurance -- Additional 53 gencraI5.6-5. 10 Partial Utilization .................... ........ 5.15� 14. 10.2 receipt and application of proceed. .... ....... 5.12-5.13 Protection, Safety and .............................. 620-6.21, 1.3.2 'Punch list.......... ................. 14.11 Radioactive Material— defintion of 1.32 Vnera14.5 OWNER's responsibilityfor .............................. 8.10 Recommendation of Payment ................. 14.4, 14 ' 5, 14.13 Record Documents 6.19, 14.12 Records; procedures.for maintaining .......................... 2.8 Reference Points.......................................................4.4 Reference to Standards and Specifications or Technical Societies .................... I .... I ... I ........... 3.3 Regulations, Laws and(or) ...................................... 6,14 Rejecting Defective Work .. '.............................. 9.6 Related Work -- atSite ....... I ........... 11 ............. ; ........ ; ............ 7.1-7.3 Performed prior to Shop Drawings and Samples submittals review ... ....... .......... 6.28 Remedies, cumulative__..__..., ....................... 17.4. 17.5 Removal or Correction ofDofectiv? Work .......... ...... 13.11 rental agreements, OWNER approval rcquired ..... 11.4.5.3 replacement of ENGINEER� by OWNER ......... ........ ­:& 2 Reporting and Resolving Discrepancies .................................. 2.5, 33.2, 6.14,2 Reports -- .and Drawings .................................................4.11 and Tests. OWNW,s responsibility.,., .......... ...... $.4 Resident and Project Representative -- definition of ............ I ......... I .... I ................... I., ... 1.33 provisionfor ........................................... ....... ......... 9.3 sii EJCDC GENERAL CONDITIONS 1910-8 (1990 EDITION) wICITY OF FORT.COI.I,[NS,\IODIFICA710,14S (RFV 9199) NORTH ELEVATION v1e•;t�4. 1 -.41 I'EAST ELEVATION. 1116':l*-;D" Tp- ------ IT— 'SOUM ELEVATION . L2 ----------- ------ ILI LWTS—TL"V� 1—Inrb—sp. conp 1, "Y ,m,, mi,,Ao,, Mtc.2. b 'Ib f It, this dlll.11t 1, a ...It. Article or Paragraph Num ber Resident Superintendent, CONTRACTOR's............... 62 Responsibilities-- CONTRACTORs-in general,,,,.. I ............... I ........... 6 ENGINEER! s-in.genera I........................................9 Limitations on.............................................9.13 OWNER's-in general..............................................8 Retainage............................................................1.4.2 Rcuse of Documents ................................................. 3.7 Review by CONTRACTOR: Ship Drawings and Samples Prior to Submittal ..........................6.25 Review of Applications for Progress Payments ..... ..... .......... .................. 14.4-14.7 Right to an adjustment...........................................10.2 Rightsof Way ............................. .. ... ...................4.1 Royalties, Patent Fees and......................................6.12 Safe Structural Loading ..........................................6.18 Safety -- and Protection................................4.3.2, 6.16, 6.18, ............._......................6.20-6.21, 7.2, 13.2 general ............................... ...................... Ci.20-6.23 Representative, CONTRACTORS ......................6.21 Samples -- definition of ............ .................. ........................ 1.34 general....:..:...............1..:.................-.:.....: 6.24-6.28 Review by CONTRACTOR .... ............ ................ 6.25 Review by ENGINEER..............................6.26, 6.27 related Work.....................................................0.28 submittal of 6.24.2 submittal procedures.........................................6.25 Schedule of progress.,., .......... : .............. 2.6. 2.8-2.9, 6.6, ..............................6.29, 10.4, 15.2.1 Schedule of Shop Drawing and Sample Submittals..............................2.6, 2.8-2.9, 6.24-6.28 Schedule of Values...............................2.6, 2.8-2.9, 14.1 Schedules -- Adherence to ..... .............................................. 15.2.1 Adjusting...........................................................6.6 Change of Contract Times.................................10.4 Initially Acceptable........... _.... _.:...._.. _.._...... 2.8: 2.9 Preliminary .....................:....... ........................ 2.6 Scope of Changes .......................... ............. 10.3-10.4 Subsurface Conditions ........................................ 4.2.1.1 Shop Drawings -- and Samples, general., .................... I .......... 6.24-6.28 Change Orders & Applications for Payments, and ... ....... ...... I ..... I—— .... .._...... 9.7-9.9 definition of ...................... :....... ......................... 1.35 ENGINEFR's approval of 3.6.2 ENGINEER s.responsibility for review ..................................... 9.7, 6.24-6.28 related Work .......................... ._....._.................:6.28 review procedures.... I..........................18, 6.24-6:28 Article or Paragraph Number submittal required... ............................................. 6.241 Submittal Procedures.........................................6.25 use to approve substitutions.. ..... ................ _6.7.3 Shown or Indicated ............................................... 4.11 Site Access......................................................72, 13:2 Site Cleanliness ........................................................ 6.17 Site, Visits to -- by ENGINEER...........................................9.2, 13.2 by othcrs............................... ..........................13.2 "special causes of loss" policy firm, insurance .......................................................5.6.2 definition of ................... ................ I ................. 1,36 Speci ficat ions-- defination of....................................................1.30 of Technical Societies, reference to., ................ 3.3.1 precedence......................................................3.3.3 Standards and Specifications of Technical Societies,,,,,,,,,,,,,,,,,,,,,,,,,,,,, 3.3 Starting Construction, Bcforz............................... .5-2.8 Starting the Work......................................................2.4 Stop or Suspend Work -- by CONTRACTOR...........................................15, i by OWNER.....................................8.8, 13.10, 15.1 Storage of materials and equipment„.,_..............4.1, 7.2 Structural Loading, Safety ...: ........... :..:...:....:....... ..... 6.18 Subcontractor Concerning ................................................ 6.8-6. I 1 definition of. ........... ........................................ J.37 dcla%s 12.3 waiver of rights................................................0.11 Subcontractors --in general,,,,,,,,,.„.....................6.8-6.11 Subcontracts --required provisions.,,,.,_„ 5.11, 6.1 I,114.3 Submittals — ,Applications for Payment„ ................................ 14.'-- Maintenance and Operation ivfanuals...............14,12 Procedures...................................................... 6.25 Progress Schedules:.....................................2.6. 2.9 Samples ............................... ...:................ 6.24-6:28 Schedule of Values ....................................."2.6, 14.1 Schedule of Shop Drawingsand Samples Submissions, ...................... ...... 1.2.6, 2.8-2.9 Shop Drawings ........................................ 6.24-6.38 Substantial Completion -- certification of............................6.30.2.3, 14.8-14.9 definition of. .................................................... J1.38 Substitute Construction iMethods or Procedure* ........ 6, 7.2 Substitutes and "Or Equal" lterns:..............................6.7 CONTRACTOR's ExpenK .......... .I ................ 6.7.1.3 FNGINFF..R's Evaluation6.7:3 "Or -Equal.. ................................................... 0.7.1.1 Substitute Construction Methods riii EJCDC GLNERAL CONDITIONS 1910.8 (1990 EDITION) wl CITY OF FORT COLUNIS MODIFICATIONS (REV 9/99) Article or Paragraph Number or Procedures .............................................. 6.7.2 Substitute Items 6:7.1.2 Subsurface and Physical. Conditions -- Drawings of, in or relatitg to,,,,,,,,,,,,,,,,,,,,,,„ 4.2. L2 ENGIlVEER's Review 4.14 general_ ............. ................................... ......... 4.2 Limited Reliance by CONTRACTOR Authorized 4.2.2 Notice of Differing Subsurface or Physical Conditions ......................................... 4.2.3 Physical Conditions.......................................4.2.1.2 Possible Contract Documents Change...............4.2.5 Possible Price andTimes Adjustments .... ,..... _,_.4._.6 Reports and Drawings......................................4.2.1 Subsurface and 4.2 Subsurface Conditions at the Site,,,,,,,,,,,,,,,,,„4.2.1.1 Technical Data.---- ...................:.......:........4.2.2 Supervision-- CONTRACTORs responsibility.. ....... __........... .... ... i; l OWNER shall not supervise ......... .... , 8.9 ENGINEER shall not supervise................9.2, 9.13:2 Superintendence...............................7...................... 6.2 Superintendent, CONTRACTOWs resident...............6.2 Supplemental costs .................. :................. ...:..:....11.4.5 Supplementary Conditions -- definition of.....................................................1.39 principal references to.................1.10, 2.2, 2.7, ............4:2, 4.3, 5.1, 53, SA, 5.6-5.9, ...... I ... 5.11,6.8,6.13,7.4,8.11,9.3,9.I0 Supplementing Contract Documents ..........................3.6 Supplier -- definition of ............ *­ ............. principal references to.......,,;3.7, 6.5, 6.8-6.11, 6.20, ..........................................6.24, 9.13, 14.12 Waiver of Rights ............................. ..:...... .......... 6.11 Surety -- consent to final payment ........................ 14.12, 14.14 ENGINEER has no duty to 9.1'3 Notification of..................................10.1, 10.5, 15.2 qualification of .................................. ...5.1-5.3 Survival of Obligations ........................................... 6.34 Suspend Work, OWNER May .......................1.3,10. 15.1 Suspension of Work and Termination --,,,,,,,,,,,,,,,,,,,,,,IS CONTRACTOR May Stop Work orTerminate ... ................... .................:.......15.5 OWNER May Suspend Work ...... ........................ 15.1 OWNER May Term inate ............................ 1.5.2-15.4 Taxes --Payment by CONI'RAC'TOR .................. .......6.15 Technical Data -- Limited Reliance by CONTRACTOR,,,,,,,,,,,,,,,,, 4.2.2 Possible Price and Times Adjustments ...... ........4.21.6 Reports of Differing Subsurface and Physical Conditions...... .... ..................... N 42.3 Temporary construction facilities .......... .._........ ,........ .1 Article or Paragraph Number Termination_ by CONTRACTOR 15.5 by OWNER .................... S.8, .............. 15.1-15.4 of ENGINEER's employment .............................. 8.2 Suspension of Work-in general .................._,........15 Terms and Adjectives ................................. :............. 3.4 Tests and Inspections -- Access to the Work, by others„....................:....13.2 CONPRACI'OWs responsibilities ......... ......13.5 cost of 13.4 covering Work prior to, .... I ......... : ........... I ... 13.6-13.7 Laws and Regulations (or)_ .......................... ..... 13.5 Notice of Defects..................................:............13.1 OWNER May Stop Work ... ............................13.10 OWNF.R's independent testing ..........................13A special, required by ENGINEER .........................9.6 timely notice required ....................................... 13.4 Uncovering the Work, at ENGNEER's request.............. ..13.8 13.9 Times-- Adjusting..........................................................6.6 Change of Contract......................................... ...12 Computation of................................................17.2 Contract Times --definition of ........................... j.12 day _, ...........................17.2 1 Milestones � 12 Requirements-- appeals.................................................9.10, 16 clarifications, claims and.disputes..................9.1 I, 11.2, 12 Commencement of Contract Times,,,,,,,,,,,,,;,, 2. 3 Preconstruction Conference .............................. 2.8 schedules ......................................... 2.6, 2.9, 6.6 Starting the Work..........................................2.4 Title. Warranty of .............:. .................................... .14.3 Uncovering Work ... ....... ...... .... ........... ........... ..13:8-13.9 Underground Facilities, Physical Conditions -- definition of ...................................................... 1.41 Not Shown cr Indicated...._............................. 4 .3.2 protection of.............................................4.3, 6.20 Shown or Indicated,,,,,,,,,,,,,,,,,,,,,,,,„-„.,,,_,..,.,,,4.3.1 Unit Price Work -- claims ....................... ........................11.9.3 definition of; ...................... 1,42 genera I11.9. 14.1, 14.5 Unit Prices— general 11.3.1 Determination for....................................„..,-„9.10 Use of Premises .. ....... .........": '...,.... 6.16, 6. I8, 6.30.2.4 Utility owners.............................6.13, 6.20, 7.1-7.3, 13.2 Utilization, Partial ........ .......... :1.28. 5.15. 6.30.2.4. 14.10 Value of the Work .............:..........:.......................... 11.3 Values, Schedule of..............................2.6. 2.8-2.9, 14.1 EJCDC GENERAL CONDMONS I910.8 (1990 L:DITION) wI CITY OF FORT COLLINS MODIFICA'11ONS (RF.V 9/97) Variations in Work --Minor Authorized., .................... ; .................6.25, 6,27, 9.5 Article or Paragraph Number Visits to Site --by ENGIYEER.................................... 9.2 _ Waiver of Claims --on Final Payment._. _ -............, 14.15 Waiver of Rights by insured parties..................j.1 I, 6.11 Warranty and Guarantee, General --by CONTRACTOR ............ :................................... 6.30 Warranty of Title, CONTRACTOR's.................. ..... 14.3 Work -- Access to 13.2 byothers ................................ ......... 7 Changes in the....................................................1.0 Continuing the ................................................. 6.29 CONTRACTOR May Stop Work or Terminate...............................................15.5 Coordination of .................................................... 7A Cost of the ................................................. 11.4-11.5 definition of 1.1, A3 neglected by CONTRACTOR——— ...................13.14 otherWork............................................................7 OWNER May Stop Work ................................ .13.10 OWNER May Suspend Work...................j3.10, 15.1 Related, Work at Site ................. I................... 7.1-7.3 Starting the,...................... ................................. .2.4 Stopping by CONTRACTOR ............................. I,5.5 Stopping by OWNER.; ....:..........................15.1-15.4 Variation and deviation authorized minor ........... 3.6 Work Change Directive -- claims pursuant to.............................................10.2 definition of 1.44 principal references to .................... 3.5.3, 10.1-10.2 Written Amendment -- definition of......................................................1.45 principal references to .............. ] A 0, 3.5, 5.10,15,12, ..........................i.6.2, 6.8.2. 6.19, 10.1, 10.4. ...........................1.1.2,12.1,13.12.2,14.7.2 Written Clarifications and Interpretations ...................... ........... 3.6.3. 9.4. 9.11 Written Notice Required -- by CONTRACTOR............................7.1, 9.10-9.11, ........................................... 10.4, 11.2. 111 by OWNER .............._....9.10-9.1l, 10.4, 11.2, 13.14 IN EJCDC GENERAL CONDITIONS 19I0.8 (1990 EDFIIOt� w/ CITY OF FORT COLUNS MODIFICATIONS (REV 9199) (This rage left blank intentionally) xvi EJCDC: GENERAL. CONDITIONS 1910 •S (1990 EDITION) W/CITY OF FORT COLUNS MODIFICATIONS (RF,V 99Q) GENERAL CONDITIONS ARTICLE I--DE[TI IITIONS Wherever used in these General Conditions.or in the other Contract Documents the following terms have the meanings indicated which are applicable to both the singular and plural thereof: 1.1, Addenda --Written or graphic instrument-, issued prior to the opening of Bids which clarify, correct or change. the Bidding Requirements or the Contract Documents. 1.2. Agreement —The written contract between OWNER and CONTRACTOR covering the Work to be performed other Contract Documents are attached to the Agreement and made a part thereof as provided therein. 1.3. Application for Pavme» t- The form accepted by ENGINEER which is to be used by'CON"I'RAG'fOR in requesting progress or final payments and which is to be accompanied by such supporting documentation as is required by the, Contract Documents. 1.4. Asbestos --Arty material that contains more than one ]percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration. 1.5. Bid —The offer or proposal of the bidder submitted on the prescribed form setting forth the prices for the Work to be performed. 1.6. Bidding Documents —The advertisement or invitation to Bid, instructions to bidders, the Bid form, and the proposed Contract Documents (including all Addenda issued prior to receipt of Bids). 1.7, Bidding Requirements --The advertisement or invitation to Bid instructions to bidders, and the Bid form. I.S. Bondr—Performance and Payment bonds and other instruments of security. 1.9. Change Order —A document recommended by ENGINEER, which is signed by CONTRACTOR and OWNER and authorizes an addition. deletion or revision in the Wort:, or an adjustment in the Contract Price or the Contract Timm issued on or after the Effective Date of the Agreement. eement. 1. M Contract Documents —The Agreement, Addenda (which pertain to the Contract Documents), CONTRACI'OR's Bid (including documentation accompanying the Bid and any post Bid documentation submitted prior to the Notice of Award) when attached as an c\hibit to the Agreement, the Notice to Proceed the Bonds, these General Conditions, the Supplementary Conditions, the Specifications and the Drawings as the EJCDC GENERAL CONDrnom 1910-s (tm Ectiticto at CITY OF FORT COLLINS MODIFICATIONS (REV,IP-O 1 same are more specifically identified in the Agreement, together with all Written Amendments, Change Orders, Work Change Directives, Field Orders and ENGIIN-EER's written interpretations and clarifications issued pursuant to pamgraphs3.5, 3.6.1 and 3.6.3 on or after the Effective Date of the Agreement. Shop Drawing submittals approved pursuant to paragraphs 6.26 and 627 and the reports and drawings referred to in paragraphs 4.11 and 4.2.2 are not Contract Documents. 1.11, Contract Price —The moneys payable by OWNER to CONTRACTOR for completion of the Work in accordance with the Contract Documents as stated in the Agreement (subject to the provisions of paragraph 11.9.1 in the case of Unit Price Work). 1.12. Contract Times —The numbers of days or the dates stated in the Agreement: (i) to achieve Substantial Completion, and (ii) to complete the Work so that it is ready for final payment as evidenced by ENGINEER's written recommendation of final payment in accordance with paragraph 14.13. 1.13. CONTRACTOR==The person, fimi or corporation with whom OWNER has entered into the Agreement 1.14. defective —An adjective which when modifying the word Work refers to Work that is unsatisfactory, faulty or deficient in that it does not conform to the Contract Dmuments, or does not meet the requirements of any inspection, reference standard, test or approval referred to in the Contract Documents, or has been damaged prior to ENGINEER's recommendation of final payment (unless responsibility for the protection thereof has been assumed by OR'NER at Substantial Completion in accordancewith paragraph 14.5 or 14.10). 1.15. Drawings --The drawings which show the scope, extent and character of the Work to be furnished and performed by CONTRACTOR and which have been prepared or approved by ENGINEER and are referred to in the Contract Documents. Shop drawings are not Drawings as so defined 1.16. Effective Date of tire Agreement —The date indicated in the Agreement on which it becomes effective, but if no such date is indicated it means the date on which the Agreement is signed and delivered by the last of the two parties to sign and deliver. 1.17. ENGINEER —The person, firm or corporation named as such in the Agreement. 1.18. ENGINEER's Consultant --A person. firm or corporation having I contract with ENGINEER to furnish services as ENGINEER's. independent professional associate or consu Itani with respect to the Projectand who is identified as such in the Supplementary Conditions. 1.19. Field Order —A written order issued by ENGINEER which orders minor changes in the Work in accordance with paragraph 9.5 but which does not involve a change in the Contract Price or the Contract Times. 120. General Requirements —Sections of Division I of the Specifications. 121. Hazardous Waste —The term Hazardous Waste shall have the meaning provided in Section 1004 of the Solid Waste Disposal Act (42 USC Section 6n)3) as amended from time to time. 1 22.a. La+vs and Regulations; Laws or Regtdationss -Any and all applicable laws, rules, regulations, ordinances. codes and orders of any and all governmental bodies, agencies, authorities and courts having jurisdiction. l 22.b. Legal flolictms--shall be those holidays observed by the City of Fort Collins. 1.23. Liens —Liens, .charges, security interests or encumbrances upon real property or personal property. 1.24, hfilestone--A incipal event specified in the Contract Documents relating to an intermediate completion date or time prior to Substantial Completion of all the Work. 1.25. Notice of Award A }written notice by OWNER to the apparent successful bidder stating that upon compliance by the apparent successful bidder With the conditions precedent enumerated therein, within the time specified, OIVNM will sign and deliver the Agreement. L26. Notice. to Proceed —A written notice given by OWNER to CONTRACTOR (with a copy to ENGINEER) fuming the date on which the Contract Times will commence to run and on which CONTRACTOR shall start to perform CONTRACTOR'S obligations under die Contract Documents. 1.27. OIPNER—The public body or authority, corporation, association, firm or person with whom CONTRACTOR has entered into the Agreement and for whom the Work is to be provided 128. Partial Utilization —Use by OWNER of a substantially completed part of the Work, for the purpose, for which it. is intended (or a related purpose) prior to Substantial Completion of all the Work_ L29. PCBs -Polychlorinated biphenyls. 