HomeMy WebLinkAboutRFP - 7011 ELECTRICAL ENGINEERING SERVICES FOR FORT COLLINS UTILITIESCity of
Fort Collins
�rcasing
REQUEST FOR PROPOSAL
ELECTRICAL ENGINEERING SERVICES
FOR
CITY OF FORT COLLINS
FORT COLLINS UTILITIES
PROPOSAL
7011
Purchasing Division
215 North Mason, 2"d Floor
Opening Date:
MARCH 26, 2009
3:00 P.M. (our clock)
rev 01/08
Reference evaluation (Top Ranked Firm)
The Project Manager will check references using the following criteria. The evaluation rankings
will be labeled Satisfactory/Unsatisfactory.
QUALIFICATION
STANDARD
Overall Performance
Would you hire this Professional again? Did
they show the skills required by this project?
Timetable
Was the original Scope of Work completed
within the specified time? Were interim
deadlines met in a timely manner?
Completeness
Was the Professional responsive to client
needs; did the Professional anticipate
problems? Were problems solved quickly and
effectively?
Budget
Was the original Scope of Work completed
within the project budget?
Job Knowledge
If a study, did it meet the Scope of Work?
If a Professional administered a construction
contract, was the project functional upon
completion and did it operate properly?
Were problems corrected quickly and
effectively?
stdwopsa rev 07/08
PROFESSIONAL SERVICES AGREEMENT
WORK ORDER TYPE
THIS AGREEMENT made and entered into the day and year set forth below by and
between THE CITY OF FORT COLLINS, COLORADO, a Municipal Corporation, hereinafter
referred to as the "City" and , hereinafter referred to as "Professional'.
WITNESSETH:
In consideration of the mutual covenants and obligations herein expressed, it is agreed
by and between the parties hereto as follows:
1. Scope of Services. The Professional agrees to provide services in accordance
with any project Work Orders for , issued by the City. A blank sample of a work order is
attached hereto as Exhibit "A", consisting of ( ) pages and is incorporated herein by
this reference. The City reserves the right to independently bid any project rather than issuing a
Work Order to the Professional for the same pursuant to this Agreement.
2. The Work Schedule. The services to be performed pursuant to this Agreement
shall be performed in accordance with the Work Schedule stated on each Work Order.
3. Time of Commencement and Completion of Services. The services to be
performed pursuant to this Agreement shall be initiated as specified on each Work Order. Time
is of the essence. Any extensions of any time limit must be agreed upon in writing by the
parties hereto.
4. Contract Period. [Option 1] This Agreement shall commence , 200 ,
and shall continue in full force and effect until 200 unless sooner terminated as
herein provided. In addition, at the option of the City, the Agreement may be extended for
additional one year periods not to exceed ( ) additional one year periods. Renewals
and pricing changes shall be negotiated by and, agreed to by both parties. The Denver Boulder
Greeley CPIU published by the Colorado State Planning and Budget Office will be used as a
8
stdwopsa rev 07/08
guide. Written notice of renewal shall be provided to the Professional and mailed no later than
ninety (90) days prior to contract end.
5. Early Termination by City/Notice. Notwithstanding the time periods contained
herein, the City may terminate this Agreement at any time without cause by providing written
notice of termination to the Professional. Such notice shall be delivered at least fifteen (15)
days prior to the termination date contained in said notice unless otherwise agreed in writing by
the parties. All notices provided under this agreement shall be effective when mailed, postage
prepaid and sent to the following address:
Professional: City: With Copy to:
in the event of any such early termination by the City, the Professional shall be paid for services
rendered prior to the date of termination subject only to the satisfactory performance of the
Professional's obligations under this Agreement. Such payment shall be the Professional's sole
right and remedy for such termination.
