HomeMy WebLinkAboutCHANGE ORDER - BID - 6062 (2)City of Fort Collins ,a Engineering Department Change Order Form PROJECT TITLE: Lemay Avenue at Mulberry Street Right Turn Lane PROJECT NUMBER: 30525037.6 (Bid No. 6062 ) CONTRACTOR: Naranjo Civil Contracto/a'(PO No. 7707265) CHANGE ORDER NUMBER: 4 --2----f-- n preparing change orders show in order as separate numberea paragrapns the tonowing 1. Reason for change. 2. Description of change. 3. Change in contract cost. 4. Change in contract time. 1.&2. See attached invoice for details The contract cost will decrease by ($3,055.48) 4. There will be no change in contract time. ORIGINAL CONTRACT COST $157,743.00 TOTAL APPROVED CHANGE ORDERS $2,114.12 TOTAL PENDING CHANGE ORDERS $0.00 TOTAL THIS CHANGE ORDER ($3,055.48) TOTAL % OF THIS CHANGE ORDER -1,94% TOTAL C.O. % OF ORIGINAL CONTRACT -0.60% ADJUSTED CONTRACT COST $156,80064 ACCEPTED BY: REVIEWED BY: (Engineer) 7r/s -o r v` SUBMITTED BY: /' 1 ' DATE: (Proje/ctt Manager) APPROVED BY: �,1G(,l� DATE: (Department Head) APPROVED BY: DATE: (Purchasing Agent over $30,000) cc: Contractor Purchasing Project File Engineering Depintment • 281 North College Avenue • P.O. Box 580 , Fort Collins, CO 80522-0580 • (970) 221-6605 ® 281 e North Department 281 Noah Collage Avenue • P.O. Box 580 •Fort Collins, CO 80522-0580 c:nerroncwu..• Tel: (970) 221-6605 • Fax (970) 221-6378 Change Order Project Lemay Avenue at Mulberry Street Right Tom Lane Contract / Bid 16062 Contractor Naranjo Civil Constructors CHANGE ORDSR NO.: Final Reconciling Change Order DESCRIPTION: 1. Reason for Change: A. Reco icle Seal contract, items. Delete quantities not used. of Chance Original Contract This Change Order Revised Contrast Amount Item Rem Description Unit Quantity Unit Price Total Quantity Um Price Total Quantity Unit Price Total 202-00035 Removal of Concrete Pipe LF 99 $16.50 S 1.633.50 32 $16.501 529.00 131.00 $16.60 S 2,161.50 202-00200 Removal of Sidewalk BY 135 $11.20 $ 1,512.00 10 $11.201 $ 112.00 145.00 $11.20 S 1,624.00 202-00210 Removal of Concrete Pavement SY 164 $25.70 S 4,214.80 4 $25,70 $ 102.80 168.00 $25.70 $ 4,317.60 203-01500 Blading HR 8 $150.00 $ 1,200.00 4 $150.00 $ 600.00 12.00 $150.00 $ 1,800.00 20840050 Storm Drain Inlet Protection EACH 5 $300.00 $ 1 500.Oo -2 $300.00 5 (600.00) 3.00 S300.00 $ 900.00 208-00070 Stabilized Construction Entrance EACH 1 $1,614.00 $ 1,514.00 -1 $1514.00 $ (1,514.00) 0.00 $1,514.00 $ 208-0090 Erosion Gontrol LS 0 $0.00 $ 1 $4419.07 $ 4,419.07 1.00 S4,419.07 $ 4,419.07 304-06000 Aggregate Base Course (Class 6) TON 254 $32.50 S 8,255.00 163.69 S32.50 S 5,319.93 417.69 $32.50 S 13,574.93 403-32821 Hot Mix Asphalt (Grading SG) (100) (PG 58-28) TON 38 $96.00 $ 3,648.00 -2,22 $96.00 5 '213.12) 35.78 $96.00 $ 3,434.88 403-33851 Hot Mix Asphalt (Grading S) (100) (PG 64-28) TON 38 $96.00 5 3,648.00 1459 $96.00 S 1,400.64 52.69 $96.00 $ 5,048.64 412-01020 Concrete Pavement (10 Inch) Fast Track BY 261 $101.00 $26,361.00 -252 $101.00 S (25,462.00) 9.00 $101.00 S 909.00 412-01002 Concrete Pavement (10 Inch) Class P BY 0 $0.00 $ 256 $93.22 $ 23,864.32 266.00 $93.22 $ 23,864.32 603-01150 151nch Reinforced Concrete Pipe LF 55 $54.20 $ 2,931.00 53 554.201 5 2,872.60 108.00 $54.20 $ 6.853.60 608-00006 Concrete Sidewalk IS loon) BY 94 $54.50 $ 5,151.20 10 554.80 $ li48.00 104.00 $54.80 $ 5,699.20 609-24002 Gutter Type It (2 Foot) LF 176 $23.30 S 4,100.80 -12 $23.30, $ M79.60) 164.00 $23.30 $ 3.821.20 700-70010 F/A Minor Contract Revisions FA 1 $10,000.00 $10,000.00 (1.00) $10,000.001 $ (10.000.00) 0.00 $10.000.00 S 700-70016 F/A Fuel Cost Adjustment FA 1 $1.500.00 $ 1500.00 (1.Oo) $1,500.00 S (1,500.00) 0,00 $1,500.00 $ - 700-70021 F/A On -The -Job Trainee HOUR 0 $0.00 $ 0.00 $0.00 $ 0.00 $0.00 5 700-70022 F/A OJT Colorado Training Program FA 1 St5C.00 $ 150.oC (too) $150.00 S (150.00) 0.00 9150.00 S 700-70380 F/A Erosion Control I FA 1 $1,000.GG $ 1,000.00 (1.00) $1,000.00 S (t.000.00) G.00 $7,000.00 S Total from Original Contract g78,369.30 Total Increase/Decrease $ (94137) Total After Change Order $ 77,427.94 3. Criginal Contract Cost $157,743.00 Total Approved Change Orders S 2,114.11 Total This Change Order S (141.37)7- v{�3055•r{'g�/ Total Overpayment from Error on Pay Application No.2 S 12.114.11) , Revised Contract Amount after Final Change Order $156,801.6 4. Change in Contract Time: None