1.30. Petrotetun--Petroleum, including crude oil or any friction thereof which is liquid at standard conditions of temperature and pressure (60 degrees Fahrenheit and 14.7 pounds per square inch absolute), such as oil, petroleum, fuel oil, oil sludge,, oil refuse. gasoline, kerosene and oil mixed with other non-I-Iarardous Wastes and crude oils. 1.3E Project -The total construction of which the Work to be provided under the Contract Documents may be the whole, or a part as indicated elsewhere in the Contract Documents. 1.32.a. Radiouclive XIalerial—Source, special nuclear, or byproduct material as defined by the Atomic Energy Act of EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ C1TY OF FORT Cot.L1 Ns mow [CATIONS (REV 4P000) 1954 (42 USC Section 2011 et seq.) as amended from time to time. 1.32.b. Rezrdar Working Hours-Rettular working hours are defined as 7:00am to 6:00pnt unless otherwise specified in the General Requirements. 1,33. Resident Project Representative —The authorized representative of ENGINEER who may be assigned to the site or. any part thereof. 1.34. Samples —Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the Work will be judged 135. Shop Draxdngs--All drawings; diagrams, illustrations, schedules and other data or information which are specifically prepared or assembled by or for CONTRACTOR and submitted by CONTRACTOR to illustrate some portion of the Work. 1.36. Spec cations --Those portions of the Contract Documents consisting of Written technical descriptions of materials equipment; construction systems,. standards and workmanship as applied to the Work and certain administrative details applicable thereto. 1.37. Subcontractor --An individual, firm or corporation having a direct contract with CONTRACTOR or with any other Subcontractor for the performance of a part of the Work at the site. 1.35. Substantial Completion --The Work (or a specified part thereof) has progressed to the point where, in the opinion of ENGINEER as evidenced by ENG]INEER's definitive certificate of Substantial Completion, it is sufficiently complete, in accordance with the Contract Documents, so that the Work (or specified part) can be utilized for the purposes for which it is intended: or if no such certificate is issued, when the Work is complete..and.ready for final payment as evidenced by ENGiNEER's written recommendation of final payment in accordance with paragraph 1.4.13. The terms "substantially complete' and "substantially completed" as applied to all or part of the Work refer to Substantial Completion thereof. 1.39. Supplementary Conditions —The part of the Contract. Documents which amends or supplements these General Conditions. 1.40. Supplier —A manufacturer, fabricator, supplier, distributor, materialman or vendor having a direct contract With CONTRACTOR or with any Subcontractor to furnish, materials or equipment to be incorporated in the Work by CONTRACTOR or any Subcontractor. 1.41. Unclergrotord Facilities —All pipelines, conduits, ducts, cables, wires, manholes; vaults, tanks, tunnels or other such facilities orattachments, and any encasements containing such facilities which have been installed underground to furnish any of the following services or materials: electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television. sewage and drainage removal. traffic or other control systems or water. 1.42.. thrit Mee {York —Work to'.be paid for on the basis of unit prices. 1.43. Work —The entire completed construction or the various separately identifiable parts thereof required to be furnished under the Contract Documents. Work includes and.is the result of performing or furnishing labor and furnishing and incorporating materials and equipment into the construction, and performing or furnishing services and furnishing documents, all as required by the Contract Documents, 1.44. Work Change Urrective—A written directive to CONTRACTOR, issued on or alter the Effective Date of the Agreement and signed by OWNER and recommended. by ENGINEE& ordering an addition deletion or revision in' the Work, or responding to differing or unforeseen physical conditions under which the Work is to be performed as provided in paragraph 4.2 or 4:3 or to emergencies under paragraphfi23. A Work Change Directive will not change the Contract Price or the Contract Times, but is evidence that the. parties expect that the change directed or documented by a Work Change Directive will be incorporated in a subsequently issued Change Order following negotiations by the panics as to its effect, if any, on the Contract Price or Contract Times as provided in paragraph 10.2. 1.45. Witten Antenzibw tt—A «Tittcn amendment of the Contract Documents, signed by OWNER and CONTRACTOR on or after the Effective Date of the Agreement and normally dealing with the nonengineering or nontechnical rather than strictly construction -related aspects of the Contract Documents, ARTICLE 2—PRELLbIINARY MATTERS DeGvery ofBont 2.1. When CONTRACTOR delivers the executed Agreements to OWNER, CONTRACTOR shall also deliver to OWNER such Bonds as CONTRACTOR may be required to furnish in accordance with paragraph -5.1. Copies of Document 2.2 OWNER shall furnish to CONTRACTOR up to ten copies (unless otherwise specified in the Supplementary Conditions) of the Contract Documents as are reasontlbly necessary for the execution of the Work. Additional copies will be furnished, upon request, at the cost of reproduction Commencement of Contract Times; Notice to Proceed• 2.3. The Contract Times will commence to tun on the thirtieth day after the Effective Date of the Agreement, or, EXDC GENERAL CONDITIOM 1910-8 (1990 Editiar) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4r000) if a Notice to Proceed is given, on the day indicated in the Notice to Proceed. A Notice.to Proceed may be given at any time within thirty days after the Effective Date of the Agreement of-Bid-opening•or-the-thirtieth-day-after-the.6tY dive -fate of-the-Agre,an ent-whlcheYer-date-is-earlier: Starting the Work: 2.4. CONTRACTOR shall start to perform the Work on the date when the Contract Times commence to tun. but no Work shall be done at the site prior to the date on which the Contract Times commence to run. Before Starting Construction: 2.5. Before undertaking each part of the Work, CONTRACTOR shall carefully study and compare the Contract Documents and check and verify pertinent figures. shown thereon and all applicable field measurements: CONTRACTOR shall promptly report in writing to ENGNFF..R. any conflict, error,. ambiguity or discrepancy which CONTRACTOR may discover and shall obtain a written interpretation or clarification from ENGINEER before proceeding with any Work affected thereby; however, CONTRACTOR shalf not. be liable to OWNER or ENGNEF,R for failure to report any conflict; error, ambiguity or discrepancy in the Contract Documents, unless CONTRACTOR knew or reasonably should have known thereof. 16. Within ten days after doe Effective Date of the Agreement (unless otherwise specified in the General Rcquiremcnts), CONTRACTOR shall submit to ENGINEER for review: 2:6.1. a preliminary progress schedule indicating the times (numbers of days or dates) for starting and completing the various stages of the Work, including any Milestones specified in the Contract Documents; 2.6.2. a preliminary schedule of Shop Drawing and Sample submittals which will list each required submittal and the times for submitting, reviewing and processing such submittal; ? 6.2.1. In no ease will a schedule be acceptable which allows less than 21 calendar days for each review by Engineer. 2.6.3. A preliminary schedule of values for all of the Work which will include quantities and prices of items aggregating the Contract Price and will subdivide the Work into component parts in sufficient detail to serve as the basis for progress. payments during construction Such prices will include. an appropriate amount of overhead and profit applicable to each item of Work. 2.7. Before any Work at the site is started. CONTRACTOR and GWNER shall eeeh deliver to the etllef OIWi ER with copies to iciAntified ; the c,,..'.a.....entar-y C'e;da:.R n II'NGfNFEf� certificates of insurance (and other evidence of insurance Feasenebly- roquest , reuuested by OWNER) which CONTRACTOR and QAENER Fespeofively af is required to purchase and maintain in accordance with paragraphs 5.47F6-and 43. Preconstruetion Conference: 2.8. Within twenty days after the Contract Times start.to run, but before any Work, at the site is started, a conference attended by CONTRACTOR. ENGINEER and others as appropriate will be held to establish a working understanding among the parties as to the Work and to discuss the schedules referred to in paragraph 2.6, procedures for handling Shop Drawings and other submittals processing Applications for Payment and maintaining required records. Initia v Acceptable Schedules- 2:9.. unless otherwise provided in the Contract Documents -'� ^aew before any work at the site be a conference attended by CONTRACTOR, ENGINEER and others as appropriate desi fats ted by OWNER will be held to review for acceptability to ENGINEER as provided below the schedules submitted in accordance with paragraph 2.6. and Division i - General Reqgiremenm, CONTRACTOR shall have an additional ten days to make corrections and adjustments and to complete and resubmit the schedules. No progress payment shall be made to CONTRACTOR until the schedules are submitted to and acceptable to ENGINEER as provided below. The progress schedule will be acceptable to ENGINEER as providing an orderly progression of the Work to completion within any specified Milestones and the Contract Times, but such acceptance will neither impose on ENGINEER responsibility for the sequencing, scheduling or progress of the Work nor interfere with or relieve CONTRACTOR from CONTRACTOR's full responsibility therefor. CONTR4CTOR's schedule of Shop Drawing and Sample submissions will be acceptable to ENGINEER as providing a workable arrangement for reviewing and processing the required submittals CONTRICTORs schedule of values will be acceptable to ENGI`i LEER as to form and substance. ARTICLE 3--COiNTRACl' DOCUMENTS: INTENT, AINtEtNDING, REUSE Intent: 3.1. The Contract Documents. comprise the entire agreement between OWNER and CONTRACTOR concerning the Work: The Contract Documents are complementary; what is called for by one is as binding as if called for by all. The Contract Documents will be construed in accordance with the law of the place of the Project. 3.2_ It is the intent of the Contract Documents to EJCDC UENEM CONDMONS 1910-8 (1990 Ec itim) w1 CITY OF FORT COLLINS btODllICA,r1ONS (RL'V 412000) describe a functionally complete Project (or part thereof) to be constructed in accordance with the Contract Documents. Any Work, materials or equipment that may reasonably be inferred from the Contract Documents or from prevailing custom or trade usage as being required to produce the intended result will be furnished and performed whether or not specifically called for. When words or phrases which have a well-known technical or construction industry or trade meaning are used to describe Work. materials or equipment, such words or phrases shall be interpreted in accordance with that meaning. Clarifications and interpretations of the Contract Documents shall be issued by ENGINEER as provided in paragraph 9.4. 3.3. Reference to Standards and Specifications of Technical Societies. Reporting and Resohing Discrepancies.• 3.3.1. Reference to standards, specifications, manuals or codes of any technical society, organization or association, or to the Laws or Regulations of any governmental authority, whether such reference be specific or by implication, shall mean the latest standard,, specification, manual, code or Laws or Regulations in effect at the time of opening of Bids (or, on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents: 3.3.2. if, during the performance of the Work, CONTRACTOR discovers any conflict, error, ambiguity or discrepancy within the Contract Documents or between the Contract Documents and any provision of any such Law or Regulation applicable to the performance :of the Work or of any such standard, specification, in or cods or of any instruction of any Supplier referred to in paragraph 6.5. CONTRACTOR shall report it to ENGINEER in writing at once, and, CONTRACTOR shall not proceed with the Work affected thereby (except in an emergency as authorized by paragraph 6.23) until an amendment or supplement to the Contract Documents has been issued by one of the methods indicated in paragraph 3.5 or 3.6; provided however, that CCNTFUNCTOR shall not be liable to OWNER or ENGINEER for failure to report any such conflict, error, ambiguity or discrepancy unless CONTRACTOR knew or reasonably should have known thereof. 3.3.3. Except as otherwise specifically stated in the Contract Documents or as may be provided by amendment or supplement thereto issued by one of the methods indiaited in paragraph 3.5 or 3.6, the provisions of the Contract Documents shall take precedence in resolving any conflict, error, ambiguity or discrepancy between the provisions of the Contract Doctuments and: 3.3.3.1. the provisions of any such standard. specification, manual, code or instruction (whether or not specifically incorporated by reference in the Contract Documents); or 3.3.3.2. the provisions of any such Laws or Regulations applicable to the performance of the Work (unless such an 'interpretation of the provisions of the Contract Documents would result in violation of such Law or Regulation). No provision of any such standard, specification, manual, code or instruction shall be effective to change the duties and responsibilities of OWNER, CONTRACTOR or ENGINEER, or any of their subcontractors, consultants, agents or employees from those set forth in the Contract Documents, nor shill it be effective to assign to OWNER. ENGINEER or any of F.NGiNF,ER's Consultants, agents or employees any duty or authority to supervise or direct the furnishing or performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of paragraph 9.13 or any other provision of the Contract Documents. 3.4. Whenever in the Contract Documents the terms "as ordered", "as directed", "as required", "as allowed", "as approved" or terms of like effect or import are used, or the adjectives "reasonable", "suitable", "acceptable", "proper" or "satisfactory" or adjectives of like effect or import are used to describe a requirement, direction, review or judgment ofEi IGINGER as to the Work, it is intended that such requirement, direction, review or judgment will be solely to evaluate, in general, the completed Work for compliance with the requirements of and information in the Contract Documents and conformance with the design concept of the completed Project as a functioning whole as shown or indicated in the Contract Documents (unless there is a specific statement indicating otherwise). The use of any such term or adjective shall not be effective to assign to ENGINUER any duty or authority to supervise or direct the furnishing or performance of the Work or any duty or authority to undertake responsibility contrary to the provisions of paragraph 9.13 or any other provision of the Contract Documents. Anrenr6ng and Supplementing Contract Documents. 15.. The Contract Documents may be amended to provide for additions, deletions and revisions in the Work or to modify the terms and conditions thereof in one or more of the following ways: 3.5.1. a formal Written :amendment, 3.5.2. a Change Order (pursuant to paragraph 10.4), or EJCDC GENERAL CONDIT101,519I0-3 (I M Edition) iv/ CITY OF FORT COLLINS MODIFICATIONS (REV 4R000) 3.5.3. a Work Chtutge Directive (pursuant to paragraph 10.1). 3.6. In addition, the requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work may be authorimd, in one or more of the following ways: 3.6.1. A Field Order (pursuant to paragraph 9.5), 3.6.2. EI1GINEER's approval of a Shop Drawing or Sample (pursuant to paragraphs 6.26 and 6.27), or 3.6.3. ENGINEER's written interpretation or clarification (pursuant to paragraph 9.4). Reuse of Documents: 3.7. CONTRACTOR, and any Subcontractor or Supplier or other person or organization performing or furnishing any of the Work under a direct or indirect. contract with OWNER (i) shall not have or acquire any title to or ownership rights in any of the Drawings, Specifications or other documents (or copies of any thereof) prepared by or bearing the seal of ENGINEER or ENGiNEER's Consultant, and (ii) shall not reuse any of such Drawings, Specifications, other documents or copies on extensions of the Project or any other project without written consent of OWNER and ENGINEER and specific written verification or adaptation by ENGINEM ARTICLE 4-AVAILABILITY OF LANDS; SUBSURFACE AND PHY5ICA1:, CONDITIONS; REFERENCE POINTS : vailabiGryofLands: 4.1. OWNER shall furnish, as indicated in the Contract Documents, the lands upon which the Work is to be performed, rights -of -way and easements for access thereto, and such other lands which are designated for the use of CONTRACTOR Upon -reasonable written•request statement: o€teeord-legal-titla-end-legs I-description-of=the Itrrtds-upon-whit;h-the-Work-is-to-be-performed-and OVIrNER'y-interest-thereirt-as-necessary-forgivirt�; rtpticx o� or-fFluFL—a—macharut>'S—hdlT—ago tnSl—b1rG11—IandS—m OWNER shall identify any encumbrances or restrictions not of general application but specifically related.to use of lands so furnished with which CONTRACTOR will have to comply . in performing the Work. Easements for permanent structures or permanent changes' in c6sting facilities will be obtained and paid•for by OWNER, unless otherwise provided in the Contract Documents. If CONTRACTOR and OWNER are unable to agree on entitlement to or the amount or extent of any adjustments in the Contract Price or the Contract Times as a result of any delay in OWNER's furnishing these lands, rights -of - way or easements. CONTRACTOR may make a claim therefor as provided in Articles 11 and 12. CONTRACTOR shall provide for all additional lands and access thereto that may be required for temporary construction facilities or storage of materials and equipment. 4.2. Subsurface and Physical Conditions: 4.2.1: Reports and. Drawings:. Reference is made to the Supplementary Conditions for identification of: 4.2.1.1. Subsurface Conditions: Those. reports of explorations and tests of subsurface conditions at or contiguous to the site that have been utilized by ENGINEER in preparing the Contract Documents; and 4.2.1.1. Plr)sical Cori&tions: Those drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the site (except Underground Facilities) .that have been utilized by ENGINEER in preparing the Contract Documents. 4.2.2. Limited Reliance by COAIMCTOR 4whorized- Tedmical Data:, CONTRACTOR may rely upon the general accuracy of the "technical data" contained in such reports and drawings, but such reports and drawings are not Contract Documents. Such "technical data" is identified in the Supplementary Conditions. Except.tbr such reliance on such "technical data", CONTRACTOR may not rely upon or make any claim against OWNER, ENGINEER or any of ENGINEER'S Consultants with respect to: 4.22.1. the completeness of such reports and drawings for CONTRACTOR's purposes, including, but not limited to, any aspects of the means, methods, techniques; sequences and procedures of construction to be employed by CONTRACTOR and safely precautions and programs incident thereto, or 4.2.22. other data, interpretations, opinions and information contained in such reports or shown or indicated in such drawings, or 4.22.3. any CONTRACTOR interpretatim of or conclusion drawn from any "technical data" or any such dai<a, interpretations; opinions or irdornation. 4.2.3. Notice of D erit Subsurface or Physical Conditiwts. If CONTRACTOR believes that any subsurface or physical condition at or contiguous to the site that is uncovered or revealed either: 4.2.3.1. is of such a nature as to establish that any "technical daLt" on which CONTRACTOR is entitled to rely as provided in paragraphs 42.1 and 4.22 is materially inaccurate, or 4.2.3.2. is of such a nature as to require a change in the Contract Documents, or 4.2.3.3- differs materially from that shown or EJCVC GENERAL CONDMONS I910S (1990 Edition) col CITY OF FORT COLLINS MODIFICATIONS (.REV 4P000) indicated in the Contract Documents, or 4.2.3.4. is of an unusual nature, and differs materially from conditions ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract Documents; then CONTRACTOR shall, _ promptly immediately after becoming aware thereof and before further disturbing conditions affected thereby or performing any Work in connection therewith (except in an emergency as permitted by paragraph6.23), notify OWNER and ENGINEER in writing about such condition. CONTRACTOR shall not further disturb such conditions or perform any Work in connection therewith (except as aforesaid) unfit receipt of written order to do so. 4.2.4. ENGINEER's Review: ENGINEER will promptly review the pertinent conditions, determine the necessity of OWNER's obtaining additional exploration or tests with respect thereto and advise. OWNER in writing (with a copy to CONTRACTOR) of hjNGfNEER's findings and conclusions. 4.2.5. Possible Contract Dactunents Change: If ENGINEER concludes that a change in the Contract Documents is required as a result of a condition that meets one or more of the categories in paragraph 4.2.3, a Work Change Directive or a Change Order will be issued as provided in Article 10 to reflect and document the consequences of such change. 4.2.6. Possible Price and J'imes 4,fustmenLT: An equitable adjustment in the Contract price or in the Contract Times, or both, wilt be allowed to the extent that the existence of such uncovered or revealed condition causes an increase or decrease in CONTRACTOR's ccot of, or time required for performance of; the Work; subject, however, to the following: 4.2.6.1. such condition must meet any one or more of the categories described in paragraphs 4.2.3.1 through 4:2.3.4, inclusive; 4.2.6?. a change in the Contract Documents pursuant to paragraph 4.2.5 will not be an automatic authorization of nor a condition precedent to entitlement to any such adjustment; 4:2.61 with respect.,to Work that is paid for on a Unit Price Basis, any adjustment in Contract Price will be subject to the provisions of paragraphs 9.1 U and 11.9; and 4.2.6.4. CONTRACTOR shall not be entitled to any adjustment in the Conin+ct Price or Times if; 4.2.6.4.1. CONTRACTOR knew of the existence of such conditions at the time CONTRACTOR made a final commitment to OWNER in respect of Contract Price and Contract Times by the ' Fea IXa7.lwb t wt0. +-o IL F d Rs 4 (Mit. •f?u. � - U4vrm�'ILL -- PUMP N—E �_: 91 p o. sua Lv AM �L V a .1 _- .r•k ue,a -�,a - .www�n. �� � 6.w�a .,. ,tom+. . .I aaere.e.