6. Design, Project Insurance and Insurance Responsibility. The Professional shall
be responsible for the professional quality, technical accuracy, timely completion and the
coordination of all services rendered by the Professional, including but not limited to designs,
plans, reports, specifications, and drawings and shall, without additional compensation,
promptly remedy and correct any errors, omissions, or other deficiencies. The Professional
shall indemnify, save and hold harmless the City its officers and employees, in accordance with
Colorado law, from all damages whatsoever claimed by third parties against the City and for the
City's costs and reasonable attorney's fees arising directly or indirectly out of the Professional's
negligent performance of any of the services furnished under this Agreement. The Professional
shall maintain commercial general liability insurance in the amount of $ combined single
limits and errors.and omissions insurance in the amount of
9
stdwopsa rev 07/08
7. Compensation. In consideration of services to be performed pursuant to this
Agreement, the City agrees to pay Professional on a time and reimbursable direct cost basis
designated in Exhibit "B", consisting of ( ) page(s), attached hereto and incorporated
herein by this reference. At the election of the City, each Work Order may contain a maximum
fee, which shall be negotiated by the parties hereto for each such Work Order. Monthly partial
payments based upon the Professional's billings and itemized statements are permissible. The
amounts of all such partial payments shall be based upon the Professional's City -verified
progress in completing the services to be performed pursuant to the Work Order and upon
approval of the Professional's direct reimbursable expenses. Final payment shall be made
following acceptance of the work by the City. Upon final payment, all designs, plans, reports,
specifications, drawings, and other services rendered by the Professional shall become the sole
property of the City.
8. City Representative. The City will designate, prior to commencement of work, its
project representative who shall make, within the scope of his or her authority, all necessary and
proper decisions with reference to the project. All requests for contract interpretations, change
orders, and other clarification or instruction shall be directed to the City Representative.
9. Project Drawings. Upon conclusion of the project and before final payment, the.
Professional shall provide the City with reproducible drawings of the project containing accurate
information on the project as constructed. Drawings shall be of archival, prepared on stable
mylar base material using a non -fading process to provide for long storage and high quality
reproduction. "CD" disc of the as -built drawings shall also be submitted to the owner in and
AutoCAD version no older then the established city standard.
10. Monthly Report. Commencing thirty (30) days after Notice to Proceed is given on
any Work Order and every thirty days thereafter, Professional is required to provide the City
Representative with a written report of the status of the work with respect to the Work Order,
10
stdwopsa rev 07/08
Work Schedule and other material information. Failure to provide any required monthly report
may, at the option of the City, suspend the processing of any partial payment request.
11. Independent Contractor. The services to be performed by Professional are those
of an independent contractor and not of an employee of the City of Fort Collins. The City shall
not be responsible for withholding any portion of Professional's compensation hereunder for the
payment of FICA, Workers' Compensation, other taxes or benefits or for any other purpose.
12. Personal Services. It is understood that the City enters into this Agreement
based on the special abilities of the Professional and that this Agreement shall be considered as
an agreement for personal services. Accordingly, the Professional .shall neither assign any
responsibilities nor delegate any duties arising under this Agreement without the prior written
consent of the City.
13. Acceptance Not Waiver. The City's approval of drawings, designs, plans,
specifications, reports, and incidental work or materials furnished hereunder shall not in any way
relieve the Professional of responsibility for the quality or technical accuracy of the work. The
City's approval or acceptance of, or payment for, any of the services shall not be construed to
operate as a waiver of any rights or benefits provided to the City under this Agreement.
14. Default. Each and every term and condition hereof shall be deemed to be a
material element of this Agreement. In the event either party should fail or refuse to perform
according to the terms of this agreement, such party may be declared in default.
15. Remedies. In the event a party has been declared in default, such defaulting
party shall be allowed a period of ten (10) days within which to cure said default. In the event
the default remains uncorrected, the party declaring default may elect to (a) terminate the
Agreement and seek damages; (b) treat the Agreement as continuing and require specific
performance; or (c) avail himself of any other remedy at law or equity. If the non -defaulting
party commences legal or equitable actions against the defaulting party, the defaulting party
11
stdwopsa rev 07/08
shall be liable to the non -defaulting party for the non -defaulting party's reasonable attorney fees
and costs incurred because of the default.
16. Binding Effect. This writing, together with the exhibits hereto, constitutes the
entire agreement between the parties and shall be binding upon said parties, their officers,
employees, agents and assigns and shall inure to the benefit of the respective survivors, heirs,
personal representatives, successors and assigns of said parties.
17. Law/Severability. The laws of the State of Colorado shall govern the
construction, interpretation, execution and enforcement of this Agreement. In the event any
provision of this Agreement shall be held invalid or unenforceable by any court of competent
jurisdiction, such holding shall not invalidate or render unenforceable any other provision of this
Agreement.
