ADDENDUM No. 3
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of Bid 7127: College/Harmony Intersection Improvements
Federal Aid Project No. STU M455-077
OPENING DATE: 3:00 P.M. (Our Clock) April 21, 2010
To all prospective bidders under the specifications and contract documents described above,
the following changes are hereby made.
CHANGE:
Bid Opening Date Has Been Changed To April 21, 2010.
Revisions to the Project Special Provisions:
A. Revision to Section 420 - Geosynthetics
The project special provision for "Geotextile (Crack Reduction) (High Density)" is deleted
from the Project Special Provisions.
Clarifications to the Project Special Provisions:
A. Clarification to Section 609 — Curb and Gutter
■ Addendum #2 is revised to clarify when tie bars are required between the curb/gutter
and the concrete pavement. Tie bars will not be required if curb and gutter is placed
monolithic with the concrete paving. Tie bars will be required if there is a
construction joint between the curb/gutter and the pavement. In both cases, the pan
thickness along concrete paving will be the depth of the pavement which is 11
inches.
Please contact John D. Stephen, CPPO, LEED AP, Senior Buyer at (970) 221-6777 with any
questions regarding this addendum.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE BID/QUOTE STATING THAT THIS ADDENDUM HAS BEEN
RECEIVED.