- - � _ • :nrlt�eaT '� • .. � � _ .a la. .. ��e.eee-_. � tt�-EL5W410N � ha/I�ION � �••••• � � � i a i - I II G N SECT. TH 0.0 SOU7H WALL OF PUMP HOUSE It SECT, NRU NORTH WALL Of PUMP HOUSE <6b 6'+f a elbT / WfST W4LL5 SINI U.0.) a6.b 'e'+ ' < ai�Q '. :_'.-, ,�IN,lyr �l - .. _ �. w �" ,.�. n-- y� These as -built tlrarl nas have been prepared. 1n par[q on the Casts of information co Di tad nE f-rnl:— by otM1erp. The not be reap-ns101e far any err- -r omi ss Ions rhi ch have been tncorp-rates into this tl-cameo[ a ult.r iyCw LG�I / PLAN 6ecT oN K 3d r� Nrrr+r w ki— 9 PIT DETAILS IN ICE MAI NT. AM. AE 10 FLAGPOLE DETAIL JJ F Jw ... r �`+ ® /,. any „' \ k ® \ h J•l - .. - .,.:.0 er.w me/ .z,. .+.ua .... ., /".. /z, --� '8 -� Ld,41s' ( •) III.. QHill ! 7 G. C - ~ EDGE OF PIT IN ICE MAINT. 0.M. 14'+ 8 PIT 6EAM OETALL h"+I'-e' /.b 14"• ho' t�.W.lydl. _ a -L2 `"Ah�I`H A2 t'>Iltr fW lz 6Pd.Wl rC }WGM zQ - .. U - '0 a ] F nsu:. cf Lr Z -e-.W 41 _ • uw.. T __- t - UT ® - - i {.�:j,- �'TIq.1L�FTx':�al:rdLP+'1 3� 2 I.,:y� �'eertAO COINN6 DOo¢ 3 ALL 5�'T �u�bJb l T 4 t>• .II' f risD lue 0-oe IN 5 HEAD AT OVERHEAD COILIt)G 00.. ` JAI. AT OVERHEAD COILING 09. A4.6 A46 '3p�ll-o G Y3g Flo i Y al0 submission of a bid or becoming bound under a negotiated contract; or 4.2.6.4.2. the existence of such condition could reasonably have been discovered or revealed as a result of any examination, investigation; exploration, test or study of the site and contiguous areas required by the Bidding Requirements or Contract Documents to be conducted by or for CONTRACTOR prior to CONTRACTOR's making such final commitment; or 4.2.6.4.3. CONI'RA(,-I'OR failed to give the written notice within the time and as required by paragraph 4.2.3. If OWNER and CONIRACTOR are unable to agree on entitlement to or as to the amount or length of any such equitable adjustment in the Contract Price or Contract Times, a claim may be made therefor as provided in Articles I I and I) However, OWNER, ENGIiNIEER and ENGINEER's Consultants shall not be liable to CONTRACTOR for any claims, costs, losses or damages sustained by CONTRACTOR on or in connection with any other project or anticipated project 4.3. Pl±vsieal Conditions -Underground Facilities: 4.3.1. Shown orindicated: The information and data shown or indicated in the Contract Documents with respect to existing Underground Facilities at or contiguous to the site is based on information and data furnished to OWNER or ENGINEER by the owners of such Underground Facilities or by others. Unless it is otherwise expressly provided in the Supplementary Conditions: 4.3.1.1. OWNER and ENGINEER shall not be responsible for the accuracy or completeness of any such information or data; and 4.3.11 The cast of all of the following will be included in the Contract Price and CONTRACTOR shall have full responsibility for: (i) reviewing, and checking all such information and data, (ii) locating all Underground Facilities shown or indicated in the Contract Documents,(iii) coordination of the Work with the owners of such Underground Facilities during construction, and (iv) the safety and protection of all such Underground Facilities as provided in paragraph6.20 and repairing any damage thereto resulting from the Work. 4.3.2. Not Shown or Indicated: If an Underground Facility is uncovered or revealed at or contiguous to the site which was not shown or indicated in the Contract Documents. CbN'fRACTOR shall. promptly immediately after becoming aware thereof and before further disturbing conditions affected thereby or lxrforming any Work in connection therewith (except in an emergency as required by .paragraph 6.23), identify the owner of such Underground Facility and EXI)C GENERAL CONDITIONS 19105 (1990 Edition) wl CITY OF FORT COLLINS h1ODIF1CA BONS (REV 4f_000) give written notice to that owner and to OWNER and TN-R. ENGINEER will promptly review the Underground Facility and determine the extent, if any, to which a change is required in the Contract Documents to reflect and document the consequences of the existence of the Underground Facility. If ENGINEER concludes that a change in the Contract Documents is required, a Work Change Directive or a Change Order will be issued as provided in Article 10 to reflect and document such consequences. During such time, CONTRACTOR shall be responsible for the safety and protection of such Underground Facility as provided in paragraph 6.211. CONTRACTOR shell may be allowed an increase in the Contract Price or an extension of the Contract Times, or both, to the octent that they are attributable to the. existence of any Underground Facility that was not shown or indicated in the Contract Documents and that CONTRACTOR did not know of and could not reasonably have been cxlxcted to be aware of or to have anticipated. IfOWNER and CONTRACTOR are unable to agree on entitlement to or the amount or length of any such adjustment in Contract Price or Contract Times, CON"I'RACTOR may make a claim therefor as provided in Articles I 1 and 12. However, OWNER, ENGiNEFR and ENGINEF.R's Consultants shall not be liable to CONTRACTOR for any claims, casts, losses or damages incurred or sustained by CONTRACTOR on or in connection with any other project or anticipated project. Reference Points• 4.4. OWNER shall provide engineering surveys to establish reference points for construction which in ENGINEER's judgment are necessary to enable CONTRACTOR to proceed with the Work. CONTRACTOR shall be responsible for.laying out the Work, shall protect and preserve the established reference points and shall make no changes or relocations without the prior written approval of OWNER CONTRACTOR shall report to ENGINEER whenever any reference point is lost or destroyed or requires relocation because of necessary changes in grades or locations, and shall be responsible for the accurate replacement or relocation of such reference points by professiomdly qualified personnel. 4.5. Asbestos, PCBs, Petroleum, Ua,zardous Chaste or Radioadive Material: o 4.5.1. OWNER shall be responsible for any Asbestos, PCBs, Petroleum, hazardous Waste or Radioactive Material uncovered or revealed at the site which was not shown or indicated in Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work and which may present a substantial danger to persons or property exposed thereto in connection with the Work at the site. OWNER shall not be responsible for any such materials brought to` the site by CONTRACTOR, Subcontractors, Suppliers or anyone else for whom CONTRACTOR is responsible. d-5?-C-OWR-r\6TORshall-intmedintely.-(i)•step-all O�h ancl-iltareeArr�;enfirnr suoh-notice-irt-writing)—OtFR-shall-promptly. consult-with-Ei�iGT�iEER-c�tncerrtir>t;-the-neei�sitp-Coe 04R-to-ratain-a-<tua li Tied-expaR-to•avaluata-such ha GON-'PR AGFOI2 shalt•not-bn required -to resume-1ltorlE anwrequired-perrn its-related-thereto-and-detiveie&to r*g thai and -any $tle6Eer1 .......: . 1..... heP; rendered safi� for the re5umpter—, t ar nd. m=zz... may, bo--esumed- safely. tr nrs-�r.WE T-and CO- N-'FRAGt'OR-eannot-agree-as-t-- entidement,te -eF �1or1«app,=ga ar--ash-special-conditions-under which Work is ffi either p" may therefor As provided Articles 11 and lz 60ArFR\6FOR-does-not-agree-to-resume-:ach-wtxk aimsdous eettdition-eFitt-such-a€€eeted-area-to-�,�'^`e�f�am the �5 eFk1 if QMP-s;WR d- r4nrrru AGTOR rt'ar,YT 'S+�T�-ar1[Tc'�Sx�Y Tcrc'r+\--oamriii agree-a%Ao-entitlement-to-or-the-amount-or-etient-ofnn et—T--.inc� either-party-may-make-a-cl"n-therefor-as-provided-in 4EtieiCs-f 1-d--��—v11 z -a`1r M'D sueh deleted portion-o -the-W4)rk-perforitted-Uy-OWNER's-own €oices or-others-in-nccordartce-with-flrticle-7- Rep lations-OVIN R-shaII-indemni€y-and-hold harmless—C-ON-TRAE�TOR,-Subcaitractorsc officers—directors,—employees� agants=other consultants-and-subwntmstars-o€-each-and-any-of own-neghgertee: 4.5.5. The .. C 4 A 1 -! 12 Ar "at intended to Waste revealed at the SRe- EJCDC.GENERAL COmnoNs 1910-8 (1990 Ediliaa) wf C1TY OF FORT COLLIM MODIFICATIONS (REV 4,1000) ARTICLE 5--BONDS A1N'D LNSURANCE Performance, Payment and Other Bonds. - 5.1. CONTRACTOR shall furnish Performance and Payment Bonds, each in an amount at least equal to the Contract Price as security for the faithful performance and payment of all CONTRACTOWs obligations under the Contract Documents. These Bonds shall remain in effect at least until one year after the date when final payment becomes due, except as provided otherwise by Laws or Regulations or by the Contract Documents. CONTRACTOR shall also furnish such other Bonds as arc required by the Supplementary Conditions, All Bonds shall be in the form prescribed by the Contract Documents except as provided otherwise by Law:.- or Regulations and shall be executed by such sureties as are named in the current list of "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies" as published in Circular 570 (amended) by the Audit Staff, Bureau of Government Financial Operations, U.S_ Treasury Department All Bonds signed by an agent must be accompanied by a certified copy of such agent's authority to act. 5.2. If the surety on any Bond famished by CONTRACTOR is declared a bankrupt or becomes insolvent or its right to do business is terminated in,any state where any part of the Project is located or ii ceases to meet the requirements of paragraph 5.1, CONTRACTOR shall within ten days thereafter substitute another Bond and surety, both of which must be acceptable to OWNER: 5.3. Licensed Sureties and Insurer. ; C.'ertifrcaies of Insurance: 5.3.1. All Bonds and insurance required by the Contract Documents to be purchased -and maintained by OWNER or CONTRACTOR shall be obtained from surety or insurance companies that are duly licensed or authorized in the jurisdiction in which the Project is located to issue Bonds or insurance policies for the limits and coverages so required Such surety and insurance companies shall also meet such additional requirements and qualifications as may be provided in the Supplementary Conditions. 5:3.2. CONTRACTOR shall deliver to OWNER, with copies to each additional insured identified in the Supplementary Conditions, certificates of insurance (and other evidence of insurance requested by OWNER or any other additional insured) which CONTRACTOR is required to purchase and maintain in accordance with paragraph 5.4. QVA,113R--shall additionahinsured-identified-in-the-Supplementary nce witli paragraphs 5-6 and 5.7- hereef CONTRACTOR's Liability Insurance: 5.4. CONTRACTOR shall purchase and maintain such liability and other insurance as is appropriate for the Work being performed and furnished and as will provide protection from claims set forth below which may arise out of or result from CONTRACTOR's performance and furnishing of the Work and CONTRACTOR's other obligations under the Contract Documents, whether it is to be performed .or furnished by CONTRACTOR, any Subcontractor or Supplier; or by anyone directly or indirectly employed by any of them to perform or furnish any of the Work, or by anyone for whose acts any of them may be liable: 5.4.1. claims under workers' compensation disability benefits and other similar employee benefit acts; 5.4.2. claims for damages because of bodily injury, occupational sickness or disease. .or death of CONT RAcTOR's employees; 5A.3. claims for damages because of bodily injury, sickness or disease, or death of any person other than CONTRACTOR's employees; 5:4:4-claims-for-dnmage_s-insured-by-customary rage - a a,,. , m.a. r indirectty-relate�-tat ^ cxh�reasen; 5.4.5. claims for damages, other than to the Work itself because of injury to or destruction of tangible property wherever located, including loss of use resulting therefrom; and 5.4.6. clauns for damages b;crause of bodily injury or death of any person or property damage arising out of the ownership, maintenance or use of any motor vehicle. The policies of insurance so required by this paragraph 5.4 to be purchased and maintained shall: 5.4.7. with respect to imwranoe required by paragraphs 5.4.3 through 5.4.6 inclusive and 5.4.4, include as additional insureds (subject to any customary exclusion in respect, of professional liability), OWNER ENGINEER; ENGI-NEER's Consultants and any other persons or entities identified in the Supplementary Conditions, all of whom shall be listed as additional insureds, and include coverage for the respective officers and employees of all such additional insureds; 5.4.3. include the specific coverages and be written for not less than the limits of liability provided in the Supplementary Conditions or required by Laws or Regulations, whichever isgreater, 5.4.9. include completed operations insurance; EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) wt CITY OF FORT COLLIM MODIFICATIONS (REV 4r000) 5.4.10. include contmaual liability insurance covering CONTRACTOR's indemnity obligations under paragraphs 6.12, 6.16 and 6.31 through 6.33; 5A.11. contain n provision or endorsement'that the coverage afforded will not be cancelled, materially changed or renewal refused witil at least thirty days' prior written notice has been given to OWNER and CONTRACTOR and to each other additional insured identified in the Supplementary Conditions to whom a certificate of insurance has been issued (and the certificates of insurance famished by the CONTRACTOR pursuant to paragraph 5.3 2 will so provide); 5.4.12. remain in effect at least until final payment and at all timesthereafter when CONTRACTOR may be correcting, removing or replacing ckfective Work in accordance with paragraph 13.,12; and 5.4.13. with respect to completed operations insurance, and any insurance coverage written on a claims -made basis, remain in effect for at least two years after final payment (and CONTRACTOR shall furnish OWNER and each tither additional insured identified in the Supplementary Conditions to whom a certificate of insurance has been issued evidence satisfactory to OWNER and any such additional insured of continuation of such insurance at final payment and one year thereafter). Oi NER'sLiabilityInsurance: 5.5. in addition to insurance required to be provided by CONTRACTOR under paragraph 5.4, OWNER, at OWNER's option,. may purchase and maintain at OWNI ER's expense OWNER's overt liability insurance as will protect OWNER against claims which may arise from operations under -the Contract Documents. Propert}, Insurance: S:Ca--IJn lass-otheawisa-prov idetf-in-the-Supplementary Eonditions,-4W'ti'TR sblatl-purGhasc�--and-maintatfl of-tha-full-replasalitent-cost-ihereo�(subject to -stash clecttactible--amoun[s-as-mey-tx-provieiacl-in-tfw SuppkmentaF•v-�ortditiemy-or-rcx{uiratf-by-haws-and Ragulations).-This•irtsttr<a nca•sha ll: &6:1—iraelutle—the—interests—of—OW:�FfiR; i NQ JratatteS-aclantlf itxl-Ln-t}ll!-.SklpplCmenlHFy-COnditlkMS; each•of-whtxn-is-deemed•to-have•an-insurable-interest taracbslttlll-ba-listed as-an-insureti-oFetkbitiona}-insured; 3:6�-6e-wFtktrn-on-a-Bntidc�9-l2usk=B11-Ftsl�oF open per-il , .e following pet lTftre, lightning —extended 9 eovzraga-chali-vnndalisnt-anti-ntakicious-tifischiat; eAfthquake, collapse, debris removal, demalitiDn 5:63--include-expen:r-im,urred-in-the-rgydir-or replacement of any-insured-property-(ificluding-but-not areltitnetsr -... or ahatother-loeation-thtihwas.agreed-to-in-wnting-hy provided that be n inaluded in anymerx wemmended by ENGDMER�ffix] 5:6:S-brrmaintained-itrelieet--until- anal-paymen" trade -a tlttrw-day,e-written-notice-to-eaoh-other-addnional IaMHad- o_s-may-be-required-by-the-Supplementary-t onditk)m-or •Ontina4 iplefflOntffly is deer;alto have -an insurable-utterea-artd� R-be-hsted-as 5.8. Ali ate Peheies (and the eenifleateg ethafeiqui•e t to be purohmed And maintained-by-4Vk�'TI�in-accordatne-with-paragraphs-S:G coverage -afforded -will -not -be -cancelled -or -materially chaff dad-uFrartawal•ra€ttsad-urttil-at least-thirEy-days'-prior written--notice-has--been-given-to-OIRNER--and whom-n-certifiente-of-itY-uranea-has-been-i .sued -and -will contain —waiver -provisions —in —accordance —with paeagsapk z'Fl- 5.9. OWNER shall not be responsible for purchasing andmaintaining any, property insurance to protect the interests of CONTRACTOR, Subcontractors or others in identt6ed-in-Use-SupQ en mtaty-Gondition T-he-risk-of less wit tsueh- such-loss-•and-if-arV-oF- h m-wishes-property-inwranca coverag�-taitEn=the-limits-of-such-amounts,-each-miy purchase-and-maintain-ii-at-the-purehnset's owrt-erpertsa. 5-l0-1f-60N=f-R-4GFOR-reyursts-irt writittg thaE-ether Special insuraiwe-h— -• - raw........ n.,ta. +tr.:tt....-Amendment. lyric ---to EJCDC GENERAL CONDMONS 191" (1990 Edition) 10 w/ CITY OF FORT COLLI NS MODa1CATIONS (REV 4,2000) contmaneatitanho�il>a-1Nork ahtha-silo-0W�1F�sha{l-in VffiFhtg R6i` d _ FIb40F9R- 5.11. __W eiveFef4Zk*tS -5-1-1-1-OV44El-and-60r�TRAC-TOR-intend-that-all policies-purchnsad-in•accordance-with-paragmphs i:6 Subcontractors —ENGINEER, EG1YBERs insureds-or-additional-itKureds-in-such-policies-and will pFevide primary eevemge for. All 1A.-Ses And damages eaused by the perils rev red-thereby—,41 sueh-pelie.w.+ W in the event of pa5"ent ef aRy less or- e th iilSkrrB . - tha-tnsureds-er-ttciditienel-}r�airds--Ehcraundar: OWNER and GONTRA,14OR waiy�� a6h Oti,._ Rd th0if _. pOetive-etp,Ce,--s- diwtor-,ant e.vees-Hnd-agents-for..,It.__..., _ ow,e^^^^ and any-oF rtls_anvorAd l�y'r, Mush -policies -and nni, other1-he WaFk�,a4 4=11—lyflov. against , sub0otlrffleFnr�h�3Erl ��ISIi, 15�6i......o-Z1,, EornultanLS-and-all-other-pem. , ns-or-entities-identtEed le.ws ando :. ,.`i^-e of the above wnivefq .; -11 extend to the rights AY snaking such -waiver tray have to -die proceeds of tep or payable•uttder-any-policy-so•issuad- . . 5,11.2. 111 ffddkiDPq OWNER it .,:t.t against GON-TP.AC--TOR Subeontmeters, ENGDJEER, LaIT.d7DiERR9 - ofLcers directors -employees -and -agents -of -any -of them -€bra of-use-or--other-consequentia I -loss -extend ittg beyond-direct-physical-loss-uF-.iamage-to arising -out -of or-resulting-from-fire•or-other peril; whether=or-not-insurad•b),GW 1ER:�-and 3-1-1.' �. loss-or-damage-to-the-eompleta� resuldfi.-from-fite-or-other-irts-ure(,I-peril-covered by env lsepeR3`-insumnea-tttainEeirtac{ on the dur4t—pnrtial—uti limit tkm—pursuant—to paregaph-t4-1 U-a€ter-Substantial-Gdmpletit)d pursumt-to•pamgtttph-1.4 9-orutler-ft -payment pursu rred to }n dais _. ttt,,,e insurers will have no rights of recovery-against-any-af-64NTR•f1CTO�Subeontrastors: Receipt andApplicution of insurance Proceeds: 5.12. Any insured loss under the policies of insurance required by paragraphs 5.6 and 5.7 will be adjusted with OWNER -ER and made payable to OWNER as fiduciary for the insureds, as then interests may appear, subject to the requirements of any applicable mortgage clause and of paragraph 5.13. OWNER shall deposit in a separate account any money so received, and shall distribute it in accordance with such agreement as the parties in interest may reach. If no other special agreement is reached the damaged Work shall be iepaired or replaced, the moneys so received applied on account thereof and the Work and the cost thereof covered by an appropriate Change Order or Written Amendment. 5.13. OWNER as fiduciary shall have power to adjust and settle env lass with the insurers unless one of the parties in interest shall object in writing within fifteen days after the occurrence of loss to OWNER's exercise of this power. if such objection he made, OWNER as fiduciary shall make settlement with the insurers in accordance with such agreement as the parties in interest may reach. if no such agreement among the parties in interest is reached, OWNER as fiduciary shall adjust and settle the loss with the insurers m4­ party ai Acceptance of Bonds and Inatrarce; Option to Replace: 5.14. If OWNF has any objection to the coverage afforded by or other provisions of the, Bonds-oF insurance required to be purchased .and maintained by the etheF--party CONTRACTOR in accordance with Article 5 on the basis of nonconformance with the Contract Documents, the objecting-party-shall-se-ru>tif -the-other-party OWNER will notify tent fifteen CONTRACTOR ut writing within days after receipt deliv of the certificates (or-otheF-e%4dence requested) to OWNER as required by paragraph 2.7. other-such-additional-infomintion-in-respect-of-insurance provided-tts-this-other-may-Feasonablrrequest—lf-eitheF party-sloes-not-purchasz-or-maintain-ail-of-the-Bmds-arxl tnsttranou-required-uf-sucft-party--tar-the-EontrRGt writit>e-of such -failure -to -purchase -prier -to -the -star of -the to tttaattaWi0in the required eovrrage> 1tiEheut prrjudiee te-an" 11411 Fight or-remedy-the-otha parry -may -elect -to -obtain -equivalent Bonds-or-utsuranex-to-protect-such•other-party!s-irNeFesKs•at tha-expans&of-tho-paFy-who-was-required-to-provide-such 6ontract-Price•aceordttrely- Partial Utilization -Property Insurance: 5.15. If OWNER finds it necessary to occupy or use a portion or portions of the Work prior to Substantial EJCDC GENERAL COMMONS 1910.3 (1990 Editim) w/ a-ry OF GORT COLLI M MODI FI CAMNs (RL- V 4r 000) Completion of all the Work, such use or occupancy may be accomplished in accordance with paragraph 14.10, pprovided that no such use or occupancy shall commence before the insurers providing the property insurance have acknowledged notice thereof and in writing effected any changes in coverage necessitated thereby. The insurers providing the property insurance shall consent by endorsement on the policy or policies, but the property insurance shall not be cancelled or permitted to lapse on account of any such partial use or occupancy. ARTICLE: 6-CONTRACTOR'S RESPONSIBILITIES Supenision and Superintendence: 6.1. CONTRACTOR shall supervise, inspect and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the Contract Documents. CONTRACTOR shall he solely responsible for the means methods, techniques, sequences and procedures of construction, but CONTRAC OR shall not be responsible for the negligence of others in the design or specification of a specific means, method, technique. sequence or procedure ofconstruction which is shown or indicated in and expressly required by the:' Contract Documents. CONTRACTOR shall be responsible to see that the completed Work complies accurately with the Contract Documents, 6.2. CONTRACTOR shall keep on the Work at all times during its progress a competent resident superintendent, who shall not be replaced without written notice to OWNER and ENGINEER except under extraordinary circumstances. The superintendent will be CONTRACTOWs representative at the site and shall have authority to act on behalf of CONTRACTOR All communications to the superintendent shall be as binding as if given to CONTRACTOR - Labor, Materials and Equipment: 6.3. CONTRACTOR shall provide competent, suitably qualified personnel to survey, lay out and construct the Work as required by the Contract Documents CONTRACTOR shall at all times maintain good discipline and order at the site. Except as otherwise required for the safety or protection of persons or the Work or property at the site. or adjacent thereto, and except as otherwise indicated in the Contract Documents, all Work at the site shall be performed during regular working hours and CONTRACTOR will not permit overtime work or the performance of Work on Saturday, Sunday or any legal holiday without OWNER's written consent given after prior written notice to ENGINEER, CONTRACTOR shall submit requests to the ENGINEER no less than 48 hours in advance of anv Work to he performed on Saturday. Sunday, Holidays or outside the Regular Working Hours. 