18. Prohibition Against Employing Illegal Aliens. Pursuant to Section 8-17.5-101,
C.R.S., et. seq., Professional represents and agrees that:
a. As of the date of this Agreement:
1. Professional does not knowingly employ or contract with an illegal alien
who will perform work under this Agreement; and
2. Professional will participate in either the e-Verify program created in
Public Law 208, 104th Congress, as amended, and expanded in Public Law 156,
108th Congress, as amended, administered by the United States Department of
Homeland Security (the "e-Verify Program") or the Department Program (the
"Department Program"), an employment verification program established
pursuant to Section 8-17.5-102(5)(c) C.R.S. in order to confirm the employment
eligibility of all newly hired employees to perform work under this Agreement.
b. Professional shall not knowingly employ or contract with an illegal alien to
perform work under this Agreement or knowingly enter into a contract with a
subcontractor that knowingly employs or contracts with an illegal alien to perform work
under this Agreement.
C. Professional is prohibited from using the e-Verify Program or Department
Program procedures to undertake pre -employment screening of job applicants while this
Agreement is being performed.
12
stdwopsa rev 07/08
d. If Professional obtains actual knowledge that a subcontractor performing work
under this Agreement knowingly employs or contracts with an illegal alien, Professional
shall:
1. Notify such subcontractor and the City within three days that Professional
has actual knowledge that the subcontractor is employing or contracting with an
illegal alien; and
2. Terminate the subcontract with the subcontractor if within three days of
receiving the notice required pursuant to this section the subcontractor does not
cease employing or contracting with the illegal alien; except that Professional
shall not terminate the contract with the subcontractor if during such three days
the subcontractor provides information to establish that the subcontractor has not
knowingly employed or contracted with an illegal alien.
e. Professional shall comply with any reasonable request by the Colorado
Department of Labor and Employment (the "Department") made in the course of an
investigation that the Department undertakes or is undertaking pursuant to the authority
established in Subsection 8-17.5-102 (5), C.R.S.
f. If Professional violates any provision of this Agreement pertaining to the duties
imposed by Subsection 8-17.5-102, C.R.S. the City may terminate this Agreement. If this
Agreement is so terminated, Professional shall be liable for actual and consequential
damages to the City arising out of Professional's violation of Subsection 8-17.5-102,
C.R.S.
g. The City will notify the Office of the Secretary of State if Professional violates this
provision of this Agreement and the City terminates the Agreement for such breach.
19. Special Provisions. Special provisions or conditions relating to the services to
be performed pursuant to this Agreement are set forth in Exhibit "C", consisting of
page(s), attached hereto and incorporated herein by this reference.
13
stdwopsa rev 07/08
THE CITY OF FORT COLLINS, COLORADO
By:
James B. O'Neill II, CPPO, FNIGP
Director of Purchasing & Risk Management
Date:
ATTEST:
City Clerk
APPROVED AS TO FORM:
Assistant City Attorney
[Insert Professional's name] or
[Insert Partnership Name] or
[Insert individual's name]
Doing business as [insert name of business]
in
Title:
CORPORATE PRESIDENT OR VICE PRESIDENT
Date:
ATTEST:
Corporate Secretary
14
(Corporate Seal)
stdwopsa rev 07/08
EXHIBIT "A"
WORK ORDER FORM
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
DATED:
Work Order Number:
Purchase Order Number:
Project Title:
Commencement Date:
Completion Date:
Maximum Fee: (time and reimbursable direct costs):
Project Description:
Scope of Services:
Professional agrees to perform the services
identified above and on the attached forms in
accordance with the terms and conditions
contained herein and in the Professional Services
Agreement between the parties. In the event of a
conflict between or ambiguity in the terms of the
Professional Services Agreement and this work
order (including the attached forms) the
Professional Services Agreement shall control.
The attached forms consisting of _ (_) pages
are hereby accepted and incorporated herein, by
this reference, and Notice to Proceed is hereby
given.
15
stdwopsa rev 07/08
User Acceptance
Professional
By:
Date:
City of Fort Collins
By:
James B. O'Neill II, CPPO, FNIGP
Director of Purchasing and Risk Management
(over $60,000.00)
Date:
Financial Services
City 01 Purchasing Division
215 N. Mason St. 2" Floor
Fort Collins Fo Box 5
Fort Collins,s
CO 80522
970.221.6775
Purchasing 970.221.6707
ftgov.com/Pi(rchasiiig
REQUEST FOR PROPOSAL
FOR
ELECTRICAL ENGINEERING SERVICES
FOR
FORT COLLINS UTILITIES
The City of Fort Collins is seeking proposals from experienced Consultants to perform system
analysis of the Fort Collins Utility (FCU) distribution system and to provide standards for
interconnecting distributed generators.
