HomeMy WebLinkAboutCHANGE ORDER - BID - 6049 ASPHALT OVERLAY PROJECTChange Order Form Engineering Department PROJECT TITLE: 2008 Street Maintenance Program, Asphalt Overlay PROJECT NUMBER: 320200 (Bid No. 6049) CONTRACTOR: Lafarge Northern Inc. (PO #8851919) CHANGE ORDER NUMBER: 4 n preparing change orders show In order as separate numbered paragraphs the o owing: 1. Reason for change. 2. Description of change. 3. Change in contract cost. 4. Change in contract time. 1.&2. See attached invoice for details 3. The contract cost will increase by $312,067.59 4. There is no change in contract time. ORIGINAL CONTRACT COST TOTAL APPROVED CHANGE ORDERS TOTAL PENDING CHANGE ORDERS TOTAL THIS CHANGE ORDER TOTAL % OF THIS CHANGE ORDER TOTAL C.O. % OF ORIGINAL CONTRACT ADJUSTED CONTRACT COST ACCEPTED BY: REVIEWED BY: SUBMITTED BY: APPROVED BY: APPROVED BY: �( ,,,(Purchasing Agent over $60,000) cc: Accounting Purchasing Contractor Project File 14.98 % 16.10% $2,083,654.65 $17,225.56 $6,094.43 $312,067.59 $2,419,042.23 TE: •" � _ GrJ TE: "� 09 TE: 'W ' TE: c2 12,`09 Engineering Department • 281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0530 • (970) 221-6605 2008 Overlay Contract Renewal Bid No. 6049 Change Order No: 4 Date: 7/18/2008 1. Reason For Change: This work is typically performed by Streets crews, however due to delays elsewhere on the project, this work needs to be a. transferred to this contract in order to keep the overall maintenance project on schedule. 2. Description Of Change: a. Add all Grinds, Taper milling & placement of SG Asphalt mix in the Brittany Knolls Nieghborhood 3. Change In Contract Amount Item Qty Unit Unit Cost Total Cost a. 202.01 Grinding (planing) Surface Preparation <3" 7,050.66 BY $ 2.60 $ 18,331.72 b. 202.02 Grinding (planing) Surface Preparation 3 to 5" 7,972.02 BY $ 7.25 $ 57,797.15 C. 202.05 Taper Planing Adjacent to Gutter 8,274.00 LF $ 6.09 $ 50,388.66 d. 203.02 Excavation - General Over 100 CY 1,267.01 CY $ 16.85 $ 21,349.12 e. 403.06 HMA - Grading SG 3,644.86 TON $ 45.05 $ 164,200.94 TOTAL CHANGE IN CONTRACT AMOUNT $ 312,067.59 4. Change In Contract Time a. No days will be added to the contract. TOTAL CHANGE IN CONTRACT TIME 0 Days H:\p.m.p\PROJECTS\2008\Asphalt\Pay Estimates\2008 CONTRACTORS MONTHLY PAY ESTIMATE.XLS Page 1 Change Order Form CityDEFark Collins Engineering Department PROJECT TITLE: 2008 Street Maintenance Program, Asphalt Overlay PROJECT NUMBER: 320200 (Bid No. 6049) CONTRACTOR: Lafarge Northern Inc. (PO #8851919) CHANGE ORDER NUMBER: n preparing change or ers s ow in order as separate num ere paragraphs e ollowmg: 1. Reason for change. 2. Description of change. 3. Change in contract cost. 4. Change in contract time. 1.&2. See attached invoice for details 3. The contract cost will increase by $2.820.66 4. There is no change in contract time. ORIGINAL CONTRACT COST $2,083,654.66 TOTAL APPROVED CHANGE ORDERS $17.225.56 TOTAL PENDING CHANGE ORDERS $318,162.02 TOTAL THIS CHANGE ORDER $2,820,66 TOTAL %OF THIS CHANGE ORDER 0.14% TOTAL C.O. % OF ORIGINAL CONTRACT 16.23% ADJUSTED CONTRACT COST $2,421,862.89 ACCEPTED BY: REVIEWED BY: SUBMITTED BY: APPROVED BY: APPROVED BY: cc: Accounting Purchasing Contractor Project File FE: v_ e`gp TE: E: l,,I�JWu DATE: eparlment Head), DATE: (Purchasing Agent over $60,000) Engineering Department • 281 NortL College Avenue • P.O. Rox 580 •Fort Collins, CO 30522-0580 • (970) 221-6605 2008 Overlay Contract Renewal Bid No. 6049 Change Order No: 5 Date: 7/25/2008 1. Reason For Change: a. Manholes are out of tolerance due to asphalt which appears to have shoved under high volume of traffic 2. Description Of Change: a. Adjust 8 Manholes on E. Prospect between College & Timberline Rd. Mill off lop 2" and patch back. 3. Change In Contract Amount: Item Unit Hrs. Charged Unit Cost Total Cost a. Tandems HRS. 8.00 $ 72.00 $ 576.00 I). Service Truck HRS. 1.50 $ 57.00 $ 85.50 c. Landscape Tractor HRS. 3.00 $ 90.00 $ 270.00 d. Transport/Small Crew HRS. 2.00 $ 92.00 $ 184.00 e. Mill HRS. 3.00 $ 180.00 $ 540.00 I. Foreman/Pickup HRS. 1.00 $ 62.00 $ 62.00 g Laborers HRS. 23.00 $ 34.00 $ 782.00 h. 403.07 Asphalt Patch Ton 5.18 $ 62.00 $ 321.16 TOTAL CHANGE IN CONTRACT AMOUNT $ 2,820.06 4. Change In Contract Time a. No days will be added to the contract. TOTAL CHANGE IN CONTRACT TIME 0 Days H:\p.m.p\PROJECFS\2008\Asphalt\Pay Estimates\2008 CONTRACTORS MONTHLY PAY ESTIMATE.XLS Page 1