6A. Unless otherwise specified in the General Requirements, CONTRACTOR shall furnish and assume full responsibility for all materials. equipment, labor, transportation, construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water. sanitary facilities, tempomry facilities and all other facilities and incidentals necessary for the furnishing, performance, testing, start-up and completion of the Work. 6.4A. Purchasing Restrictions: CONTRACTOR must comply with the City's purchasing restrictions. A copy of the resolutions are available for review in the offices of the Purchasing and Risk Management Division or the City Clerk's office. 6.4.2, Cement Restrictions: Citv of Fort Collins Resolution 91-121 requires that suppliers and producers of cement or products containing cement to certify that the cement was not made in cement kilns that bum hazardous waste as a fuel. 6.5. All materials and equipment shall be of good quality and new, except as otherwise provided in the Contract Documents. All warranties and guarantees specifically called for by the Specifications shall expressly run to the benefit of OWNER. if required by ENGINEER, CONTRACTOR shall furnish satisfactory evidence (including reports of required tests) as to the kind and quality of materials and equipment. All materials and equipment shall be applied, installed, connected, erected, used, cleaned and conditioned in accordance kith instructionk of the applicable Supplier, except as otherwise provided in the Contract Documents. Progress &-hedule: 6.6. C,ONTRACTOR shall adhere to the progress schedule established in accordance with paragraph 2.9 as it may be adjusted from time to time as provided below: 6.6.1. CONTRACTOR shall subunit to ENG rUEER for acceptance (to the extent indicated in paragraph 2.9) proposed adjustments in the progress schedule that will not change the Contract Times (or Milestones). Such adjustments will conform generally to the progress schedule then in effect quid additionally will comply with any provisions of the General Requirements applicable thereto. 6.6.2. ,Proposed adjustments in the progress schedule that will change the Contract Times (or Milestones) shall be submitted in accordance with the requirements of paragraph 12.1. Such adjustments may only be made by a Change Order or Written Amendment in accordance with Article 12. 6.7. Substitutes and "Or Equal " !tents: 6.7.1. Whenever an item of material or equipment is specified,ur described in the Contract Documents by using the name of a proprietary item or the name of a particular, Supplier, the specification or description is intended to establish the type, function and quality required. Unless the specification or description EXI)CGENERALCONI)MONS [9t0.4I (1990Edition) 12 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4(Z000) contains or is followed by words reading that no like, equivalent or "or -equal" item or no substitution is permitted, other items of material or equipment or material or equipment of other Suppliers may be accepted by ENGINEER under the following circumstances: 6.7.1.1. Vr-Equal": If in ENGINEEWs sole discretion an item of material or equipment proposed by CONTRACTOR is functionally equal to that named and sufficiently y similar so that no change in related Work will be required, it may be considered by ENGINFF.,R as an "or -equal" item, in which case review and approval of the proposed item may, in FNGfNF..ER's sole discretion, be accomplished without compliance with some or all of the requirements for acceptance of proposed substitute items. 6.7.1.2. Substinrte Items: If in ENGINEER's sole discretion an item of material or equipment proposed by CONTRACTOR does not qualify as an "or -equal" item under :subparagraph 6.7.1.1, it will be considered a proposed substitute item. C6NTR.4cTOR shall submit sufficient information- as provided below to allow ENGINEER to determine that the item of material or equipment proposed is essentially equivalent to' that named and an acceptable substitute therefor. The procedure for review by the ENGINEER will include the following as supplemented in the General Requirements and as FNGINEFR may' decide is appropriate under the circumstances: Requests for review of proposed substitute items of material or equipment will not be accepted by FNGTNF.,ER from anyone other than CONTRACTOR If CONTRACTOR wishes to furnish or use a substitute item of material or equipment, CONTRACTOR shall first make written application to ENGINEE-R for acceptance thereof, certifying that the proposed substitute will perform adequately the functions and achieve the results called for by the general design, be similar in substance to that specified and be suited to the 4nme use as that specified The application will state the extent, if any, to which the evaluation and acceptance of the propused substitute will prejudice CONTRACTOR's achievement of Substantial Completion on time, whether or not acceptance of the substitute for use in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with OWNER for work on the Project) to adapt the design to the proposed substitute and whether or not incorporation or use of the substitute in connection with the Mork is subject to payment of any license fee or royalty. MI variations of the proposed substitute from that specified will be identified in thee application and available maintenance, repair and replacement service- will be indicated. , The application will also contain an itemized estimate of all costs or credits that will result directly or indirectly from acceptance of such substitute, including costs of redesign and claims of other contractors affected by the .resulting change, all of which will be considered by ENGINEER in evaluating the proposed substitute. ENGINEER may require CONTRACTOR to furnish additional data about the proposed substitute. 6.7.1.3. CONM4C'TOR's Expense: All data to be provided by CONTRACTOR in support of any proposed "or -equal" or substitute item will be at CONTRACTOR's expense. 6.7.2. Substitute Conshuction tle8rals or Procedures: If a specific means, method, technique, sequence or procedure of construction is shown or indicated in and expressly required by the Contract Documents CONTRACTOR may famish or utilize a substitute means, method, technique, sequence or procedure of construction acceptable to ENG[NEER. CONTRACTOR shall submit sufficient information to allow ENGINEER, in ENGINEER's sole discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract Documents. "The procedure for review by ENGINEER will be similar to that provided in subparagraph 6.7.1.2. 6.7.3. Engineer's Evaluation: ENGT1NEFR will he allowed a reasonable time within which to evaluate each proposal or submittal made pursuant to paragraphs 6.7,1.2 and 6.7.2. ENGINEER will be the sole judge of acceptability. No "or -equal" or substitute will be ordered, installed or utilized without ENGINEER's prior written acceptance which will be evidenced by either a,Change Order or an approved Shop Ihawing. OWNER may require CONTRACTOR to famish at CONTRACTOR's ,expense a special performance guarantee or other surety with respect to any "or -equal" or substitute. ENGINEER will record time required by ENGINEER and ENGINEER's Consultants in evaluating substitutes proposed or submitted by CONTRACTOR pursuant to paragraphs 6.7.1.2 and 6.7.2 and in making changes in the Contract Documents (or in the provisions of any other direct contract with OWNER for work on the Project) occasioned thereby. Whether or not ENGINEER accept%a substitute item so proposed or submitted by CONTRACTOR, CONTRACTOR shall reimburse O\VNER for the charges of ENGUMIZ and ENGTNEER's Consultants for evaluating each such proposed substitute item. 6_9. Concerning Subcontractors, Suppliers and Others: 6.8.1. CONTRACTOR shall not employ any Subcontractor, Supplier or other person or organization (including those acceptable to OWNER and ENGINEER as indicated in paragraph 6.5.2), whethix initially or as a substitute, against whom OWNER or ENGINEER may have reasonable objection. CONTRACTOR shall not be required to employ any Subcontractor, Supplier or other person or organization to furnish or perform any of the Work against whom CONTRACTOR- has reasonable objection. EJCDC GENERAL CONDITIONS 19105 (1990 Edition) %V/aTY OF FORT COLLINS MODIFICATIONS (REV 4P000) 6.9. CONTRACTOR shall perfonu not less than 20 percent of the Work with its own forces that is without subcontracting). The 20 percent requirement shall be understood to refer to the Work the value of which totals not less than 20 percent of the Contract Price. 6.8.2. It-the-Supplementary-Genditiom Bidding Documents require the identity of certain Subcontractors. Suppliers or other persons or organizations (including those who are to furnish the principal items of materials or equipment) to be submitted to OWNER in-advance-of-the-Teoitted date prior to the Effective Date of the Agreement for acceptance by OWNER and ENGINEER, —and -if GONTRAC-TOR has submitted a list thereof in OWNER's, or ENGINEER's acceptance (either in writing or by failing to make.written objection thereto by the date indicated for acceptance or objection in the bidding documents or the Contract Documents) of atiy strsh-Sulxontrastor Supplier-e-etheF persotior ",eked an the basi. tieeep such -substitution -and -an -appropriate -Change -Order will be issued eF Written Amendment signed, will constitute a condition of the Contract re airing the use of the named subcontractors, suppliers or .other persons or organization on the Work unless prior written approval is obtained from OWNER and ENGINE-FR. No acceptance by OWNER or ENGINEER of any such Subcontractor, Supplier or other person or organization shall constitute a waiver of any right of OWNER or ENGINEER to reject defective Work. 6.9.1. CONTRACTOR shall be fully responsible to OWNER and ENGINEER for all acts and omissions of the Subcontractors, Suppliers and other persons and organizations performing or furnishing any of the Work under a direct or indirect contract with CONTRACTOR just as CONTRACTOR is responsible for CONTRACTOR's own acts and omissions. Nothing in the Contract Documents shall create for the benefit of any such Subcontractor, Supplies or other person or organization any contractual relationship between OWNER or ENGINEER and any such Subcontractor, Supplier or other person or organization nor shall it create any obligation on the part of OWNER or ENGINEER to pay or to see to the payment of any moneys due any such Subcontractor, Supplier or other person or organization except as may otherwise be required by Laws, and Regulations. OWNER or ENGINEER may furnish to any subcontractor, supplier or other person or organization evidence of amounts paid to CONTRACTOR in accordance with CONTRACTOR'S "Applications for Payment". 6.9.2.. CONTRACTOR shall be solely responsible for scheduling and coordinating the Work of Subcontractors. Suppliers and other persons and organizations performing or furnishing any of the Work under a direct or indirect contract with CONTRACTOR. CONI'RAC'TOR shall require all Subcontractors, Suppliers and. such other persons and organizations performing or furnishing any of the Work to communicate with the ENGINEER through CONTRACTOR 6.10. The divisions and sections of the Specifications and the identifications of any Drawings shall not control CONTRACTOR in dividing the Work among Subcontractors or Suppliers or delineating the Work to be performed by any specific trade, 6.11. All Work perforated for CONTRACTOR by a Subcontractor or Supplier will be, pursuant to an appropriate agreement between CONTRACTOR and the Subcontractor or Supplier which specifically binds the Subcontractor or Supplier to the applicable terms end conditions of the Contract Documents for the benefit of OWNER and ENGINEER. Whenever any-Aieh-a"niertt additional 7FOpttifitlFf2Het, pft3Vfl2f-Ifl pamgraphs5.6 er$7, the agreement between the C-01,�TR-r\GTnR-arid=the Subcontractor-or-Suppliehwill a�mll other arisin�oe{ at or resulting tfottt eery of the perilstevrrecl b}= the-Work.—if-the-insurers-on-anv-such-polioies-require separate weiver-fern r er -Supplier� 99N-1 Patent Fees and Rorvelfies: 6.12. CONTRACTOR shall pay all license fees and royalties and assume all costs incident to the use: in the performance of the Work or the incorporation in the Work of any invention, design, process; product or device which is the subject of patent rights or copyrights held by others. If a particular invention, design, process, product or device is specified in the Contract Documents for use in the Performance of the Work and if to the actual knowledge.of OWNER or ENGINEER its use is subject to patent rights or copyrights amlline for the payment of any license fee or royalty to others, the existence of such rights shall be disclosed by OWNER in the Contract Documents. To the fullest extent permitted by Laws and Regulations, CONTRACTOR shall indemnify and hold harmless 01VINEF ENGINEER, ENGINEER's Consultants and the officers, directors, employees, agents and other consultants of each and any of them from and against all claims, costs, losses and damages arising out of or resulting from any infringement of patent rights or copyrights incident to the use in the performance of the Work or resulting from the incorporation in the Work of any invention, design, process, product or device not specified in the Contract Documents. EXI)C GENERAL CONDIITONS 1910-8(1990 Editiar) 14 w/ CITY OF FORT COLLINS MODIFICATIONS (12L•"V 471000) Permits: 6.13. Unless otherwise provided in the Supplementary Conditions, CONTRACTOR shall obtain and pay for all construction permits and licenses. OWNER shall assist CONTRACTOR, when necessary, in obtaining such permits and licenses. CONTRACTOR shall pay all governmental charges and inspection fees necessary for the prosecution of the Work, which are applicable at the time of opening of Bids, or, if there are no Bids, on the Effective Date of the Agreement. CONTRACTOR shall pay all charges of utility owners for connections to the Work and OWNER shall pay all charges of such utility owners for capital costs related thereto such as plant investment fees. 6.14. LawsandReguladons: 6.14. L CONTRACTOR shall give all notices and comply with all Laws and Regulations, applicable to furnishing and performance of the Work. Except where otherwise expressly required by applicable Laws and Regulations, neither OWNER nor ENGINEER shall be responsible for monitoring COMi'RACTOR's compliance with any Laws or Regulations. 6.14.2. if CONTRACTOR performs any Work knowing or having reason to know that it is contrary to Laws or Regulations, CONTRACTORR shall bear all claims, costs, losses and damages canted by, arising out of or resulting therefrom; however, it shall not be CONTRACTOR's primary responsibility to make certain that the Specifications and Drawings are in accordance with taws and Regulations, but this shall not relieve CONTRACTOR of CONTRACTOR's obligations under paragraph 3.3 2. Taxes. 6.15. CONTRACTOR shall pay all sales, consumer, use and other similar taxes required to be paid by CONTRACTOR in accordance with the Laws and Regulations of the place of the project which are applicable during the performance of the Work. 6.15.1. OWNER is exempt from Colorado State and local sates. and use taxes on materials to be permanently incorporated into the vroject: Said taxes shall not -be included in the Contract Price. CONTRACTOR must apply for. and receive, a Certificate of Exemption from the Colorado Department of Revenue for construction materials to be ph sy icall incorpprated into the tyro This Certification of Exemption provides that the CONTRACTOR shall neither pay nor include in his Bid. Sales and Use Taxes on those building and construction materials physically incorporated into the proiect. Address: Colorado Department of Revenue State Capital Annex 1375 Sherman Street. Denver_ Colorado, 80261 Sales and Use Taxes for the State of Colorado Regional Transportation District (RTD) and certain Colorado counties are collected by the State of Colorado and are included in the Certification of Exemption. :AII applicable Sales and Use Taxes (including State collected taxes), on any items other than construction and building materials physically inc:oMrated into the project are to be paid by CONTRACTOR and are to be included in appropriate bid items. Use of Premises: 6.16. CONTRACTOR shall confine construction equipment, the storage of materials and equipment and the operations of workers to the site and land and areas identified in and permitted by the Contract Documents and other land and areas permitted 135• Laws and Regulations, rights -of -way, permits and easements, and shall not unreasonably encumber the premises with construction equipment or other materials or equipment. CONTRACTOR shall as,%urne full responsibility for any damage to any such land or area, or to the owner. or occupant thereof or of any adjacent land or areas, resulting from the performance of the Work. Should any claim be made by any such owner or occupant because of the performance of the Work, CONTRACTOR shall promptly settle with such other party by negotiation or otherwise resolve the claim by arbitration or other dispute resolution proceeding or at law. CONTRACTOR shall, to the fullest octent permitted by i.aws and Regulations, indemnify and hold harmless OWNER, ENGINEER LNG NEERs Consultant and anyone directly or indirectly employed by any of them from and against all claims, costs, losses and damages arising out of or resulting from any claim or action, legal or equitable, brought by any such owner or occupant against OWNED ENGINEER or any other patty indemnified hereunder to the extent caused by or based upon CONTRACTOR's performance of the Work. 6.17, During the progress of the, Work, CONTRACTOR shall keep the premises free from accumulations of waste materials, rubbish and other debris resulting from the Work_ At the completion of the Work CONTRACTOR shall remove all waste materials, rubbish and debris from and about the premises as well as all tools, appliances, construction equipment and machinery and surplus materials. CONTRACTOR shall leave the site clean and ready for occupancy by OWNER at Substantial Completion of the Work. CONTRACTOR shall restore to original condition all property not. designated for alteration by the Contract Documents. 6.18. CONTRACTOR shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall CONTRACTOR subject any part of the Work or adjacent property to stresses or pressures that will endanger it. Record Documents• EJCDC GENERAL CONDITIONS 1910.8 (1990 E(fition) wf C1TY OF FORT COLLINS MODIFICATIONS (REV 4r000) 6.19. CONTRACTOR shall maintain in a safe place at the site one record copy of all Drawings, Specifications, Addenda, Written Amendments. Change Orders, Work Change Directives, Field Orders and written interpretations and clarifications (issued pursuant to paragraph 9.4) in good order and annotated to show all changes made during construction. These record documents together with all approved Samples and a counterpart of all approved Shop Drawings will be available to ENGINEER for reference. Upon completion of the Work, and prior to release of final payment, these record documents, Samples and Shop Drawings will be delivered to ENGINEER for OWNER. Safety and Protection: 6.20. CONTRACTOR shall be responsible for initiating, maintaining and supervising all safety precautions and programs in.connection with the Work. CONTRACTOR shall take, all necessary precautions for the safety of. and shall provide the necessary protection to prevent damage, injury or loss to: 6.20.1. all persons on the Work site or who may be affected by the Work; 6.20.2. all the Work and materials and equipment to be incorporated therein, whether in storage on or off the site: and 6.20.3. other property at the site or adjacent thereto; including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities and Underground Facilities not designated for removal, relocation or replacement in the course of construction. CONTRACTOR shall comply with all applicable Laws and Regulations of any public body having jurisdiakm for safety of persons or property or to protect them from damage, injury or loss; and shall eruct and maintain all necessary safeguards for such safety and protection. CONTRACTOR shall notify owners of adjacent property and of Underground Facilities and utility owners when prosecution of the Work may affect them, and shall cooperate with them in the protection, removal, relocation and replacement of their property. All damage, injury or loss to any property referred to in paragraphs 6.20.2 or 6.20.3 caused, directly or indirectly, in whole or in part, by CONTRACTOR, any Subcontractor. Supplier or any other person or organization directly or indirectly employed by any of them to perform or furnish any of the Work or anyone for whose acts any of them may be liable, shall be remedied by CONTRACTOR (except damage or loss.attributable to the fault of Drawings or Specifications or to the acts or omissions of OWNER or ENGINEER or ENGINEER's Consultant or anyone emploved by arty of them or anyone far whose acts any of them may be liable, and not attributable, directly or indirectly, in whole or in part. to the fault or negligence of CONTRACTOR or any Subcontractor, Supplier or other person or organization directly or indirectly employed by any of them). CONTRACTOR'S duties and responsibilities for the safety and protection of the Work shall continue until such time as all the Work is completed and ENGINEER has issued a notice to OWNER and CONTRACTOR in accordance with paragraph 14.13 that the Work is acceptable (exmpt as otherwise expressly provided in connection with Substantial Completion). 