The City of Fort Collins is currently participating in a Grant from the Department of Energy that
will model the use of different type of distributed generation on the Utility's distribution system.
The purpose of the contract is to provide technical support and analysis on the impacts that the
installation of DG will have on the system.
The selected consultant may be retained by the City of Fort Collins Utilities annually for up to
five years to provide services for like or similar work on projects as they are required.
Written proposals, three (3) copies and the entire proposal on CD (one CD) will be received at
the City of Fort Collins' Purchasing Division, 215 North Mason St., 2nd floor, Fort Collins,
Colorado 80524. Proposals will be received before 3:00 p.m. (our clock), March 26, 2009
Proposal No. 7011. Electrical Engineering Services —City of Fort Collins, Fort Collins Utilities. If
delivered, they are to be sent to 215 North Mason Street, 2"d Floor, Fort Collins, Colorado
80524. If mailed, the address is P.O. Box 580, Fort Collins, 80522-0580.
Questions concerning the scope of the project should be directed to Project Manager Steve
Catanach, Light & Power Operations Manager, (970) 416-2622.
Questions regarding proposals submittal or process should be directed to
Opal Dick, CPPO, Senior Buyer (970) 221-6778.
A copy of the Proposal may be obtained as follows:
1. Download the Proposal/Bid from the BuySpeed Webpage,
www.fcqov.com/eprocurement
2. Come by Purchasing at 215 North Mason St., 2"d floor, Fort Collins, and request
a copy of the Bid.
The City of Fort Collins is subject to public information laws, which permit access to most
records and documents. Proprietary information in your response must be clearly identified and
will be protected to the extent legally permissible. Proposals may not be marked 'Proprietary' in
their entirety. Information considered proprietary is limited to material treated as confidential in
the normal conduct of business, trade secrets, discount information, and individual product or
service pricing. Summary price information may not be designated as proprietary as such
information may be carried forward into other public documents. All provisions of any contract
resulting from this request for proposal will be public information.
Sales Prohibited/Conflict of Interest: No officer, employee, or member of City Council, shall have
a financial interest in the sale to the City of any real or personal property, equipment, material,
supplies or services where such officer or employee exercises directly or indirectly any decision -
making authority concerning such sale or any supervisory authority over the services to be
rendered. This rule also applies to subcontracts with the City. Soliciting or accepting any gift,
gratuity favor, entertainment, kickback or any items of monetary value from any person who has
or is seeking to do business with the City of Fort Collins is prohibited.
Collusive or sham proposals: Any proposal deemed to be collusive or a sham proposal will be
rejected and reported to authorities as such. Your authorized signature of this proposal assures
that such proposal is genuine and is not a collusive or sham proposal.
The City of Fort Collins reserves the right to reject any and all proposals and to waive any
irregularities or informalities.
Sincerely,
James B. O'Neill II, CPPO, FNIGP
Director of Purchasing & Risk Management
Request For Proposal
For
Electrical Engineering Services
For
Fort Collins Utilities
1.1 REQUEST FOR PROPOSAL
Proposals are requested from experienced Consultants to perform system analysis of the
Fort Collins Utility (FCU) distribution system and to provide standards for interconnecting
distributed generators.
The City of Fort Collins is currently participating in a Grant from the Department of Energy
that will model the use of different type of distributed generation on the Utility's distribution
system. The purpose of the contract is to provide technical support and analysis on the
impacts that the installation of DG will have on the system.
1.2 SCOPE OF WORK
The scope of work for the system analysis interconnection standards shall consist of the
following components:
a) Determine the anticipated impact of distributed generation (DG) on selected
distribution feeders in the FCU system
2. Determine the acceptable level of DG penetration before adversely affecting the
existing distribution system in the following areas:
a) Desensitizing system protection settings and coordination between protective
devices, short circuit current contributions from DG's and their effect on and
fault rating of equipment and other connected DG's on the same feeder.
b) System efficiency due to voltage regulation, voltage and current imbalances,
losses, power factor, and load factor due to variable generation sources.
c) Power quality including, harmonic distortion, flicker, do injection and power
factor.
d) Unintentional islanding and the negative effects of different customers DG
with respect to each other including ferroresonance.
