HomeMy WebLinkAboutCORRESPONDENCE - BID - 7081 BRIDGE REPLACEMENT - WHITCOMB AND MAGNOLIA (2)WHITCOMB-MAGNOLIA
BRIDGE REPLACEMENT
PRE -BID CONFERENCE
October 8, 2009
10:00 A.M.
215 N. Mason Street
Training Room
City of Fort Collins
Engineering Dept.
Capital Projects
INTRODUCTIONS
Capital Projects Team
• Rick Richter
— Capital Projects Manager
• Tim Kemp
— Project Engineer, 416-2719
• Craig Farver
— Senior Construction Inspector, 222-0854
• Syl Mireles
— Traffic Control Supervisor, 221-6815
ATTENDANCE
• Please be sure to resister
• BID OPENING
When: October 21, 2009
3:00 P.M. Our Clock
Where: 215 North Mason
Street (2nd Floor)
1
IMPORTANT MILESTONES
• AWARD CONTRACT
— Approximately October 30, 2009
• CONSTRUCTION START DATE
Approximately November 9, 2009
• SUBTANTIAL COMPLETION
— 45 Working Days from Construction Start Date
• FINAL COMPLETION
— Maximum allotted time is 10 working days
following completion
SUMMARY OF WORK
Whitcomb -Magnolia Bridge Replacement
• This work shall consist of the Contractor constructing
a new 14x2.5 Cast in Place Concrete Box Culvert.
Also included in the work are the two tie-in sections
at both ends that transition from 14' back to the
existing Box Culvert. Work will also include but not
be limited to the placement of concrete Curb,
Sidewalk, Driveways and Ramps. Demolition work
will be done by the City of Fort Collins.
CONSTRUCTION DOCUMENTS
• Whitcomb -Magnolia Bridge Replacement
— Bid No. 7081
— Project Specifications
— Planset
• Designed by: City of Fort Collins
• Sheet Ws 1-8
7
PROJECT COORDINATION
• City of Fort Collins Storm Water Crews
— Removal of Asphalt, Box and Concrete
— Placement of Bedding Material. Contractor needs
to be present on the last day of placement to
coordinate acceptance.
• City of Fort Collins Surveying and Traffic Control
• CTL Thompson — Material Testing thru City
HIGHLIGHTS FROM GENERAL
CONDITIONS & GENERAL REG'S
SUPERINTENDENTS
— The General Contractor SHALL employ a full time
Superintendent whose sole responsibility is to monitor and
coordinate all facets of the work.
• LIQUIDATED DAMAGES
— Substantial Completion:
• 45 working days from possession of site
• Liquidated Damages of $430.00 for each calendar day will
be assessed
FINAL ACCEPTANCE
— Final acceptance must be met within 10 days after
substantial completion. Liquidated damages of $600.00 per
calendar day will be charged if this schedule has not been
HIGHLIGHTS FROM GENERAL
CONDITIONS & GENERAL REG'S
• WARRANTY
— The Contractor will be required to warranty their
work for 2 years after date of final acceptance
• CONSTRUCTION HOURS
— The operation of all machinery and vehicles must
take place between the hours of lam to 6pm
— The Contractor may request extended hours
• The request must be approved by the City of
Fort Collins 3 days prior to any work
— Weekends or Holidays
3
HIGHLIGHTS FROM GENERAL
CONDITIONS & GENERAL REG'S
• PROJECT MEETINGS
— Once a week on site, time to be determined
• PROGRESS AND SCHEDULE REVISIONS
— Schedules shall be updated weekly with a two
week 'look ahead" at proposed work and needs
• SITE CLEAN-UP
— The construction work shall be accomplished in a
neat, clean and orderly fashion
— City can have streets swept and bill to Contractor
5
HIGHLIGHTS FROM SPECS
211-01 Dewatering
I`
HIGHLIGHTS FROM SPECS
515-01 Waterproofing Coating
IT IL
� xOo
1. E
ti
L"7
11
HIGHLIGHTS FROM SPECS
602-01 Reinforcing Steel (Epoxy Coated)
604-01 Manhole Ring and Cover
608-01 & 02 Concrete Sidewalk & Driveway (6")
608-03 Concrete Ramp w/ Truncated Domes (8")
609-01 & 02 Curb, Type 2 (Section IIB)
HIGHLIGHTS FROM SPECS
626-01 Mobilization
of original contract % of item bid amount /
amount earned % of original contract amount, whichever is
less
5 25 / 2.5
10 50/5
25 60 / 6
50 100 / 10
Completion of all work on In excess of 10% of original contract
the project amount
H�
5
Thanks For Attending!
Any Questions or concerns can be addressed to:
- John Stephen
• Office: (970) 221-6777
• Email: istephen@fcQov.com
- Tim Kemp
• Office: (970) 416-2719
• Email: tkemp@fcgov.com
- Craig Farver
• Cell: (970) 222-0854
• Email: cfarver@fcoov.com