6.21. Safety Represenmrive. CONTRACTOR shall designate a qualified and experienced safety representative at the site whose duties and responsibilities shall be the prevention of accidents and the maintaining and supervising of safety precautions and programs. Hazard Communication Programs: 6.22. CONTRACTOR shall be responsible for coordinating any exchange of material safety data sheets or other hazard communication information required to be made available. to or exchanged between or among, employers at the site in accordance with laws or Regulations. Fanergencies- 6 21 In emergencies affecting the.safety or protection of persons or the Work or property at the site or adjacent thereto, CONTRACTOR, without special instruction or authorimtion from OWNER or ENGTNF..ER, is obligated to act to prevent threatened damage, injury or loss. CONTRACTOR shall give ENI GINEER prompt written notice if CONTRACTOR believes that any significant changes in the Work or .variations from the Contract. Documents have been caused thereby. If ENGINEER determines that a change in the Contract Documents is required because of the action taken by CONTRACTOR in response to such an emergency,'a Work Change Directive or Change Order will be issued to document the consequences of such action 6.24, Shop Drawings and.Samples- 6.24.1. CONTRACTOR shall submit Shop Drawings to ENGINEER for review and approval in accordance with the accepted schedule of Shop Drawings and Sample submittals (see paragraph 2.9). All submittals will be identified as ENGINEER may require and in the number of copies specified in the General Requirements. The data shown on the Shop Drawing will be complete. with respect to quantities, dimensions, specified performance and design criteria, materials and similar data to show ENGINEER the materials and equipment CONTRACTOR proposes to provide and to enable ENGINEER to review the, information for the limited purposes required by paragraph 6.26. 6.24.2. CONTRACTOR shall also submit Samples to ENGINEER for review and approval in accordance with said accepted schedule of Shop Drawings and Sample' submittaLs. Each Sample Will be' identified clearly as to material, Supplier, pertinent data such as catalog numlxrs and thc.use for which intended and otherwise as ENGINEER may require to enable ENGINEER to review the submittal for the limited 16 EJCDC GENERAL CONDITIONS 1910-8 (1990 Editim'i w/ (,71Y OF FORT COLLI Ivy MODII7CA-1lONS (RL"V 4f? 006) purposes required by paragraph 6.26. The numbers of each Sample to be submitted will be as specified in the Specifications. 6.25. Submittal Procedures. 6.25.1. Before submitting each Shop Drawing or Sample. CONTRACTOR shall have determined and verified: 6.25.1.1. all field measurements; quantities; dimensions, specified performance criteria, installation requirements, materials, catalog numbers and similar information with respect thereto, 6.25.1.2. all materials with respect to intended use, fabrication, shipping, handling, storage, assembly and installation perwining to the performance of the Work, and 6.25.1.3_ all information relative to CONTRACTOR's sole responsibilities in respect of means methods, technique.% sequences and procedures of construction and safety precautions and programs incident thereto. CONTRACTOR shall also have reviewed and coordinated each Shop Drawing or Sample with other Shop Drawings and Samples and with the requirements of the Work and the Contract Documents. 6.25.2. Each submittal will bear a stamp or specific written indication that CONTRACTOR has satisfied CONTRACTOR's obligations under the Contract Documents with respect to CONTRACfOWs review and approval of that submittaL 6.25.3. At the time of each submission, CONTRACTOR shall give ENGINEER specific written notice of such variations, if any, that the Shop Drawing .or Sample submitted may have from the requirements of the Contract Documents; such notice to be in a written communication separate from the submittal; and, in addition, shall cause a specific notation to be made .on each Shop Drawing and Sample submitted to ENGINEER for review and approval of each such variation 6.26. ENGINEER will review and approve Shop Drawings and Samples in accordance with the schedule of Shop Drawings and Sample submittals accepted by ENGINEER as required by paragraph 2.9. ENGINEER's review and approval will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work, conform to the information Oven in the Contract Documents and be compatible. with the design concept' of the completed Project as a functioning whole as indicated by the Contract Documents. ENGINEER's review and approval will not extend to means methods, techniques, sequences or procedures of construction (except where a particular means; method, technique, sequence or procedure of _D Of 0 Q ZQ ZW J ce J Q a the basis f O W taveeb... lncorporateEl 0Z LL Q r ruw \ YrA8.4 construction is specifically and expressly called for by the Contract Documents) or to safety precautions or programs incident thereto. The review and approval of a separate item as such will not indicate approval of the assembly in which the item functions. CONTRACTOR shall make corrections required by ENGINEER, and shall return the required number of corrected copies of Shop Drawings and submit as required new Samples for review and approval. CONTRACTOR shall direct specific attention in writing to revisions other than the corrections called for by ENGINEER on previous submittals. 6.2T ENGINEER's review and approval of Shop Drawings or Samples shall not relieve CONTRACTOR from responsibility for any variation frond the requirements of the Contract Documents unless CONTRACTOR has in writing called ENGINEER'S attention to each such variation at the time of submission as required by paragraph 6.25.3 and ENGINEER has given written approval of each such variation by a specific written notation thereof incorporated in or accompanying the Shop Drawing of Sample approval; nor will any approval by ENGHNEER relieve CONTRACTOR from responsibility for complying with the requirements of paragraph 6.25.1. 6,28. Where a Shop Drawing or Sample is required by the Contract Documents or the schedule of Shop Drawing and Sample submissions accepted by .ENGINEER as required by paragraph 2.9, any related Work performed prior to ENGINEER's review and approval of the pertinent suhmittal will be at the sole expense and responsibility of CONTRACTOR. Continuingthe Work: 6.29, CONTRACTOR shall carry on .the Work and adhere to the progress schedule during all .disputes or disagreements with OWNER. No Work shall be delayed or postponed pending resolution of any disputes or disagreements, except as permitted by paragraph 155 or as OWNER and CONTRACTOR may otherwise agree in writing. 6.30. CONMICTOR'v Ceneral Warranty and (7uarantee: 6.30,1. CONTRACTOR warrants and guarantees to OWNER, ENGINEER and ENGINEER'S Consultants that all Work will be in accordance with the Contract Documents and will not be defective. CONTRACTOR's warranty and guarantee hereunder excludes detects or damage caused by: 6,30.1.1. abuse, modification or improper maintenance or operation by persons other than CONTRACTOR, Subcontractors or Suppliers; or 6.30.1.2. normal wear and tear under normal usage. 6.30.2. CONTRACTOR's obligation to perform and complete the Work in accordance with the Contract Documents shall be absolute. None of the Mowing will constitute an acceptance of Work that is not in EXI)C GENERAL Comm om 19 io-s I t 99Q E(itivtf) w10 Y OF FORT COLLINS MODIFICATIONS (REV 4r!0001 accordance with the Contract Documents or a release of CONTRACTOR's obligation to perform the Work in accordance with the Contract Documents. 6.30 2.1. observations by ENGINEER; 6.30.2.2. recommendation of any progress or final payment by LNGMER; 6.30 2.3. the issuance of a certificate of Substantial Completion or any pavmLmt by OWNER to. CONTRACTOR under the Contract Documents; 6.30 2.4. use or occupancy of the Work or any part thereof by OWNER; 6.30.2.5. any acceptance by OWNER or any failure to do so 6.30.2.6: any review and approval*of a Shop Drawing or Sample submittal or the issuance of a notice of acceptability by ENGINEER. pursuant to paragraph 14.13; 6.30.2.7. any inspection, test or approval by others; or 6.30.2.S.. any correction of defective Work by OWNER Indenuriffcation: 6.31. 'ro the fullest extent permitted by. Laws and Regulations, CONTRACTOR shall indemnify and hold harmless OWNER ENGINEER ENGNEERZs Consultants and the officers, directors, employees, agents and other consultants of each and any of them from and against all claims, costs, losses and damages (including, but not limited to, all fees and charges of engineers, architects, attorneys and other professionals and all court or arbitration or other dispute resolution costs) caused by, arising out of or resulting from the performance of the Work; provided that any such claim, cost, loss or damage: (i) is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the UVork itself), including the loss of use resulting therefrom, and (ii) is caused in whole or in part by any negligent act or omission of CONTRACTOR, any Subcontractor, any Supplier, any person or organization directly or indirectly employed by any of them to perform or furnish any of the Work or anyone for whose acts any of them may be liable, regardless of whether or not caused in part by any negligence or omission of a person or entity indemnified hereunder or whether liability is imposed upon such indemnified party by Laws and Regulations regardless of the negligence of any such person or entity. 6.32. In any and all claims against OWNER or ENGINEER or any of their respective consultants, agents, officers, directors or employees by any employee (or the mn,ivor or personal representative of such employee) of CONTRACTOR any Subcontractor, any Supplier, any person or organisation directly or indirectly employed by 17 any of them to perform or Punish any of the Work or anyone for whose acts any of them may be liable, the indemnification obligation under paragraph6.31 shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for CONTRACTOR or any such Subcontractor, Supplier or other person or organization under workers' compensation arts; disability benefit acts or other employee benefit acts. 6.33. The indemnification obligations of CONTRACTOR under paragraph 6.31 shall not extend to the liability of ENGINEER and ENGINaR's Consultants, officers, directors, employees or agents caused by the professional negligence, errors or om issions of any of than. Survival ojObhgations: 6.34'. All representations, indemnifications, warranties and guarantees made in, required by or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion and acceptance of the Work and termination or completion of the Agreement. ARTTCLE 7-OTHER WORK Related Work at Site: 7.1. OWNER may perform other work-, 'related, to the Project at the site by OWNER!, own forces, or let other direct contract- therefor which shall contain General Conditions similar to these, or have other work performed by utility owners, If the fact that such other work is to be performed was not noted in the Contract Documents, then: (i),written notice thereof will be given to CONTRACTOR price to starting any such other work and (u) CONTRACTOR may make a claun therefor as provided in Articles 1 l and 12 if CONTRACTOR believes that such performance will involve additional expense to CONTRACTOR or requires additional time and the parties are unable to agree as to the amount or extent thereof, T2. CONTRACTOR shall altord each other contractor who is a party to such a direct contract and each utility owner (and OWNER, if O `NE-R is performing the additional work with O NEIR's employees) proper and safe access to the site and a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such other work and shall properly connect and coordinate the Work with theirs Unless otherwise provided in the Contract Documents, CONTRACTOR shall do all cutting, fitting and patching of the Work, that may be required to make its several parts come together properly and integrate with such other work. CONTRACTOR shall not endanger any work of others by cutting, excavating or otherwise altering their work and will only cut or alter their work with the written consent of ENGINEER and the others whose work will be affected. The duties and responsibilities of CONTRACTOR under this paratvaph are for the benefit of such utility owners and other contractors to the extent that there are comparable 18 EJCDC GENERAL COMMONS 191" (1990 Editian) wf CITY OF FORT COLLINS MODa1CATIONs (REV 4l7006) provisions for the benefit of CONTRACTOR in said direct contracts between OWNER and such utility owners and other contractors: 7.3. If the proper execution or results of any part of CONTRACTOR's Work depends_ upon work performed by others under this Article 7, CONTRACTOR shall inspect such other work and promptly report to ENGINEER in writing any delays, defects or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and results of CONTRACTOR's Work. CONTRACTOR's failure so to report will constitute an acceptance of such other work as fit and proper for integration with C0NTR4CTOR's Work except for latent or nonapparent defectsand deficiencies in such other work. CoortGnation: 7,4: If .OWNER contracts with others for the performance of other work on the Project at the site. the following will be set forth in Supplementary Conditions: 7.4.1. the person, firm.or corporation who will have authority and responsibility for coordination of :the activities among the variouti prime contractors will be identified; T4.2. the specific matu:rs to be covered by such authority and responsibility will be itemized; and 7,43. the extent of such authority and responsibilities will be provided. Unless otherwise provided in the Supplementary Conditions, OWNER shall have sole authority and responsibility in respect of such coordination, ARTICLE 8--OWNER'S RESPOi'NSEBILMES 8.1. Except as otherwise provided in these General Conditions, OWNER shall issue all communications to CONTRACTOR through ENGINEER V. In case of termination of the employment of ENGINEER, OWNER shall appoint an engineer against whom-G013-TRAC—TOR—makes-no•-reasonable-objectiexr whose status under the Contract Documents shall be that of the former ENGlti tEER 9.3. OWNER shall furnish the data required of OWNI ER under the Contract Documents promptly and shall make payments to CONTRACTOR promptly when they are due as prov ided in paragraphs 14.4 and 14.13. , 8.4. O NI ER's duties in respect of providing lands and easements and providing engineering surveys to establish reference pointsare set forth in paragraphs 4.1 and 4.4. Paragraph 4.2 refers to OWNER's identifying and making available to CONTRACTOR copies of reports of explorations and tests of subsurface conditions at the site and drawings of physical conditions in existing structures at or contiguous to the site that have been utilized by ENGINEER in preparing the Contract Documents. ttY—irtstirattet+ aru snE forth•iR.peragraphs 5-4through-5-i9- 8.6. OWNER is obligated to execute Change Orders as indicated in paragraph 10.4. 8.7. ORN1 Rs responsibility in respect of certain inspections, tests and approvals is set forth in paragraph 13.4. 8.8. In connection with OkVNER's right to stop Work or suspend Work, sce paragraphs 13.10 and 15.1. Paragraph 15.2 deals with OWNER's right to terminate services of CON't'RAGI'OR under certain circumstances. s.9. The .OWNER shall not supervise, direct or have control or authority over, nor be responsible for. CONTRACCOR's means, methods, techniques, sequences or procedures of construction or the safety precautions and programs incident thereto, or for any failure of CON,rRAC'i'OR to comply with haws and Regulations applicable to the furnishing or performance of the Work. OWNER will not Inc responsible for CONTRACTOR's failure to perform or furnish the Work in accordance with the ContractDoctmaents. respeet of undiselered Ambe *a ; P08s; aerfelaum, lie sirdous ur Radieaetiy��leterials-ttncroyarad-oFrayealad-art�h�sita-is 8-1-1.—rrn.«ktoz ' h r-n?rrR ArrnoPIG arrangamants-have-bean-mach-to-satisfy-4W'�FER's obligatrxva-urnder-the-C-orttraet-Aeeu...e:,t�-;?"" '- rasponsibiiitv-in-respect-thereof-will-ba-as=sew€orth-in-tlaa Supplementary-Gonditions- ARTICLE 9-FNG1NF.ER'S STATUS DiiRiNG CONSTRUCTION OINVER's Representative: 9.L ENGINEER will be OWNER's representative during the construction period. The duties and responsibilities and the limitations of . authority of ENGINEER as ORNERs representative during construction are set forth in the Contract Documents and shall not be extended without written consent of OWNER and ENGINEER Phily to Site: 9.2. ENGINEER will make visits to the site at intervals appropriate to the' various stages of construction as ENGINEER deems necessary in order to observe as an experienced and qualified design professional the progress Ejux GENEF AL con Dtmom 191os o9go Edittai) cotCtTY OF FORT crouaNs NIODLHCATtoNs (ttEv.trzoo0) that has been made and the quality of the variousaspects of CONTRACTOR's executed Work. Based on information obtained during such visits and observations. ENGINEER will endeavor for the benefit of OWNER to determine, in general, if the 1Vork is proceeding in accordance with the Contract Document_-. ENGINEER will not be required to make exhaustive or continuous on - site inspections to check the quality or quantity of the Work. L-NGIN E.ER's efforts %till be directed toward providing for OWNER a grater degree of confidence that the completed Work will conform generally to the Contract Documents. On the basis of such visits and on - observations, ENGINEER will keep OWNER informed of the progress of the Work and will endeavor to guard OWNER against defective Work. ENGiNEER2's visits and on=site observations are subject to all the limitations on ENGINEER's authority and responsibility set forth in paragraph 9.13, and particularly, btit without limitation during or as a result of ENGINEER!; on -site visits or observations of CONI'R4CI'OR's Work. ENGINEER will not supervise, direct. control or have authority over or be responsible for CONI'RtACTOR's means, methods, techniques sequences or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of CONTRACTOR to comply with Laws and Regulations applicable to the furnishing or perfomaancc of the Work. Project Representative., 9.3, If OWNER and ENGINEER agree, ENGINEER will furnish a Resident Project Representative to assist ENGINEER in providing more continuous observation of the Work. The responsibilities and authority and limitations thereon of any such Resident Project Representative and assistants will be as provided in paragraphs 9.3 and 9.13 aFid in the S ippie . enter. ' Conditions of these General Conditions. If OWNER desifmates another representative or agent to represent OWNER at the site who is not ENGfiVEER's Consultant, agent or employee, the responsibilities and authority and limitations thereon of such other person will be as provided in Genditie I t MP.1h 9.3 of these General Conditions if the FNGNEFR fumiches a Resident Pro'ecy t Representative (RPR ar other assistant- or iE the OWNER_ck iartates a R-presenLltivr. or agent all as provided in paragraph 9.3 of the General Conditions, these Representatives shall have the authority and limitations as provided in paragmaph 9.13 of the General Conditions and shall be subiect to the following: 9 3 1 The Representative's dealings in matters pertaining to the on -site work will in general, be with the ENGII TEF.R and CONTRACTOR But the Representative will keep the OWNER pr earl advised about such matters. The Representatives dealing with subcontractors will only be through or with the full knowledge and approval of the CONTRACTOR 9 3 ? Duties and Responsibilities. Representative will: 9.3.2 l.Schedules Review the progress 19. schedule and other schedules prepared by the CONTRACTOR -and consultwith the ENGMEER concerning acceptability. 9.3.2.2. Conferences and Meeting - Attend meeting with the 'CONTRACTOR such as preconstruction conferencxstprogress meetings and other iob conferences alai prepare and circulate copies of minutes of meegg s. 9.3.2.3. Liaison 93.2.3.1. Serve as ENGINEER'S liaison with CONTRACTOR working principally through CONTRACTOR'S superintendent to assist the CONTRACTOR in understanding the.Contract Documents. 9.3.2.3.2. Assist in obtainine from OWNER additional details or infomiation, when requiretl for proper execution of the Work. 93 <.3.3. Advise the ENGIN`EFR and CONTRACTOR of the commencement of any Work requiring a Shop Drawirtg or s<Implc submission if die submission has not hcen approved by the ENGINEER 9.3.2.4.Review of Work Rejection of Defective Work, Inspections and Tests - 9.3.2.4.1. Conduct on -site observations of the Work in progress to assist the ENGINEER in determining that the Work is proceeding in accordance with the Contract Documents. 9.3:2.43. Accompany visiting_ inspectors representing public or other agencies having jurisdiction over the Project. record the results of these inspections and report to the ENGINEER. 9.32.5. tnterpretation of Contract Documents. Report to ENGINEER when clarifications and interpretations of.the Contract Documents are needed and trarumit to CONTRACTOR clarification aryl intcMtation of the Contract Documents as issued by the ENGINEER 9.3.2.6. Modifications. Consider and evaluate CONTRACTOR'S suggestions far EJCDC GENERAL CONDITIONS I M-S (1990 Ec iticii ) `�� w/ CITY OFFORTCOLLIMNIODWICATIONS(RrV,IP_OOO) modification in Drawings or Specifications and report these recommemlations to ENGINEER. Accurateh• transmit to CONTRACTOR decisions issued by the ENGLNEER 9.3.2.7. Records. 9.3.2.8. RepcM& 9.3.2.8,1. Fumish ENGINEER periodic reports as required, of the orogress of the Work and of the CONTRACTOR'S compliance with the progress schedule and schedule of shop Drawing and sample ,w m ttal 9.32.8:2. Consult with ENGINEER in advance of scheduling major tests_ inspections or start of importvtt phases of the Work. 9.3 2.8.3. Draft proposed Change Orders and Work Directive Chan, obtaining backup material from the CONTRACTOR and recommend to ENGINEER Change Orders, Work Directive Changes and field orders. 9.3.2.8.4. Report. immediately to ENGIIVEER and OWNER the occurrenoe of any accident. 9.3.2.9. Payment Requests. Review applications for Myment with CONTRACTOR for compliance with the established procedure for their submission and forward with recommendation to ENGINEER noting particularly the relationship of thetyment requested to the schedule of values work completed and materials and cyuitmnent delivered at the site but not 'incorporated in the Work. 9.3.2.10. Completion. 