HomeMy WebLinkAboutCHANGE ORDER - BID - 6045 ASPHALT SUPPLY (2)Change Order Form
Engineering Department
PROJECT TITLE: Drake/Ziegler Improvements Project - Phase III
PROJECT NUMBER: 30523280.6 (Bid #6099)
CONTRACTOR: Lafarge Northern Inc. (PO #8853160)
CHANGE ORDER NUMBER: 4
n preparing change orders show in order as separate numbered paragraphs the following:
1. Reason for change. 2. Description of change.
3. Change in contract cost. 4. Change in contract time.
1.&2. See attached invoice for details
3. The contract cost will increase by $86,583.28
4. There is no change in contract time.
ORIGINAL CONTRACT COST
$2,025,011A4
TOTAL APPROVED CHANGE ORDERS
$68,936.15
TOTAL PENDING CHANGE ORDERS
$0.00
TOTAL THIS CHANGE ORDER
$86,583.28
TOTAL % OF THIS CHANGE ORDER
4.28%
TOTAL C.O. % OF ORIGINAL CONTRACT
7.68%
ADJUSTED CONTRACT COST
$2,180,530.87
�t ���
ACCEPTED BY:
DATE:
/(Co�trector's Repr entative)
!
REVIEWED BY:
DATE:
SUBMITTED BY: 1z DATE: 7
Mct ngineering)
APPROVED BY: DATE: a
(Department Head) \ APPROVED BY: �Ki%/LIY Cir/�DNG I DATE: hod / ✓yZI
(Purchasing Agent over $60,000) %OR..
cc: Accounting
Purchasing
Contractor
Project Fife
Engineering Department • 281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (970) 221-6605
CHANGE ORDER 4
Drake - Ziegler Phase 3 Improvement Project
SUMMARY OF WORK "
Lafarge - North America
Install Sidewalk along Hewlett Packard and Avago Properties
Item Quantity Unit $/Unit Total
1
Sidewalk 6" Thick 8' Wide
SF
20,000
$3.52
$70,400.00
2
Winter Protection as required)
SF
20,000
$0.24
$4,800.00
3
Handicap Rams in 8' walk w/ Domes 8'x6'
EA
2
$2,134.17
$4,268.34
4
Ped Refuge Islands in 8' walk w/ Domes 160 SF
EA
1
$3,456.94
$3,456.94
5
30" Infall Curb and Gutter Remove and Replace
LF
40
$46.84
$1,873.60
6
18" Outfall Curb and Gutter Remove and Replace
LF
40
$44.61
$1,784.40
TOTAL
86,683.28
REASON FOR CHANGE
1,2,3,4,5,E Additonal Quantity needed for installation of sidewalk along HP/Avago '..
WHEN POSTED
Posted to Pay App #5