WORK ORDER FORM
PURSUANT TO AN AGREEMENT BETWEEN
p
TI3E CITY OF FORT COLLINS
J
and
Connell Resources
DATED: April 15, 2008
Work Order Number. 9-740700-08
Project Title:
Harmony/Ziegler Front Range Village Project
Commencement Date: April15,2008
Completion Date:
May 15, 2008
Maximum Fee:
(time and reimbursable direct costs): not to exceed 90,000.00
Project Description:
Dirt haul off Front Range Village.
Scope of Services:
Haul excess material/dirt fromFront Range Village to the Flatiron
pit off Strauss Cabin and
Horsetooth. Per Quote dated 4/9/08, bid #2071031.
Service Provider agrees to perform the services
identified above and on the attached forms in
accordance with the terms and conditions contained
herein and in the Services Agreement between the
parties. In the event of a conflict between or
ambiguity in the terms of the Services Agreement
and this work order (including tine attached forms),
the Services Agreement shall control.
Service Pro ' r
By,
D e: April 15, 2008
Approved By:
Purchasing Agent over $30,000
The attached forms consisting of three (3) pages are
hereby accepted and incorporated herein by this
reference, and Notice to Proceed is hereby given.
City of Fort Collins
Date: ApH115, 2(Y08
Connell Resources, Inc.
7785 Highland Meadows Pkwy, #100
Fort Collins, CO 80528 ■
Phone: (970) 223-3151
Fax: (970) 223-3191
Estimator: Jennifer Acton QUOTATION Date: 4/9/2008
Submitted To: City Of Fort Collins - Engineering Bid Title Dirt Haul Off Front Range Village April 08
Address: 281 North College Avenue Bid Number: 2071031
Fort Collins, CO 80522 Project Location:
Contact: Craig Farver Project City, State: ,
Phone: 970-221-6605 Fax: 970-221-6378 Engineer/Architect:
We offer for your consideration the following Quotation which, if accepted, shall constitute a contract between us.
Item Description Unit Unit Price
D. Earthwork
Export Excess Material CY $3.50
Knock Down W/ Blade HR $161.00
Notes:. Pricing Is based upon request per City of Fort Collins to have Connell load and haul excess material from Front Range Village to the Flatiron
pit off Strauss Cabin and Horsetooth, Connell will have a blade knock down the material. Approx. 3000 CY.
.The following are excluded fi om this proposal: Construction layout and engineering; Drainage facility certification; Performance and
Payment bonds; Warrantee period in excess of one year; Street cleaning for work performed by others; Permits: including but not limited to,
city building, development construction, construction dewatering, wastewater discharge, storm water discharge (NPDES), air quality, etc.;
Fees, including but not limited to, for developement, inspection, utility connection, meters, etc,; Dewatering; Maintenance of erosion control
devices for others; quality control or acceptance testing; prairie dog removal, relocation, or extermination; landscaping, seeding, or
revegetation.
. Pavement Drainage less than 1.5% designed or obtainable fall will not be guaranteed.
. All work is contingent on the availability of construction water, access to the work, negotiation of acceptable contract terms, a mutually
agreeable schedule, and verifcation of financing.
. Please provide a minimum of 2 weeks advanced notification of work requests to allow for scheduling the work. No work will be completed
without a signed Contract Agreement. Work is anticipated April l0th-18th. Dependent on weather.
Dirt Haul Off Front Range Village April 08 Page 1 of 2