9.3.110.1. Before r•'NGINEER issues a Certificate of Substantial Completion, submit to CONTRACTOR a list of observed items re uirim, correction or completion 9.3.2.10.2. Conduct final inspection in the companv of the ENGINEF..R OWNER and CONTRACTOR'and prepare a final list of items to be corrected or completed. 9.3.2.10.3. Observe that all items on the final list have been corrected or completed and make recommendations to ENGINEER concerning acceptance. 9-3.3. Limitation of Authority: The Representative shall not: 9.3.3.1. Authorize any deviations from the Contract Documents or accot any substitute materials or eyuipment, unless authorized by the ENGINEER. 9.3.33. Exceed limitations of ENGINEER'S authority as set forth in the Contract Documents. 9.3.3.3. Undertake any of the responsihilities of the CONTRACTOR. Subcontractors. or CONTRACTOR'S superintendent 9.3.3.4. Advise on or issue directions relative to, or assume control over any aspect of the means, methods, techniques: sequences or procedures for cornstniction unless such is M)ecifically called for in the Contract Documents. 9.3.35. Advise on or issue directions reizardi ng or assume control over safety precautions and programs in connections with the Work. 9.3.3.6. Accept Shop Drawings or sample submittals from anvone other than the CONTRACTOR 9.3.3.7. Authorize OWNER to occupy the Work in whole or in part. 9.3.3.8. Participate in specialized field or laboratory tests or inspections conducted by others except as soccifically authorized by the ENGINEER Clarifications and Interpretations: 9.4. ENGINEER will issue with reasonable promptness such written clarifications or interpretations of the EJCDCGENERA!.CONDITIONS1910, (IMEdition) wt.C17Y OF FORT COLD NIS MODn7CA-11ONS (REV 4r000) requirements of the Contract Documents (in the form of Drawing or otherwise) as ENGINEER may determine necessary. which shall be consistent with the intent of and reasonably inferable from the Contract Documents. Such written clarifications and interpretations will be binding on OWNER and CONTRACTOR. If OWNER or CONTRACTOR believes that a written clarification or interpretation justifies an adjustment in the Contract Price or the Contract Times and the parties are unable to agree to the amount or extent thereof if any, OWNER or CONTRACTOR may make a written claim therefor as provided in Article I t or Article 12. .authorized Variations in Mork: 9.5: ENGINEER may authorize minor variations in the Work from the requirements of the Contract Documents which do not involve an adjustment in the Contract Price or the Contract Times and are compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. These may he accomplished by a Field Order and will be binding on OWNER and also on CON'1'RAC'rOR who shall perform the Work involved promptly. If OWNER or CONTRACTOR believes. that a Field Orderjustities an adjustment in the Contract Price or the Contract'fimes and the parties arc unable to agree as to the amount or extent thereof, OWNER or CONTRACTOR may make a written claim therefor as provided in Article I 1 or 12. Rejecting Defective {York: 9.6. ENGINEER will have authority to disapprove or reject Work which ENGINEER believes to be defective, or that ENGINEER believes will not produce a completed Project that conforms to the Contract Documents or that will prejudice the integrity of the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. ENGINEER will also have authority to require special inspection or testing of the Work as provided in paragraph 13.9, whether or not the Work is fabricated, installed or completed. .Shop Drawing. Change Orders and Payments: 9.7. In connection. with ENGNEERs authority as to Shop Drawings and Samples, see paragraphs 6.24 through 6.28 inclusive. 9.8. In connection with ENGNEERs authority as to Change Orders. see Articles 10. 11, and 12. 9.9. In connection with ENGINTEER's authority as to Applications for Payment, seeArticle 14. Determinations for Unit Prices. 9.10. ENGINEER will determine the actual quantities and classifications of Unit Price Work performed by CONTRACTOR. ENGINEER will review with CONTRACTOR the ENGINEER's preliminary determinations on such matters before rendering a written decision thereon (by recommendation of an Application 21 for Payment or otherwise). ENGINEER's written decision thereon will be final and binding upon OWNER and CONTRACTOR. unless, within ten days after the date of any such decision, either OWN1 R or CONTRACTOR delivers to the other and to ENGINEER written notice of intention to appeal from ENGINEER's decision and: (i) an appeal from ENGINEER's decision is taken within the time limits and in accordance with the procedures set forth in Exhibit GC:A, "Dispute Resolution Agreement", entered into between OWNER and CONTRACTOR pursuant to Article 16, or (ii) if no such Dispute Resolution Agreement has been entered into, a formal proceeding is instituted by the appealing party in a forum of competent jurisdiction to exercise such rights or remedies as the appealing party may have with respect to E-NG1NFER's decision, unless otherwise agreed in writing by OWNER and CONTRACTOR.. Such appeal will not be subject to the procedures of paragraph 9.11. Decisions an Mputec- U L ENGINEER will be the initial interpreter of the requirements of the Contract Documents and judge of the acceptability of the Work thereunder. Claims, disputes and other matters relating to the acceptability of the Work or the interprew ion of the requirements of the Contract Documents pertaining to the performance and furnishing of the Work and claims under Articles 11 and 12 in respect of changes in the Contract Price or Contract Times will be referred initially to ENGINEER in writing with a request for a formal decision in accordance with this paragraph. Written notice of each such claim, dispute or other matter will be delivered by the claimant to ENGINEER and the other party to the Agreement promptly (but in no event later than thirty days) after the start of -the occurrence or event giving rise thereto, and written supporting data will be submitted to ENGfNhER and the Other party within suety days after the start of such occurrence or event unless ENGINEER allows an Additional period of time for the submission of additional or more accurate data in support of such claim, dispute or other matter. The opposing party shall submit any response to ENGINEER and the claimant within thirty days alter receipt of the claimant's last submittal (unless ENGINTUR allows additional time). LNGNEER will render a formal decision in writing within, thirty days altar receipt of the opposing pany's submittal, if any, in accordance with this paragraph. ENGNEER's written decision on such claim,, dispute or other matter will be final and binding upon OWNER and CONTRACTOR unless: (i) an appeal from ENG INEER's decision is taken within the time limits and in accordance with the procedures set forth in EXHIBIT GC -A, "Dispute Resolution Agreement", entered into between OWNER and CONTRACTOR pursuant to Article 16, or (ii) if no such Dispute Resolution Agreement has been entered into, a written notice, of intention to appeal from ENGNEERs written decision is delivered by OWNER or CONTRACTOR to the other and to ENGINEER within thirty days after the date of such decision and a formal proceeding is instituted by the appealing party in a forum of competent jurisdiction to exercise such rights or remedies as the appealing party may have with respect to such claim, dispute or other matter in accordance with applicable Laws and Regulations within sixty days of the date of such EJCDC GLNERAL CONDITIONS 1910-8 (1990 Editim) 22 w! CITY OF FORT COLLI NS MODIFICATIONS (REV 4Q006) decision. unless otherwise agreed in writing by OWNER and CONTRACTOR 9.12. When functioning as interpreter and judge under paragraphs9.10 and 9.1.1. ENGINEER will not show partislity [O,O11rNER or CONTRACTOR and will not be liable in connection with any interpretation or decision rendered in good faith in such capacity. The rendering of a decision by ENGINEER pursuant to paragraphs 9.10.or 9.11 with respect to any such claim, dispute or other matter (except any which have been waived by the making or acceptance of final payment as provided in paragraph 14.15) will be a 'condition precedent to any exercise by OWNER or CONTRACTOR of such rights or remedies as either may otherwise Have under the Contract Documents or by Laws or Regulations in respect of any such claim, dispute or other matterpursaari"&AFtir.1*46. 9.13. Limitations on GVGINEER's Authwity and Regromdlrilitiev. 9,13.1. Neither ENGINEER's authority or responsibility under this Article 9 or under any other provision ofthe C.ontract.Documentsnor any decision made by ENGINEER in good faith cithcrto exercise or not exercise such authority or responsibility or the undeftaking exercise or performance of any authority or responsibility by ENGINEER shall create, impose or give rise to any duty owed by ENGINEER to CONTRACTOR, arty Subcontractor, any Sul-4ilier, any other person or organization or to any surety for or employee or agent of any of them. 9.13.2. ENGINEER will not supervise, direct, control or have authority over or be responsible for CONTRACTOR's means, metho .% techniques, sequences or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of CONTRACTOR to comply with Laws and Regulations applicable to the furnishing or performance of the Work. ENGINIE-R will not be responsible for CONTRACTOR's failure to perform or ti m sh the Work in accordance with the Contract Documents. 9.13.3. ENGINEER will not be responsible for the acts or omissions of CONTRACTOR or of any Subcontractor, any Supplier, or of any other person or organization performing or furnishing any of the Work. 9.13.4. ENGNEER's review of the final Application for Payment. and accompanying documentation and all maintenance and operating instructions,. schedules. guarantees, Bonds aria certificates of inspection, tests and approvals and other documentation required to be delivered by l aragraph 14.12 will only be to determine generally that their content complies with the requirements of and in the case of certificates of mspectloru, tests and approvals that the results certified indicate compliance with, the Contract Documents. 9,13.5. The limitations upon authority and responsibility set forth in this paragraph 9,13 shall also apply to ENGI NEER's Consultants, Resident Project Representative and assistants. ARTicu 10—CHAiNGES IN THE WORK 10.1. Without invalidating the Agreement and without notice to any surety, OWNER may, at any time or from time to time, order additions, deletions or revisions in the Work. Such additions, deletions or revisions will be authorized by a Written Amendment, a Change Order, or a Work Change Directive. Upon receipt of any such document, CONTRACTOR shall promptly proceed with the Work involved which will be performed under the applicable conditions of the Contract Documents (except as otherwise specifically provided). 10.2. If OWNER and CONTRACTOR are unable to agree as to the extent, if any; of an adjustment in the Contract Price or an adjustment of the Contract Times that should be allowed as a result of a Work Change Directive, a claim may be made therefor is provided in Article I 1 or Article I1 10.3, CONTRACTOR shall not be entitled to an increase in the Contract Price or an extension of the Contract Times with respect to any Work performed that is not required by the Contract Documents as amended, modified and supplemented as provided in paragraphs 3.5 and 3.6, except in the case of an emergency as provided in paragraph 6.23 or in the case of uncovering Work as provided in paragraph 13.9. 10.4. OWNER and CONTRACTOR shall execute appropriate Change Orders recommended by ENGINEER (or Written Amendments) covering: 10.4,1. changes in the Work which are (i) ordered by OWNER pursuant to paragraph 10.1, (ii) required because of acceptance of ctejective Work under paragraph 13.13 or correcting defective Work under paragraph 13.14, or (iii) agreed to by the parties, 10,4.2. changes in the Contract Price or Contract Times which are weed to by the parties; and 10.43. changes in the Contract Price or Contract Times which embody the substance of any written decision rendered by ENGINEER pursuant to paragraph 9.11; provided that, in lieu of executing any such Change Order, an appeal may be taken from any such decision in accordance with the provisions of the Contract Documents and applicable Laws and Regulations, but during any such appeal, CONTRACTOR shall carry on the Work and adhere to the progress schedule as provided in paragraph 6.29. 10.5. If notice of any change affecting the general scope of the Work or the provisions of the Contract Documents EJCDCGENERAL CONDITIONS 1910-13 (1990 E(itigO w/ CITY OF FORT COLLINS MODIFTCA-riONS (REV 4R000) (including, but not limited to, Contract Price or Contract Times) is required by the provisions of any Bond to be given to a surety, the giving of. any such notice will be CONTRACTOR's responsibility, and the amount of each applicable Bond will be adjusted accordingly. M'FICLE: I I —CHANGE: OF CONTRACT PRICE I i.l. The. Contract Price constitutes the total compensation (subject to authorized adjustments) payable to CONTRACTOR for performing the Work. All duties, responsibilities and obligations assigned to or undertaken by CONTRAM'OR shall beat CONTRACTOR',.; expense without change in the Contract Price. 11.2. The Contract Price may only be changed by a Change Order or by a Written Amendment Any claim for an adjustment in the Contract Price shall be based on written notice delivered by the party making the claim to the other party and to ENGINEER promptly (but in no event later than thirty clays) after the start of the occurrence or event giving rise to the claim and stating the general nature of the claim. Notice of the amount of the claim with supporting data shall be delivered within sixty days after the start of such occurrence or event (unless ENGINEER allows additional time for claimant to submit additional or more accurate data in support of the claim) and shall be accompanied by claimant's written statement that the adjustment claimed covers all known amounts to which the claimant is entitled as a result of said occurrence or event. All claims for adjustment, in the Contract Price shall be determined by ENGINEER in accordance with paragaph 9.11 if OWNER and CONTRACTOR cannot otherwise agree on the amount involved. No claim for an adjustment in the Contract Price will be valid if not submitted in accordance with this paragraph 11.2. 11.3. The value of any. Work covered by a Change Order or of any claim for an adjustment in the Contract Price will be determined as fullows: 113.1. where the Work involved is covered by unit prices contained in the Contract Documents, by application of such unit prices to the quantities of the items involved (subject to the provisions of 23 paragraphs 11.9.1 through 11.9.3, inclusive); 11.3.2. where the Work involved is not covered by unit prices contained in the Contract Documents, by a mutually agreed payment basis, including lump sum (which may include an allowance for overhead and profit not necessarily in accordance. with paragraph 11.6.2): 11.3.3. where the.Work involved is not covered by unit prices contained in the Contract Documents and agreement to a lump sum is not reached under paragraph 11.3.2, on the basis of the Cost of the Work (determined as provided in paragraphs 11Aand 11.5) plus a CONTRACTOR's fee for overhead and profit (determined as provided in paragraph 11.6). Cost of rlre Work: 11.4, 'The term Cost of the Work means the stun of all costs.necessarily incurred and paid by CONTRACTOR in the proper performance of the Work. Except as otherwise may be agreed to in writing by OWNER, such costs shall be in amounts no higher than those prevailing. in the locality of the 1?roject, shall include only the following items and shall not include any of the costs'itcmized in paragraph 11.5: 11A.I.Pqyroll costs for employees in the direct employ of CONTRACTOR in the performance of the Work under schedules of job classifications agreed upon by OWNER and CONTRACTOR. Such employcs shall include without limitation superintendents, foremen and other . personnel employed full-time at the site. Payroll costs for employees not employed full -titre on the Work shall be apportioned on the basis of their time spent on the Yoric payroll costs shall iraslud,-but•not be limited to; salaries and wages plus the cost of fringe benefits which shall include social security contributions, unemployment, excise and payroll taxes, workers' compensation, health and -retirement benefits; bonuses; Andholi-44A, pay applicable thereto. The expenses of performing Work after regular working hours, on Saturday, Sunday or legal holidays, shall be included in the above to the extent authorized by OWNER. 11.4.2. Cost of all materials and equipment furnished and incorporated in the Work, including costs, of transportation and storage thereof, and Suppliers', field services required in connection therewith All cash discounts shall . accrue to CONTRACTOR unless OWNER deposits funds with CONTRACTOR with which to make payments, in which case the cash discounts shall accrue to OWNER. All trade discounts, rebates and refunds and returns from sate of surplus materials and equipment shall acme to OWNER and CONTRACTOR shall make provisions so that they may be obtained.. 11.4.3, payments made by CONTRACTOR to the Subcontractors for Work performed or furnished by Subcontractors. If required by OWNER, EJCDCGENERALCONUI'1 oNsoio4(i99oEditim) 24 w/ CITY OF FORT COLLI Ivy MODIFICATIONS (RLV 4(1000) CONTRACTOR shall obtain competitive bids from Subcontractors acceptable to OWNER and CONTRACTOR and shall deliver such bids to OWNER who will then.determine, with the advice of ENGINEER. which bids, if any, will be accepted. If any subcontract provides that the Subcontractor is to be paid on the basis of Cost of the Work plus a fee, the Subcontractor's Cost of the Work and fee shall be determined in the same manner as CONTRACTOR's Cost of the Work and fee as provided in paragraphs 11.4, 11:5, 11.6 and 11.7. All subcontracts shall be subject to the other provisions of the Contract Documents insofar as applicable. 11.4.4. Costs of special consultants (including but not limited to enginedrs, architects, testin laboratories, surveyors, attorneys and accountants employed for services specifically related to the Work. 11.4.5. Supplemental costs including the following: 11 A.5.1. The proportion of necessary transportation, travel and subsistence expenses of CONfRACTOR's employees incurred in discharge of duties connected with the Work. 11.4.5.2. Cast, including transportation and maintera<ance, of all materials, supplies, equipment, machinery, appliances, ounce and temporary facilities at the site and hand tools not owned by the workers, which arc consumed in the performance of the Work, and cost Jess market value of such items used but not consumed which remain the property of CONTRACTOR. 11 A,53. Rentals of all construction equipment and machinery and the parts thereof whether rented from CONTRACTOR or others in accordance with rental agreements approved by OWNER with the advice of ENGINEER, and the costs of transportation, loadini; unloading, installation, dismantling and removal thereof —all in accordance with terms of said rental agreements. The rental of any such equipment, machinery or, parts shall cease when the use thereof is no longer necessary for the Work. 11.4.5.4. Sales, consumer, use or similar taxes related to the Work, and for which CONTRACTOR is Gable, imposed by Laws and Regulations. 11.4.5.5. Deposits lost for causes other than negligence of CONTRACTOR, any Subcontractor or anyone directly or indirectly employed by any of them or for whose acts any of than may. be liable, and royalty payments and fees for permits and licenses. 11.4.5,6. Losses and damages (and related expenses) caused by damage to the Work, not compensated by insurance or otherwise, sustained by CONTRACTOR in connection with the performance and furnishing of the Work (except losses and damages within the deductible amounts of property insurance established by Ol«tER in accordance with paragraph 5.9), provided they have resulted from causes other than the negligence of CON -CRAG -OR, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable. Such losses shall include settlements made with the written consent and approval of OWNER No such losses, damages and expenses shall be included in the Cost of the Work for the purpose of determining CONTRACTOR's fee. IE however, any such loss or damage requires reconstruction and CONTRACTOR is placed in charge thereof, CONTRACTOR shall be paid for services a fee proportionate to that stated in paragraph 11.6.2. 11.4.5.7. The cast of utilities; furl and sanitary facilities at the site. 1.1.4.5.5. Minor expenses such as telegrams, long distance telephone calls, telephone service at the site, expressage and similar petty cash items in connection with the Work. 11.4:5.9. Cost of premiums for additional Bonds and insurance required because of changes in the Work. 11.5. The term Cost of the Work shall not include any of the following: 11.5.1. payroll costs and other compensation of CONTRACTOR's officers, executives, principals (of partnership and sole proprietorships), general managers, engineers, architects, estimators, attornevs, auditors, accountants, purchasing and contracting agents, expediters, timekeepers, clerks and other personnel employed by CONTRACTOR whether at the site or in CONTRACTOR's principal or a branch office for general administration of the Work and not specifically included in the agreed upon schedule of job classifications referred to in paragraph 11 4.1 or specifically covered by paragraph I1,4,4—all of which are to be considered administrative costs covered by the CONTRACTOR's fee. 11.5.2). Expenses of CONTRACTOR's principal and branch .offices other than CONTRACTOR's office at the site. 11:5.3. Any part of CONTRACTOR's capital expenses, including interest on CONTRACTOR'S capital employed for the Work and charges against CONTRACTOR for delinquent payments. 