HomeMy WebLinkAboutCHANGE ORDER - RFP - P1123 GENERAL CONTRACTOR FOR FIRE STATION EXPANSION AND RENOVATION PROJECT (3)PROJECT TITLE
SECTION 00950
CHANGE ORDER NO. 4
Poudre Fire Authority Station #4
CONTRACTOR: Drahota Commercial, LLC
BID NUMBER: P1123
DESCRIPTION: Construction of an approximately 15,380 square feet Fire Station, including sitework, utilities,
landscaping, an underground irrigation system and off -site work. Exterior will be brick veneer and siding over
metal stud or CMU back-up. Interior finishes will include painted gypsum board partitions; ceramic tile, carpet,
VCT, sealed concrete, suspended acoustical ceiling, wood and hollow metal doors and frames.
1. Reason for change: Incorporation of various Proposed Change Orders (PCO's).
2. Description of change: PCO #33 — Trash Haul from Deconstruct — $1,421.02; #34 — PR#22 — Fill In
Pond at Creek — $4,587.94; #35 — Add Painted 1 x4 Trim — $2,992.35; #36 — PR#25 Basement Access Panel
- $1,085.00; #37 — Add Cord Reel in Truck Bay - $302.16; #38 — RFI#44 — Add Pressure Reducing Valve -
$559.95; #39 — Delete Sixteen Seed Junipers and Add Three Austrian Pines - $(322.24); #40 — PR#28 - Add
Cork Board for Maps — $637.66; #41 — PR# 24 — Flooring Revisions — ($3,522.63).
3. Change in Contract Cost: ($7,741.21)
4. Change in Contract Time: 0 Days
ORIGINAL CONTRACT COST ` $3,042,872.00
TOTAL APPROVED CHANGE ORDERS $24,769.22
TOTAL PENDING CHANGE ORDERS 0.00
TOTAL THIS CHANGE ORDER
$7,741.21
ADJUSTED CONTRACT COST' $3,075,382.43
(Assuming all change orders approved)
ACCEPTED BY:
REVIEWED BY:
ntractor's ReVesentative
Facilities Project Manager
APPROVED BY:\/ 1'
PFA Special Operations'Chief
cc: Contractor Purchasing
Architect Project File
/z A U
Date
1 0
Date
LZ 3
Date