3. Review existing FCU interconnection standard and revise as needed to include latest
standards and incorporate limits determined in the previously performed analysis.
Including proposed equipment configurations and protection requirements.
4. Develop tool to convert existing FCU distribution model from Milsoft Windmil
database format to analysis software.
CONSULTANT QUALIFICATIONS. Proposals will be considered only from consultants
who have experienced personnel able to provide the required services. At a minimum,
stdwopsa rev 07/08
proposals submitted shall provide resumes of all personnel to be performing the work
and information substantiating previous work experience including similar projects
performed by the Consultant for utility systems that are of equal or greater complexity.
Contacts for each listed project shall be provided with the proposal.
1.3 PROPOSALS AND CONTACT INFORMATION
Information or clarification of terms concerning the scope of the proposal shall be directed to
the project engineer. The project engineer for this proposal is:
Steve Catanach, Light & Power Operations Manager
Phone: (970) 416-2622
e-mail: scatanach@fcgov.com
Information or clarification of proposal submittal or process should be directed to the Senior
Buyer.
Opal F. Dick, CPPO
Phone: (970) 221-6778
e-mail: odick@fcgov.com
Proposals shall be received before 3:00 P.M. (Our Clock) Thursday, March 26, 2009, to:
If mailed: City of Fort Collins -Purchasing
P.O. Box 580
Fort Collins, CO 80522
If delivered: City of Fort Collins -Purchasing
215 N. Mason St. 2"d Floor
Fort Collins, CO 80524
In addition to submitting a written proposal, finalists may be interviewed by the City of Fort
Collins and asked to do an'oral presentation about their company and approach to the
project. Proposals submitted should contain a detailed description of the scope.of services
the Consultant will be providing after reviewing the project scope defined herein. The
proposal should also contain itemized pricing for each component and an over all lump sum
price to perform the work.
1.4 EVALUATION CRITERIA
The submitted proposals shall be reviewed in accordance with the attached rating criteria
listed in Section 4.0.
stdwopsa rev 07/08
Section 2 -Scope of Service
2.1 DISTRIBUTED GENERATION IMPACT ANALYSIS
The Consultant shall determine the impact of proposed distributed generation (DG) on
selected distribution feeders in the FCU system. Existing and proposed generator data will
be provided to the Consultant along with the FCU distribution model in Milsoft Windmil data
format for the purpose of analyzing the impact of the added DG.
Upon completion of importing or mimicking the FCU distribution model the Consultant shall
perform an analysis of the feeders with and without the DG to determine the impact of the
DG on the system. Base cases, distribution feeders without DG, shall include the system
under peak, N-1, and lightly loaded conditions. Analysis of the cases shall include, but not
be limited to the following:
a) Voltage drop, load flow, power factor, short circuit and system loss.
b) Harmonic and power quality analysis.
c) Protection coordination study.
d) Generator start / stop, transient and dynamic stability analysis.
e) Sub -synchronous resonance and ferroresonance analysis.
Analysis performed for Items d) and e) are not applicable to the base cases. The consultant
shall explicitly state all assumptions and modeling methods as well as software used for the
studies and reference any published work used for the study.
2.2 DISTRIBUTED GENERATION PENETRATION ANALYSIS
The Consultant shall use the analysis and case studies performed in section 2.1 to
determine the acceptable level of DG penetration before adversely affecting the
existing distribution system. The amount of DG shall be incrementally increased from
the previously performed case studies to determine the following:
a) Desensitizing system protection settings and coordination between protective
devices, short circuit current contributions from DG's and their effect on and fault
rating of equipment and other connected DG's on the same feeder.
b) System efficiency due to voltage regulation, voltage and current imbalances,
losses, power factor, and load factor due to variable generation sources.
c) Power quality issues including, voltage regulation, harmonic distortion, flicker, do
injection and power factor.
d) Unintentional islanding and the negative effects of different customers with DG
and the impact they have on each other.
The Consultant will establish criteria for determining when the level of DG on the distribution
system warrants additional study and the maximum level of DG that can be supported on a
typical distribution feeder.
2.3 INTERCONNECTION STANDARD
The Consultant shall review the existing FCU interconnection standard for distributed
generating facilities and revise the document to reflect the current IEEE, NEC, UL, and other
applicable standards. The standard shall also conform to any state or federal requirements.
