WORK SCHEDULE
PROPOSED SCHEDULE
Aller.Lingle•Massey Architects P.C.
Scope of Basic Services for the Lincoln Center Additions and Renovation will be performed in accordance
with the following milestone schedule:
■ Design team interviews:
August 18, 2009
• Design team selected:
August 19, 2009
■ Contract approved:
September 1, 2009
■ Design Development Phase complete:
October 16, 2009
■ City review complete:
October 30, 2009
• Final Design Phase complete:
December 11, 2009
• City review complete:
December 28, 2009
■ Construction Documents complete:
February 1, 2010
■ RFP advertised for Contractors:
February 1, 2010
■ City review complete:
February 12, 2010
■ Construction Documents available to Contractors:
February 22, 2010
■ Construction bids received:
March 16, 2010
■ Construction contract awarded:
April 1, 2010
■ Notice to proceed:
April 12, 2010
■ Formal construction start:
June 1, 2010
■ Construction substantially complete:
April 1, 2011
■ Building flush -out and punchlist complete:
May 1, 2011
■ Facility reopens to the public:
June 1, 2011
1 Alter- Lingle -Massey Architects P.C.