HomeMy WebLinkAboutCORRESPONDENCE - RFP - P939 BUILDING COMMISSIONING ANNUAL CSU PHASE II COMMISSIONING (2)Administrative Services
Purchasing Division
June 6 2008
JUN 1 ° 2008
RECEIVED
Architectural Energy Corporation
Attn Michael J Holtz FAIA
2540 Frontier Ave Ste 201
Boulder CO 80301
RE Renewal P939 Building Commissioning
Dear Mr Holtz
The City of Fort Collins wishes to extend the agreement term for the above captioned proposal
per the existing terms and conditions and the following rate increase
Principal $177/hr
Senior Engineer $126/hr
Project Manager/Engineer $100/hr
Staff Engineer $ 88/hr
Associates Engineer $ 72/hr
Prohibition Against Employing Illegal Aliens This paragraph shall apply to all Contractors
whose performance of work under this Agreement does not involve the delivery of a specific end
product other than reports that are merely incidental to the performance of said work Pursuant
to Section 8-17 5-101 C R S et seq Contractor represents and agrees that
A As of the date of this Agreement
1 Contractor does not knowingly employ or contract with an illegal alien and
2 Contractor has participated or attempted to participate in the basic pilot employment
verification program created in Public Law 208 104th Congress as amended and
expanded in Public Law 156 108th Congress as amended administered by the
United States Department of Homeland Security (the Basic Pilot Program ) in order
to verify that Contractor does not employ any illegal aliens
B Contractor shall not knowingly employ or contract with an illegal alien to perform works
under this Agreement or enter into a contract with a subcontractor that fails to certify to
Contractor that the subcontractor shall not knowingly employ or contract with an illegal
alien to perform work under this Agreement
C Contractor shall continue to apply to participate in the Basic Pilot Program and shall in
writing verify same every three (3) calendar months thereafter until Contractor is
accepted or the public contract for services has been completed whichever is earlier
The requirements of this section shall not be required or effective if the Basic Pilot
Program is discontinued
D Contractor is prohibited from using Basic Pilot Program procedures to undertake pre-
employment screening of job applicants while this Agreement is being performed
215 North Mason Street 2nd Floor PO Box 580 Fort Colhns CO 80522 0580 (970) 221 6775 FAX (970) 221 6707
E If Contractor obtains actual knowledge that a subcontractor performing work under this
Agreement knowingly employs or contracts with an illegal alien Contractor shall
Notify such subcontractor and the City within three days that Contractor has actual
knowledge that the subcontractor is employing or contracting with an illegal alien and
Terminate the subcontract with the subcontractor if within three days of receiving the
notice required pursuant to this section the subcontractor does not cease employing
or contracting with the illegal alien except that Contractor shall not terminate the
contract with the subcontractor if during such three days the subcontractor provides
information to establish that the subcontractor has not knowingly employed or
contracted with an illegal alien
F Contractor shall comply with any reasonable request by the Colorado Department of
Labor and Employment (the Department ) made in the course of an investigation that the
Department undertakes or is undertaking pursuant to the authority established in
Subsection 8-17 5-102 (5) C R S
G If Contractor violates any provision of this Agreement pertaining to the duties imposed by
Subsection 8-17 5-102 C R S the City may terminate this Agreement If this Agreement
is so terminated Contractor shall be liable for actual and consequential damages to the
City arising out of Contractors violation of Subsection 8-17 5-102 C R S
H The City will notify the Office of the Secretary of State if Contractor violates this provision
of this Agreement and the City terminates the Agreement for such breach
The term will be extended for one (1) additional year July 31 2008 through August 1 2009
If the renewal is acceptable to your firm please sign this letter in the space provided and return
it to the City of Fort Collins Purchasing Division P O Box 580 Fort Collins CO 85022 within
the next fifteen days
If this extension is not agreeable with your firm we ask that you send us a written notice stating
that you do not wish to renew the contract and state the reason for non -renewal
Please contact John D Stephen CPPO CPPB Senior Buyer at (970) 221-6777 if you have
any questions regarding this matter
erely
J m B 0 Neill II CPPO FNIGP
cstor of Purchasing and Risk Management
.14-c G, 20?i
Signature Date
(Please indicate your desire to renew P939 by signing this letter and returning it to Purchasing
Division within the next fifteen days )
JBO mar
ARCHITECTURAL ENERGY
C 0 R P 0 R A T 1 0 N
Integrated Engineered Solutions
June 10 2008
Mr James B O'Neill Il, CPPO, FNIGP
Director of Purchasing and Risk Management
City of Fort Collins
Administrative Services — Purchasing Division
215 North Mason Street, 2nd Floor
P O Box 580
Fort Collins, Colorado 80522-0580
Dear James,
I enclose a signed and dated Renewal Amendment for Architectural Energy
Corporation's Building Commissioning Agreement with the City
I appreciate John Stephen's and your help to get things all "ship shape" with this
Agreement
All the best, and again thanks for your and John's assistance,
Michael J Holtz, FAIA, NCARB, LEED AP
President
MJH/aab
enclosure
Corporate Offices
2540 Frontier Avenue Suite 201
Boulder Colorado 80301 USA
Tel (3031444 4149 Fax (303) 444 4304
Email AECmfoGarchenergymm
Architectural Energy Corporation
Loaded Hourly Labor Rates
For Colorado Operations
2007 2008
Calendar Calendar
Year Year
Prince al
$173
$177
Senior En sneer
$123
$126
Pro act Mana er / En sneer
$98
$100
Staff En sneer
$86
$88
Assoaate En sneer
$70
$72
ARCHITECTURAL ENERGY
C 0 K r 0 A A T 1 0 N
Inr grated Enginae ed Siluur
June 6 2008
Mr John Stephens Buyer
Purchasing Division
City of Fort Collins
215 North Mesa Street 2nd Floor
P O Box 580
Fort Collins Colorado 80522
lstephen6&fcgov com
Dear John
Thanks for sending me the base contract and other information regarding our commissioning
work with the City I have continued to investigate the situation on our end
The attached table lists what we think are the 2007 building rates - those used to invoice work
to the City under the Commissioning Services Contract and our proposed rates for 2008 a
2 5% increase over the 2007 rates
The 2008 rates are what we are proposing to use for any new work authorized by the City
Please call with an questions and hopefully we can wrap up the 2008 contract amendment
extension
John thanks for all of your help
All the best
e
MANI
Michael J Hol FAIA NCARB LEED AP
President
MJH/aab
enclosure
Corporate offices
2540 Frontier Avenue Suite 201
Boulder Colorado 80301
(303)444.4149
N archenergy com