The Consultant shall also incorporate specific guides, rules, requirements or restrictions as
determined from the distributed generation penetration analysis. The Consultant will submit
stdwopsa rev 07/08
the standard for review by FCU staff for comment and revision. Upon final acceptance by
FCU, the Consultant will provide the completed interconnection standard for distributed
generating facilities in paper and electronic format.
2.4 DATABASE CONVERSION TOOL
The Consultant shall work with FCU to develop a software tool to convert existing FCU
distribution model from Milsoft Windmil database format to analysis software selected by
FCU to perform future analysis. The Consultant shall advise and assist FCU on the selection
of the analysis software to be used. The software tool will be reviewed and tested by FCU to
confirm conformance and functionality before acceptance of the tool. The Consultant shall
provide assistance and training on using the conversion tool and the selected analysis
software.
2.5 ADDITIONAL WORK
At the option of the City of Fort Collins, The Consultant will be retained as a primary service
provider for performing on -going evaluations and analysis of various distributed generation
and interconnection studies for like or similar work as needed by FCU. The initial contract
period is for one year, with an option to renewal for four (4) additional one year terms.
4
stdwopsa rev 07/08
Section 3 - Proposal Response Requirements
3.1 PROPOSALS
For this section, consultants are required to provide detailed written responses to the
following items. The responses shall be considered technical offers of what consultants
propose to provide and shall be incorporated in the contract award as deemed appropriate
by FCU. Using company letterhead, please attach your responses to these questions to the
enclosed Proposal Response Cover Sheet.
1. A cover letter stating the name, address and telephone number of the proposing
consultant. This letter must bear the signature of the person having the authority to
make the proposal for the firm.
2. A list of staff to be assigned to the project (in particular a project manager to act as first
point of contact) including resumes and work experience related to this project.
3. Description regarding how the analysis will be performed for the various identified areas
identified, the methods and assumptions used, and the limitations of the analysis.
4. Description of the software and other analysis tools to be used.
5. Detailed information of how the database conversion tool will be developed and
implemented. Database and software requirements and limitations or challenges
anticipated.
6. Price of proposed services, with narrative to include itemized information concerning the
cost of each component including labor, materials, software, travel, overhead and other
cost elements which are expected to be incurred.
7. Identification of what portion of work, if any, will be subcontracted including a list of Sub
consultants.
8. Proposed schedule, which includes a detailed timeline for task accomplishment,
projected start date, and ability to meet the Departments completion.
9. A list of at least three references, preferably entities requiring similar scope of work and
analysis. This list should include a summary of services provided, as well as a specific
contact person at each organization.
10. Any other information deemed necessary by the proposing contractor.
3.2 PROJECT SCHEDULE
Consultants shall submit completed proposals by the date specified in section 1_4
PROPOSALS AND CONTACT INFORMATION. All proposals submitted shall include the
entire proposal on CD as well as three (3) paper copies with the appropriate signatures.
stdwopsa rev 07/08
SECTION 4 - REVIEW AND ASSESSMENT
Professional firms will be evaluated on the following criteria. These criteria will be the basis for
review of the written proposals and interview session. The rating scale shall be from 1 to 5, with
1 being a poor rating, 3 being an average rating, and 5 being an outstanding rating.
WEIGHTING
QUALIFICATION
STANDARD
FACTOR
2.0
Scope of Proposal
Does the proposal show an understanding of the
project objective, methodology to be used and
results that are desired from the project?
2.5
Assigned Personnel
Do the persons who will be working on the project
have the necessary skills? Are sufficient people of
the requisite skills assigned to the project?
1.0
Availability
Can the work be completed in the necessary time?
Can the target start and completion dates be met?
Are other qualified personnel available to assist in
meeting the project schedule if required? Is the
project team available to attend meetings as
required by the Scope of Work?
1.0
Motivation
Is the firm interested and are they capable of doing
the work in the required time frame?
2.0
Cost and
Do the proposed cost and work hours compare
Work Hours
favorably with the Project Manager's estimate? Are
the work hours presented reasonable for the effort
required in each project task or phase?
2.0
Firm Capability
Does the firm have the support capabilities the
assigned personnel require? Has the firm done
previous projects of this type and scope?
stdwopsa rev 07/08