11.5.4. Cost of premiums for all Bonds and for all insurance whether or not CONTRACTOR is required by the Contract Documents to purchase and maintain the same (except for the cost of premiums covered by subparagraph 11.4.5.9 above). EXI)C GENERAL CONDITIONS 1910-3 (1990 El itim) ce! CITY OF FORT COLLINS MODIFICATIONS (REV 4R000) 11.55. Costs due to the negligence of CONTRACTOR, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable, including but not limited to, the correction of ckfectnx Work., disposal of materials or equipment wrongly supplied and making good any damage to property: 11.5.6. Other overhead or general expense costs of any kind and the costs of any item not specifically and expressly included in paragraph 11.4. I L& The CONTRACTOR's fee allowed to CONTRACTOR for overhead and profit shall be determined as follows: 11.6.1. a mutually acceptable fixed fee; or 11.6.2. if a fixed fee is not agreed upon, then a fee based on the following percentages of the various portions of the Cost ofthe Work. 11_6.2.1. for casts incurred under paragraphs 11.4.1 and 11.4.2, the CONTRAM'OR's fee shall be fifteen percent; 11.6.2.1 for casts incurred under paragraph 11.4.3, the CONTRACTOR's fee shall be five percent; II'6.2.3. where one or more tiers of subcontracts arc on the basis of Cost of the Work plus a fee and no fixed fee is agreed upon, the intent of paragraphs 11.4.1, 11.4.2, 11.4.3 and I E6.2 is that the Subcontractor who actually performs or furnishes the Work, at whatever tier, will be paid a fee of fifteen percent of the costs incurred by such Subcontractor tinder paragraphs 11.4.1 and 11.4.2 and that any higher tier Subcontractor and CONTRACTOR will each be paid afee-of-fiva percent-o�thertintot)iU-pail-to the -next -lower -tier Subcontractor; to be ne og iiated in good faith with the OWNER but not to exceed five percent of the amount paid to the next lower tier Subcontractor. 11.6.2.4. - no fee shall be payable on the basis of costs itemized under paragraphs 11.4.4, 11.4.5 and 1 l .5: 11.6:2.5. the amount of credit to be allowed by CONTRACTOR to OWNER for any change which results in a net decrease in cost will be the amount of the actual net decrease in cost plus a deduction in CONTRACTOR's fee by an amount equal to five percent of such net decrease; and 11.6.2.6. when both additions and credits, are involved in any one change, the adjustment in CONTRACTOR'S fee shall be computed on the basis of the: net change in accordance with paragraphs 11.6.2.1 through 11.62.5, inclusive. 11.7. Whenever the cast of any Wort: is to be 25 determined pursuant to paragraphs 11.4 and 11.5. CONTRACTOR will establish and maintain records thereof in accordance with generally accepted accounting practices and submit in form acceptable to LNGI\i rEER an itemized cost breakdown together with supporting data. Cash .411axances: 11.8. It is understood that CONTRACTOR has included in the Contract Price all allowances so named in the Contract Documents and shall cruse the Work so covered to be furnished and performed for such sums as may be acceptable to OWNER and ENGINEER. CONTRACTOR agrees that: 11.8.1, the allowances include the cost to CONTRACTOR (less any applicable, trade discounts) of materials and equipment required by the allowances to be delivered at the site, and all applicable taxes; and 11.8.2. CONTRACTOR's costs for unloading and handling on the site, labor, installation costs, overhead, profit and other expenses contemplated for ' the allowances have been included in the Contract Price and not in the allowances and no demand for additional payment on account of any of the foregoing will be valid, Prior to final payment, -inappropriate Change Order will be issued as recommended by ENGINEER to reflect actual amounts due CONTRACTOR on account of Work covered by allowances, and the Contract Price shall be correspondingly adjusted. 11.9. Unit Price Work.- 11.9.1. Where the Contract Documents provide that all or part of the Work is to be Unit Price Work. initially the Contract Price will be deemed to include for all Unit. Price Work an amount equal to the sum of the established unit prices for each separately identified item of Unit Price Work times the estimated quantity of each item as indicated in the Agreement. The estimated quantities of items of Unit Price Work arc• not guaranteed and are solely for the purpose of comparison of Bids and determining an initial Contract Price. Determinations of the actual quantities and classifications of Unit. Price Work performed by CONTRACTOR will be made by ENGINEER a accordance with paragaph9.10. 11.9.2. Each unit price will be deemed to include an amount considered by CONTRACTOR to be adequate to cover CONTRACTOR's overhead and profit for each separately identified item. H.93:OWNER or CONTRACTOR may make a claim for an adjustment in the Contract Price in accordance with Article I 1 if. 11.9.3.1. the quantity of any item of Unit Price. Work performed by CONTRACTOR differs materially and significantly from the estimated quantity of such item "indicated in the Agreement; EJCDC GENERAL CONDITIONS 19 t 0-9 (1990 Edition) 26 w/CITYOFFOR'rCOLLINS NIODIFICA'rIONSaREV4P000) and 11.9.3.2. there is no corresponding adjustment with respect to any other item of Work; and 11 9.3:3. if CONTRACTOR. believes that CONTRACTOR is entitled to an increase in Contract Price as a result of having incurred additional expense or OWNER believes that OWNER is entitled to a decrease in Contract Price and the parties are unable to agree as to the amount of any such increase or decrease. 11.9.3.4. CONTRACTOR acknowledges that the OWNER has the right to add or delete items in the Bid or change quantities at OWNER'S sole discretion without affecting the Contract Price of anv remaining item so lone as thedeletion or addition does not exceed twenty-five percent of the original total Contract Price. ARTICLE" 12--CHANGE OFcoN'rwt,C"f TIMES 12.1, The Contract Times (or Milestones) may only be changed by a Change Order or a Written Amendment. Any claim for an adjustment of the Contract Times (or Milestones) shall be based on written notice delivered by the party making the claim to the other party and to ENGINEER promptly (but in no event later than thirty days) after the occurrence of the event giving rise to the claim and stating the general nature of the claim. Notice of the extent of the claim with supporting data shall be delivered within si\V days after such occurrence (unless ENGINEER allows additional time to ascertain more accurate data in support of the claim) and shall be accompanied by the claimant's written statement that the adjustment claimed is the entire adjustment to which the claimant has reason to believe it is entitled as a result of the occurrence of said event. All claims for adjustment in the Contract Times (or N-lilestones) shall be determined by ENGINEER in accordance with pamgmph 9.11 if OWNER and CONTRACTOR cannot otherwise agree. No .claim for an adjustment in the Contract Times (or Milestones) will be valid if not submitted in accordance with the requirements of this paragraph 12.1. 12.2, All time limits stated in the Contract Documents are of the essence of the Agreement. 12.3: Where CONTRACTOR is prevented from completing any part of the Work within the Contract Times (or Milestones) due to delay beyond the control of CONTRACTOR, the Contract Times (or Milestones) will be extended in an amount equal to time lost due to such delay if a claim is made therefor as provided in paragraph l'_.l. Delays beyond the control of CONTRACTOR shall include, but not be limited to, acts or neglect by OWNER, acts or ne0ect of utility owners or other contractors performing other work as contemplated by Article 7, foes. floods. epidemics. abnormal weather conditions or acts of God. Delays attributable to and 15,4ACE Am BRACE - B, ARAZ! A4 /-N Wl WOOL fL05 it -A, ta Me ­ I— =�) ed A. COf[NfbN Ell ROOF FRA M/A/G PLAN I. 1­1 1114 bl"! =All— GA., No.To ­f be". VE PLAN ­CIAL WELDING .7 CD these a-bu!)t dravt ngs have been prepay d, In Part, 01 the ba31f or seed b, othe 11. The Alhi 'C' -1.0— Ich he. fncorgorat.A (FRnML (FRAM! 6EC PLAN BM SEE. eAAl 7'YP ANGLE FRAME AROUND AIECH. 01061VINGS IN.F400R e A?ooF IQ fe ­E: ­pr —10 within the control of a Subcontractor or Supplier shall be deemed to be delays within the control of CONTRACTOR. 12.4. Where CONTRACTOR is prevented from completing any part of the Work within the Contract Times (or Milestones) due to delay beyond the control of both OWNER and CONTRACTOR, an extension of the Contract Times (or Mlestones) in an amount equal to the time lost due to such delay shall be CONTRACTOR's sole and exclusive remedy for such delay. In no event shall OWNER be liable to CONTRACTOR, any Subcontractor, any Supplier, any other person or organization, or to any surety for or employee or agent of any of them, for damages arising out of or resulting from (i) delays caused by or within the. control of the CONTRACTOR, or (ii) delays heyond the control of both parties including, but not limited to, firm floods, epidemics; abnormal weather conditions, acts of God or acts or neglect by utility owners or other contractors performing other work as contemplated by Article 7. ARTICLE: 13—TFSTS AND INSPECTIONS; CORRECTION, REMOVA[, OR ACCElr1'ANCE OF DEfECTIhT WORK 13.1. Notice of Defects: Prompt notice of all defective Work of which OWNER or ENGINEER have actual knowledge will be given to CONTRACTOR. All defective Work may be rejected, corrected or accepted as provided in this Article 13. Access to I{'ork: 13.2. OWNER, ENGINEER, I"NGINEERs Consultants. other representatives and personnel of OWNER, independent tasting laboratories and governmental agencies with jurisdictional interests will have access to the Work at reasonable —tittles for thew observation, inspecting and testing. CONTRAC,fOR shall provide them proper and safe conditions for such access and advise them of CONTRACTOR's site safety procedures and programs so that they may comply therewith as applicable. Tests and Inspections: 13.3. CONTRACTOR shall give ENGINEER timely notice of readiness of the Work for all required inspections, tests or approvals, and shall cooperate with inspection and testing personnel to facilitate required inspections or tests. 13.4. OWNER shall employ and pay for the services of an independent testing laboratory to perform all inspections, tests, or approvals required by the Contract Documents except: 13A.1. for inspections, tests or approvals covered by paragraph 13.5 below; 13.4.2. that costs incurred in connection with tests or inspection, conducted pursuant to paragraph 13.9 EJCDC GENERAL CONDITIONS 1910 et (1990 Editim) wf CITY OF FORT COLLINS MODIFICATIONS (REV 42000) below shall be paid as provided in said paragraph 13.9; and 13.4.3. as otherwise specifically provided in the Contract Documents. 135. If Laws or Regulations of any public body having jurisdiction require any Work (or part thereof) specifically to be inspected, tested or approved by an employee or other representative of such public body. CONTRAGI'OR shall assume Cull responsibility for arranging and obtaining such inspections, tests or approvals, pay all costs in connection therewith, and funnish FNGI'NFFR the required certificates of inspection, or approval. CONTRACTOR shall also be responsible for arranging and obtaining and shall pay all costs in connection with any inspections, tests or approvals required for OWNERS and ENGINEER's.acceptance of materials or equipment to be incorporated in the Work, or of materials, mix designs, or equipment submitted for approval prior to CONTRACTOR's purchase thereof for incorporation in the Work. 13.6. If any Work (or the work of others) that is to be inspected, tested or approved is covered by CONTRACTOR without written concurrence of ENGINEER, it must, if requested by FNGINFER, be uncovered for observation. 13.7. Uncovering Work as provided in paragraph 13.6 shall be at CONTRACTOR's expense unless CONTRACTOR has given FNGINF..ER timely notice of CONTRr\CTOR's . intention to cover the same and FNGINFFR has not acted with reasonable promptness in response: to such notice. Uncovering (York: 13.8. If am, Work is covered contrary to the written request of ENGMER, it must, if requested by ENGINEER, be uncovered for ENGNEER's observation and replaced at CONTRACTOR's expense. 13.9: If FNi GINFF.,R considers it necessary or advisable that covered Work be observed by ENGINEER or inspected or tested by others, CONTRACTOR at ENGNEER's request, shall uncover, expose or otherwise make available for observation, inspection or testing as ENGINEER may require, that portion of the Work in question, furnishing all necessary Libor, material and equipment. If it is found that such Work is defective, CONTRAGTOR shall pay all claims, costs, losses and damages, caused by, arising out of or resulting from such uncovering; exposure; observation, inspection and testing and of satisfactory replacement or reconstruction, (including but not limited to all costs of repair or replacement of work of others); and OWNER shall be entitled to an appropriate decrease in the Contract Price, and, if the parties are unable to agree as to the amount thereoc may make a ,claim therefor as provided in Article 11. If, however, such Work is not found to be defective, CONTRAGI.OR: shall be allowed an increase in the Contract Price or an extension of the Contract Times (or Milestones), or both, directly attributable to such 27 uncovering, exposure, observation, inspection, testing,. replacement and reconstruction; and, if the parties are unable to agree as to the amount or extent thereof. CONTRACTOR may make a claim therefor as provided in Articles I I and 12, 01VNER clay Stop the ff''o& 13.10. if the Work is defecfive, or CONTRACTOR fails. to supply sufficient skilled workers or suitable materials or equipment; or fails to furnish or perform the Work in such a way that the completed Work will conform to the Contract Documents, OWNER may order CON,rRAC'TOR to stop the Work. or any portion thereof, until the cause for such order has been eliminated; however, this right of OWNER to stop the Work shall not give rise to any duty on the. part of OWNER to exercise this right for the benefit of CONTRACTOR or any surety or other party. Correction or Removal of Defective Mork: 13.11. if required by ENGINEER, CONTRACMR. shall promptly, as directed, either correct all defective Work, whether or not fabricated, installed or completed, or, if the Work has been rejected by ENGI NEM remove it from the site and replace it with Work that is not defective. CONfRACI'OR shall pay all claims, costs, lasses and damages Mused by or resulting from such correction or removal (including but not limited to all casts of repair or replacement of work of others). 13.12. Correction Period. 13.12.1. If within one yea two years after the date of Substantial Completion or such longer period of time as may be prescribed by Laws or Regulations or by the terms of any applicable special guarantee required by the Contract Documents or by any specific provision.of the Contract Documents, ariv Work is found to be defective, CONTRACTOR shall promptly, without cast to OWNER- and in accordance with OWNERS written instructions: (i) correct such ckfeefive Work, or, if it has been rejected by OWNER, remove it from the site and replace it with Work that is not defective, and (ii) satisfactorily correct or remove and replace any damage to other Work or the work of others resulting therefrom. If CONTRACTOR does not promptly comply with the terms of such instructions, or in an emergency where delay would cause serious risk of loss or damage, OWNER may have the defective Work corrected or the rejected Work removed and replaced, and all claims, costs, losses and damages caused by or resulting from such removal and replacement (including but not limited to all costs of repair or replacement of work of others) will be paid by CONTRACTOR 13.12.2.In special circumstances where a particular item of equipment is placed in continuous service before Substantial Completion of all the Work, the correction period for that item may start to. run from an earlier date if so provided in the Specifications or by Written Amendment: 13.12.3. Where defective. Work (and damage to other �S EXI)C GENER.�IL CONDMoNs 1910 S (1990 Edition) WICITY OF FORT COLLINS MODIFICATIONS (RLV 42000) Work resulting therefrom) has been corrected, removed or replaced under this paragraph 13.12, the correction period hereunder with respect to such Work will be extended for an additional period of ene-yeaF two year after such correction or removal and replacement has been satisfactorily completed. Acceptance ofDefecfive'Work: 13.13. IC instead of requiring correction or removal and replacement of defective Work, OWNER (and, prior to ENGINEER'S recommendation of final payment, also ENGINEER) prefers to accept it, OWNER may do so. CONTRACTOR shall pay all claims, costs, lasses and damages attributable to OWNER'S evaluation of and determination to accept such defectve Work (such costs to be approved by ENGI LEER as to reasonableness;). 1 f any such acceptance occurs prior to ENGINEERS recommendation of final payment, a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work. and OWNER shall be entitled to an appropriate decrease in the Contract Price, and, if the parties are unable to agree as to the amount thereof, OWNER may make a claim therefor as provided in Article 11. If the acceptance occurs after such recommendation, an appropriate amount will be paid by CONTRACI'OR to OWNER. 011,1+ER Correct Defective Work: 13.14. If CONTRACTOR fails within a reasonable time after written notice from ENGINEER to correct d /ectnre Work or to remove and replace rejected Work as required by ENGINEER in accordance with Paragraph 13.11. or if CONTRACTOR fails to perform the Work. in accordance with the Contract Documents, or if CONTRACTOR fails to, comply with any other provision of the Contract Documents, OWNER may, after seven days' written notice to CONTRACTOR, correct and remedy any such deficiency. In exercising the rights and remedies under this paragraph OWNER shall proceed expeditiously. In correction with such corrective and remedial action. OWNER may exclude CONTRACTOR from all or part of the site, take possession of all or part of the Work, and suspend CONTRACTOR's services related thereto, take possession of CONTRACTOR's tools, appliances, construction equipment and machinery at the site and incorporate in the Work all materials and equipment stored at the site or for which OWNER has paid CONTRACTOR but which are stored elsewhere. CONTRACTOR shall allow OWNER OWNER's representatives, agents and employees. OWNER's other contractors and ENGINEER and ENGINEERS Consultants access to the site to enable OWNER to exercise the. rights and remedies under this paragraph All claims, costs, losses and damages incurred or sustained by OWNER in exercising such rights and remedies will be charged against CONTRACTOR and a Chine Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and OWNER shall be entitled to an appropriate decrease in the Contract Price, and, if the parties arc unable to agree as to the amount thereof,- OWNER may make a claim therefor as provided in Article 11. Such claims, costs, lasses and damages will include but not be limited to all costs of repair or replacement of workof others destroyed or damaged by correction removal or replacement of CONTRACTOR's defective Work. CONTRACTOR shall not be allowed an extension of the Contract Times (or Milestones) because of any .delay in performance of the Work attributable to the exercise by O\VNER of OWNERS rights and remedies hereunder. ARTICLE 14--PAYNW—N'TS TO CONTRACTOR rLND CONIPLETION Schedule of Maluer 14.1. 'ncc schedule of values established as provided in paragraph 2.9 will serve as the basis for progress payments and will be incorporated into a form of Application for Payment acceptable to ENGINEER. Progress payments on account of Unit Price Work will be based on the number of units completed Application for Progress Payment. 14.2. At least twenty days before the date established for each progress payment (but not more often than once a month), CONTRACTOR shall submit to ENGINEER for review an Application for Payment filled out and signed by CONTRACTOR covering the Work completed as of the date of the Application and accompanied by such supporting documentation as is required by the Contract Documents, If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the site or at another location agreed to in writing, the Application for Payment shall also be accompanied by a bill of sale, invoice or other documentation warranting that OWNER has received the materials and equipment free and clear of all Liens and evidence that the materials and equipment are covered by appropriate property insurance and tither arrangements to protect OWNIR's interest therein, all of which will be satisfactory to OWNER. The amount of retainage with respect to progress payments will be as stipulated in the Agreement. Any funds that are withheld by the OWNER shall not be subiect.to substitution by the CONTRACTOR with securities or anv arrangements involving an escrow or custodianship. By e:cecuting the application for payment form the CONTRACTOR expressly waives his right to the benefits of Colorado Revised Statutes, Section 24-91-101, et M. CO,VTR4CTOR's Warrano of Title: 1.4.3. CONTRACTOR warrants and guarantees that title to all Work, 'materials and equipment covered by any 'lpplication for Payment whether incorporated in the Project or not, will pass to OWNER no later than the time of payment free and clear of all Liens. Review of.4pplieations for Progress Payment. 14.4. ENGINEER will. within ten days after receipt of each Application for Payment, either indicate in writing a EKVC GENERAL CON0111ONS 19103 (1990 E(fition) w/ CITY 01: FORT COLLINS MODIRCAMNS (REEEV 4R000) recommendation of payment and present the Application to OWNER, or return the Application to CONTRACTOR indicating in writing ENGLNEER's reasons for refusing to recommend payment. In the latter case, CONTRACTOR may make the necessary corrections and resubmit the Application. 'fen days after presentation of the Application for Payment to OWNER with ENGINEER's recommendation, the amount recommended will (subject to the provisions of the last sentence of paragraph 14.7) become due and when due will be paid by OWNER to CONTRACTOR 14.5. ENGINEF.Ws recommendation of any payment requested in an Application for Payment will constitute a representation by ENGINEER to OWNER, based on FNGINF..FR's on -site observations of the executed Work as an experienced and qualified design professional and on ENGINF.ER's review of the Application for Payment and the accompanying data and schedules. that to the best of fiNG1NFFR's knowledge, information and belief: 14.5.1. the Work has progressed to the point indicated, 1.4.5'2. the quality of the Work is generally in accordance with the Contract Documents (subject to an evaluation of the Work as a functioning whole prior to or upon Substantial Completion, to the results of any subsequent tests called for in the Contract Documents, to a final determination of quantities and classifications for Unit Price Work under paragraph 9.10, and to any other qualifications stated in the recommendation), and 14.5.3. the conditions precedent to CONTRACTOR's being entitled to such payment appear to have been fulfilled insofar as it is ENGI,i IEER's,responsibility to observe the Work. However, by recommending any such payment ENGINEER will not thereby be deemed to have represented that: (i) exhaustive or continuous 'on -site i tspections have been made to check the quality or the quantity of the Work beyond the responsibilities specifically assigned to ENGINEER in the Contract Documents or (it) that there may not be other matters or issues between the parties that might entitle CONTRACTOR to be paid additionally by OWNER or entitle OWNER to withhold payment to CONTRACTOR. 