HomeMy WebLinkAboutCHANGE ORDER - RFP - P959 CONSULTING ENGINEERING SERVICES W WW SW FACILITY CAPITAL IMPROVEMENTCHANGE ORDER'NO.4
PROJECT TITLE: Halligan Reservoir Enlargement
CONTRACTOR: Ayres Associates P.O. NUMBER: 8855168
DESCRIPTION:
1. The Share Vision Planning process was delayed due to work on the 404 permit
resulting in additional cost.
2. Increase the budget to cover increased costs.
3. Increase the contract amount $1,180.82.
4. No increase in contract time.
ORIGINAL CONTRACT COST $50,000.00
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER $1,180.82
ADJUSTED CONTRACT COST $51,180.82
% OF ORIGINAL CONTRACT, THIS CO 2.4%
% OF ORIGINAL CONTRACT, ALL CO`S 2.46/o
ACCEPTED DATE: 1 2 19 10Q
REVIEWED BY: SGG 426-� DATE:
Sp dial Projects Manager
APPROVED BY -1, "� > �. ; DATE:-
Watdr Resources & reatinent Mandger
APPROVED BY: - DATE:
Utilities Executive Manager
APPROVED BY: DATE:
Director Purchasing/Risk Management
Over $30,000
cc: Purchasing, Contractor, File