14.6. ENGINEER's recommendation of any payment, including final payment shall not mean that ENGINEER is responsible for CONTRACTOR's means; methods, techniques, sequences or procedures of construction or the safety precautions and programs incident thereto, or for any failure of CONTRACTOR to comply with Laws and Regulations applicable to the furnishing or performance of Work, or for any failure of CONTRACTOR to perfomt or furnish Work in accordance with the Contract Documents. 14.7. ENGINEER may refuse to recommend the whole or any part of any payment if. in ENGINEER's.opinion. it would be incorrect, to make the representations to 29. OWNER referred to in paragraph 14.5. ENOMMER may also refuse to recommend any such payment, or, because of subsequently discovered evidence or the results of subsequent inspections or tests, nullify any such payment previously recommended, to such extent as may be necessary in ENGINEER's opinion to protect O"NrER from loss because: 1.4.7.1. the Work is cltfective, or completed Work has been damaged requiring correction or replacement. 14.72. the Contract Price has been reduced by Written Amendment or Change Order, 14.7.3. OWNER has been required to correct defective Work or complete Work in accordance with paragraph 13.14, or 14.7.4. ENGINEER has actual knowledge of the occurrence of any of the events enumerated in paragraphs 15.2.1 through 15.2.4 inclusive. OWNER may.refuse to make payment of the full amount recommended by ENGINEER because: 14.7.5. claims have been made against ORTIF,R on account of CONI'RACI'OR.'s performance or furnishing of the Work, 14.7.6. Liens have been tiled in connection with the Work, except where CONTRACTOR has delivered a specific Bond satisfactory to OWNER to secure the satisfaction and discharge of such Liens, 14.7.7. there are other items, entitling OWNER toa set- off against against the amount recommended, or 14.7.8. OWNER has actual knowledge of the occurrence of anv of the events enumerated in paragraphs 14,71 [}trough 14.73 or paragraphs 15.2.1 through 15.2.4 inclusive; but OWNER must give CONTRACTOR immediate written notice (with a copy to ENGINEER) stating the reasons for such action and promptly pay CONTRACTOR the amount so withheld, or any adjustment thereto agreed to by OWNER and CONTRACTOR, when CONTRACTOR corrects to OWNER's satisfaction the reasons for such action Sub&andal comple4an: 14.8. When CONTRACTOR considers the entire Work ready for its intended use CONTRACTOR shall notify OWNER and ENGINEER in writing that the entire Work is substantially complete (except for items specifically listed by CONTRACTOR as incomplete) and request that ENGINEER issue a certificate of Substantial Completion. Within a reasonable time thereafter, OWNER. CONTRACTOR and ENGINEER shall make an inspection of the Work to determine the status of completion If ENGINEER does not consider the Work substantially complete, ENGINEER Will notify CONTRACTOR in writing giving the reasons therefor. If ENGINEER EJCDC UENUM CONU TIONS 1910-8 U990 E(htiat) 30 w! CITY OF FORT COLLI M MODIFICATIONS (REV 4,2006) considers the Work substantially complete; ENGINEER will prepare'and deliver to OVVAfER a tentative certificate of Substantial Completion which shall fix the date of Substantial Completion. There shall be attached to the certificate a tentative list of items to be completed or corrected before final payment OWNER shall have seven days after receipt of the tentative certificate during which to make written objection to ENGINEER as to any provisions of the certificate or attached list.. If, after eonsiderino such objections, ENGINEER concludes that the Work is not substantially complete, ENGINEER will within fourteen days after submission of the tentative certificate to OWNER notify CONTRACTOR in writing; stating the reasons therefor. If, after consideration of OWNER's objections, ENGINEER considers the Work substantially complete; ENGINEER will within said fourteen days execute and deliver to 'OWNER and CON'I`RAC'I'OR a definitive certificate of Substantial Completion (with a revised tentative fist of items to be completed or corrected) reflecting such changes from the tentative certificate as ENGINEER believes justified after consideration of any objections from OWNER. At the time of delivery of the tentative certificate of Substantial Completion ENGINF..ER will deliver to OWNER and CONTRACTOR a written recommendation as to division of responsibilities pending final payment between OWNER and CONTRACTOR with respect to security, operation, safety, maintenance, heat, utilities, insurance and warranties and guarantees. Unless OWNER and CONTRACTOR agree otherwise in writing and so'inform ENGINEER in writing prior to ENGINEER!- issuing the definitive certificate of Substantial Completion, ENGINEER's aforesaid recommendation will be binding on OWNER and CONTRACTOR until.final payment. 14.9. OWNER shall have the right to exclude CONTRACTOR from the Work after the date of Substantial Completion, but OWNER shall allow CONTRACTOR reasonable access to complete or correct items on the tentative list. Partial Utilization: 14.10. Use by OWNER at OWNER's option of any substantially completed pan of the Work, which: (i) has specifically been identified in the Contract Documents, or (ii)OWNER, ENGRiEER and CONTRACTOR agree constitutes a separately functioning and usable part of the Work that can be used by OWNER for its intended purpose without significant interference with CONTRACTOR's performance of the remainder of the Work, may be accomplished prior to Substantial Completion of all the Work subject to the following: 14.10-LOWNER atany time may request CONTRACTOR in writing to permit OWNER to use .my such pan of the Work which OWNE R believes to be ready for its intended use and substantially complete. If CONTRACTOR agrees that such part of the Work is substantially complete, CONTRACTOR will certifv to OWNER and ENGINEER that such part of the Work is substantially, complete and request ENG rMER to issue a certificate of Substantial Completion for that part of the Work. CONTRACTOR at any time may notify OWNER and ENGh LEER in writing that CONTRACTOR considers any such part of the Work ready for its intended use and substantially complete and request ENGR\TTM- to issue a certificate of Substantial Completion for that part of the Work. Within a reasonable time after either such request, OWNTER CONTRACTOR and ENGINEER shall make an inspection of that part of the Work to determine its status of completion. if ENGINEER does not consider that part of the Work to be substantially complete, EIi TGMEER will notify OWNTER and CONTRACTOR in writing giving the reasons therefor. if ENGINEER considers that part of the Work to be substantially complete, the provisions of paragraphs 14.8 and 14,9 will apply with respect to certification of Substantial Completion of that part of the Work and the division of responsibility in respect thereof and access thereto. 14.19.2. No occupancy or separate operation of part of the Work will be aa:omplished prior to compliance with the requirements of paragraph 5.15 in respect of property insurance. Final inspection: 14.11. Upon %inittennotice from CONTRACTOR that the entire Work or an agreed portion thereof is complete, ENGINEER will make a Faisal inspection with OWNER and CONTRACTOR and will notify CONTRACTOR in writing of all particulars in which this inspection reveals that the Work is incomplete or def c&e. CONTRACTOR shall immediately take such measures as are necessary to complete such work or remedy such deficiencies. Final: 1pplication for PapnienC 14.12. After CONTRACTOR has completed all such corrections to the satisfaction of ENGINEER and delivered in accordance with the Contract Documents all maintenance and operating instructions, schedules. guarantees, Bonds, certificates or other evidence of insurance required by paragraph 5.4. certificates of inspection, marked -up record documents (as provided in paragraph 6.19) and other documents. CONTRACTOR may make application for finial payment following the procedure for progress payments. The fmal Application for Payment shall be accompanied (except as previously delivered) by: (i) all documentation called for in the Contract Documents, including but • not limited to the eviderwe of insurance required by subparagraph 5.4.13. (6) consent of the surety, if any, to final- payment and (iii) complete and legally effective releases or waivers (satisfactory to OWNER) of all Liens arising out of or filed in connection with the Work. In lieu of such releases or waivers of Liens and as approved by OWNER CONTRACTOR may furnish receipts or releases in full and affidavit of CONTRACTOR that: (i) the releases and receipts include all labor, services, material and equipment for which a Lien could be filed, and (ii) all payrolls, material and equipment bills, and other indebtedness connected with the Work for which OWNER or OWNER's property might in any way be responsible have been paid or otherwise satisfied If any Subcontractor or Supplier fails EJCDC GENERAL CONDITIONS 19I0-5 (1990 Edition) w/ CITY OF FORT COLLIM MODIFICATIONS (REV 4l2600) to furnish such a release or receipt in full, CONTRACTOR may furnish a Bond or other collateral satisfactory to OWNER to indemnify OWNER against any Lien Releases or waivers of liens and the consent of the surety to finalize payment are to be submitted on forms conforming to the format of the Olt MIMS standard forms bound in the Project manual. Final Payment and Acceptance: 14.13. If, on the basis of ENI G rMER's observation of the Work during construction and final inspection, and ENGINEER'-, review of the final Application for Payment and accompanying documentation as required by the Contract Documents, ENGINEER is satisfied that the Work has, been completed and CONTRACTOR's other oblizations under the Contract Documents have been fulfilled, ENGINEER will, within ten days after receipt of the final Application for payment, indicate in writing ENGINEER's recommendation of payment and present the Application to ONN NER for payment. At the same time ENGINEER will also give written notice to OWNER and CONTRACTOR that the Wort: is acceptable subject to the provisions of paragraph 14.15. Otherwise, ENGINEER will return the Application to CONTRACTOR, indicating in writing the reasons for refusing to recommend final payment, in which case CONTRACTOR shall make the necessary corrections and resubmit the Application. Thirty days after presentation to OWNER of the Application and accompanying documentation, in appropriate form and substance and with ENGINEER's recommendation and notice of acceptability, the amount recommended by ENGINEER will become due and will be paid by OWNER to CONTRACTOR subicct to rzuragraeh 17.6 of these General Conditions 14A4. IC through no fault of CONTRACTOR, final completion of the Work is si&mifrcantly delayed and if ENG INFER so confirms, OWNER shall, upon receipt of CONITRACTOR's final Application for, Payment and recommendation of ENGII LEER, and without terminating the t�rcement make payment of the balance due for that portion of the Work fully completed and accepted. if the remaining balance to be held by OWNER for Work not fully completed or corrected is less than the retalnage stipulated in the Agreement, and if Bonds have been furnished as required in paragraph '5.1, the written consent of the surety to the payment of the balance due for that portion of the Work fully completed and.accepted shall be submitted by CONTRACTOR to ENO rMER with the Application for such payment. Such payment shall be made under the terns and conditions governing final payment, except that it shall not constitute a waiver of claims. Waiver of Clainis: 14.15. The making and acceptance of final payment will constitute: 14,15.1. a waiver of all claims by OWNER against CONTRACTOR. except claims arising from unsettled Liens, from defective Work appearing after "I final inspection pursuant to paragraph 14.11. from failure to comply with the.Contract Documents or the terms of any special guarantees specified therein. or from CONTRACTOR's continuing obligations under the Contract Documents-, and 14.15.2. A waiver of all claims by CONTRACTOR against OWNER other than those previously made in writing and still unsettled. ARTICLE 15--SUSPENSION OF WORK AND TERD41NAnON 01MVER May Suspend Work-: 15.1. At any time and without cause. OWNER may suspend the Work. or any portion thereof for a period of not more than ninety days by notice in writing to CONTRACTOR and ENGINEER which will fix the date on which Work will be resumed. CONTRACTOR shall resume the Work on the date so fixed CONT'RACTC)R shall be allowed an adjustment in the Contract Prix or an aNtension of the Contract Times, or both, directly attributable to any such suspension if CONTRACTOR makes an approved claim therefor as provided in Articles I 1 and 12. OWNER May Terminate: 15.2. Upon the occurrence of any one or more of the following events: 15.2.1. if CONTRACTOR persistently fails to perform the Work in accordance with the Contract Documents (including, but not limited to, failure to supply sufficient skilled workers or suitable materials or equipment or failure to adhere to the progress schedule established tinder paragnph2.9 as adjusted from time to tame pursuant to paragraph 6.6); 15.2.2. if CONTRACTOR disregards Laws or Regulations of any public body having jurisdiction; 15.2.3. if CONTRACTOR disregards the authority of ENGINEER; or 15.2.4. if CONTRACTOR otherwise violates in anv substantial way any provisions of the Contract Documents; OWNER may, after giving CONTRACTOR (and the surety, if any) seven days' written notice and to the extent permitted by Laws acid Regulations, terminate the services of CONTRACTOR, exclude CONTRACTOR from the site and, takepossession of the Work and of all CONTRACTOR's tools, appliances: construction equipment and machinery at the site and use the same to the full extent they could be used by CONTRACTOR (without liability to. CONTRACTOR for trespass or conversion).. incorporate in .the Work all materials and equipment stored at the site or for which OWNER has paid EJCDC GENERAL CONDITIONS I910S (1990 E(itim) 32 w! CITY OF FORT COLLINS MODIFICATIONS (REV 4P_000) CONTRACTOR but. which are stored elsewhere, and finish the Work as OWNER may deem expedient: In such case CONTRACTOR shall not be entitled to receive any further payment until the Work is finished If the unpaid balance of the Contract Price exceeds all claims, costs, losses and damages sustained by OWNER arising out of or resulting: from completing the Work such excess will be paid to CONTRACTOR. If such claims; costs, losses and damages exceed such unpaid balance, CONTRACTOR shall pay the difference to OWNER. Such claims, costs, losses and damages incurred by OWNER will be reviewed by ENGINEER as to their reasonableness and when so approved by ENGINEER incorporated in a Change Order, provided that when exercising any rights or remedies under this paragraph OWNER shall not be required to obtain the lowest price for the Work performed. 15.3. Where CONTRACTOR's services have been so terminated by OWNER; the temtirration will not affect any rights or remedies of OWNER against CONTRACTOR then existing or which may thereafter accrue_ Any retention or payment of moneys due CONTRACTOR by OWNER will not release CONTRACTOR from liability. 15A. Upon seven days written notice to CONTRACTOR and ENGINEER, OWNER may, without cause and without prejudice to any other right or remedy of OWNER elect to terminate the Agreement. In such case, CONTRACTOR shall be Paid (without duplication of any items): 15.4.1. for completed and acceptable Work executed in accordance with the Contract Documents -prior to the effective date of termination, including fair and reasonable sums for overhead and profit on such Work; 15.4.2. loot expenses sustained prior to the effective (late of termination in performing serviees and furnishing labor, materials or equipment as required by the Contract Documents in connection with uncompleted Work, plus fair and reasonable sums for overhead and profit on such expenses; 15.4.3. for all "claims, costs, losses and damages incurred in settlement of terminated contracts with Subcontractors, Suppliers and others: and 15.4.4. for reasonable expenses directly attributable to termination. CONTRACTOR shall not be paid on account of loss of anticipated profits or revenue or other economic -loss arising out of or resulting from such termination CONTRACTOR Alay Stop {York or Terminate: 15.5. IC through no act or fault of CONTRACTOR the Work is suspended for a period of more than ninety days by OWNER or under an order of court or other public authority, or ENGINEER fails to act on any Application for Payment within thirty days after it is submitted or OWNER Tails for thirty days to pay CONTRACTOR any sum finally determined to be due, then CONTRACTOR may, upon seven days' written notice to OWNER and ENGINEER, and provided OWNER or ENGINEER do not remedy such suspension or failure within that time, terminate the Agreement and recover from OWNER payment on the same terms as provided in paragraph 15.4. In lieu of terminating the Agreement and without prejudice to any other right or remedy, if ENGINEER has failed to act on an Application for Payment within thirty days after it is submitted, or OWNER has failed for thirty days to pay CONTRACTOR any sum finally determined to be due, CONTRACTOR may upon seven days' written notice to OWNER and ENGINEER stop the Work until payment of all such amounts clue CONTRACTOR including interest thereon. The provisions of this paragraph 15.5 are not intended to preclude CONTRACTOR from malting claim under Articles 11 and 12 for an increase in Contract price or Contract Times or otherwise for expenses or damage directly attributable to CONTRACTOR's stopping Work as permitted by this paragraph. ARTICLE 16—DISPUTE RESOLUTION If and to the eNtent that OWNER and CONTRACTOR }nave agree on the method and procedure for resolving disputes between them that may arise under this Agreement, such dispute resolution method and procedure, if any, shall be as set forth in ExhibitGC:A, "Dispute Resolution .Agreement", to be attached hereto and made a part hereof If no such agreement on the method and procedure for resolving such disputes has been reached, and subject to the provisions of paragraphs9,10, 9,11 and 9.12, OWNER and CONTRACTOR may exercise such rights or remedies as either may otherwise have under the Contract Documents or by Laws or Regulations in respect of any dispute. ,ARTICLE 17-1IISCELL,ANEOUS Giving Notice: 17.1. Whenever any provision of the Contract. Documents requires the giving of written notice, it will be deemed to have been validly given if delivered in person to the individual or to a member of the fine, or to an officer of the corporation for mvhom it is intended, or if delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice. 17.2. Con0tation of Time. 17.2.1. When any period of time is referred to in the Contract Documents by days. it will be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such day will be omitted from the computation. EJCDC GENERAL. CONDMONS 1910-5 (1990 E(fiticn) w( CITY OF FORT COLLINS MODIFICATIONS (tEy 4P--000) 17.2.1, A calendar day of twenty-four hours measured from midnight to the next midnight will constitute a day. Notice of lain 17.3. Should OWNER or CONTRACTOR suffer injury or damage to person or property because of any error, omission or act of the other party or of any of the other party's employees or agents or others for whose acts the other party is legally liable, claim will be made in writing to the other party within a reasonable time of the first observance of such injury or damage. The provisions of this paragraph 17.3 shall not be construed as a substitute for or a }waiver of the provisions of any applicable statute of limitations or repose.Cuntulative Remedies: 17.4. The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto, and. in particular but without limitation, the warranties, guarantees and obligations imposed upon CONTRACTOR by paragraphs6.12, 6.16, 6.30, 6.31, 6.32, 13.1, 13.12, 13.14, 14.3 and 15.2 and all of the rights and remedies available to OWNER and ENGINEER thereunder, are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws or Regulations by special warranty or guarantee or by other provisions of the Contract Documents, and the provisions of this paragraph will be as effective as if repeated specifically in the Contmet.Documents in connection with each particular duty, obligation, right and remedy to which they apply: Professional Fees and Court Costs Included.• 17.5. Whenever reference is made to "claims, costs, losses and damages", itshall include in each case, but not be limited to, all fees and charges of engineers, architects, attorneys and other professionals and all court or arbitration or other dispute resolution costs. 17.6. The laws of the State of Colorado po)L to this Aireement Reference to two pertinent Colorado statutes are as follows' 17.6.1. Colorado Revised Statutes (CRS 5-17-101) require that Colorado labor be employed to perform the Work to the extent of not less than SO percent (80%) of each type or class of labor in the several classifications of skilled and common labor employed on the proiect. Colorado labor means anv person who is a bona tide resident of the. State of Colorado at the time of em l vmcri without discrimination as to race, color, creed, age, religion or sex 17.62. If a claim is filed, OWNER is required by law (CRS 35-26-107) to withhold from all payments to CONTRACTOR sufficient funds to insure the Wyment of Al claims for labor, materials, tram hire, sustenance, provisions, provender, or other supplies used or consumed by CONTRACTOR or his 33 34 EJCDC GENERAL CONDI'RONS 19I OS (1990 Eatim) u'/ C17Y OF FORT COLLI h5 MODIFICATIONS (REV 42000) (f his Mc Icft blank intentionally.) EXDC GENERAL. CONDITIONS 1910 3 (19" E(Btion) 35 wt CITY OF FORT COLLUZ MODIFICATIONS (REV 4R000) 3G EJCDCGENERAL CONDMONS1910-S(t99QEcitiai) tt/ CITY OF FORT COLLINS MODIFICATIONS (REV 4l1000)