HomeMy WebLinkAboutCORRESPONDENCE - RFP - P872 PROJECT REQUIREMENTS`PROJECT REQUIREMENTS
A formal Partnering Session will be held with the selected contractor PFA team members and
Vaught -Frye Architects as soon as the selection process is completed
During the design phase(s) the contractor will be part of the design team with PFA and Vaught -
Frye Architects participating in the final design effort by assisting in the following areas
Review of designs for constructabdity
Estimating costs of different alternatives and components
Providing opinions and recommendations on suitable methods and approaches
to accomplishing the work
Provide input on construction sequences and schedules
Offer value engineering suggestions to accomplish the desired objectives in the
most cost-effective manner possible
° Provide on -going cost status of the project to the design team as the project
proceeds
The contractor is required to commit key staff members to assist the project team by attending
regularly scheduled project meetings and preparing information or responses to issues in
advance of meetings Normally attendance will be required by the contractors project manager
and superintendent In the event key technical functions are subcontracted the subcontractor
shall assist the general contractor firm in fulfilling its responsibilities under the agreement during
the design phase(s) including participation in design discussions
The PFA staff works very closely with the Architect/Engineer (Vaught Frye Architects) and the
contractor on a day to day basis as part of a team during design and construction of protects
Traditional adversarial roles are not an acceptable way of doing business You are encouraged
to call or visit to discuss further or to ask any questions that you have about the process
The Poudre Fire Authority utilizes the services of a general contractor on an as needed basis
The type and complexity of the work vanes dependent upon the specific needs of the PFA at
any given time Several protects including a 25 000 gallon Pump Test Pit a major addition to
the administrative offices additional fire stations and significant remodels and additions to
existing fire stations and the replacement of the burn budding are all possible during the terms of
any agreement
Currently none of these projects has approval so in an effort to clarify the potential scope
several recent projects are listed below for reference and to help define the scope of services
3
desired
• Prototype Fire Stations (Stations 12 & 14) — —10 500 sq foot fire stations with living
quarters apparatus bays community rooms offices and support areas typically located
on 1 to 1 5 acre sites 2 of these facilities completed in last 6 years
• Training Center Facilities -- —13 000 sq ft classroom facility with offices for training staff
added to the 27 acre training site
• Breathing Apparatus Service Center — Significant remodel of existing space to
accommodate a state of the art service and repair facility for self contained breathing
apparatus
• Remodel Fire Station 7 — Complete remodel of an existing facility Included replacement
of all interior finish new HVAC duct work all new electrical service addition of a fire
sprinkler system and a new roof structure
• Live Fire Training budding — Significant repairs to this structure to extend its useful life
• Flag Poles — The installation of Flag Poles at several facilities
• Computer Room Remodel — A remodel of space at the administrative offices to
accommodate a computer room and small conference area
This list of projects is not exhaustive of the protects completed under the current agreement and
is no guarantee of similar projects in the future Most of these projects were completed using a
team approach with the Authorities design firm however some projects were strictly design
build by the contractor and others a combination of design build and design team approaches
PROPOSAL GUIDELINES
Qualified general contractors interested in the work described in this request should submit a
minimum of the following information to the City
Describe your approach to this protect
1 General information
Name of firm contact person for this proposal title phone number fax number
street and mailing addresses any previous names of firm in last 10 years and
date established
2 Key protect staffing
Names and resumes of key project staff including proposed project manager
construction superintendent and protect cost estimator Indicate pertinent work
experience and any post high school construction management or engineering
education Include references from owners and consulting engineers for the last
2
3 protects for each assigned person and similar references for work on recent
similar building protects for each (if not among last three protects) Detail the
availability of staff assigned
3 General company resources
Indicate the resources available for cost estimating construction approach and
methods construction sequencing and scheduling Provide descriptions,
resumes organization charts and/or other indications of the degree expertise and
qualifications available to this protect Indicate location if not based in the office
location in item 1 above
Protect experience
Provide brief summary of similar construction protect work performed by the firm
in the last 5 years Highlight any participation by key staff proposed for this
protect Provide data on
° Bid cost
° Cost at completion and number of change orders
Contractor subcontractor or owner initiated claims and
their resolution
Contract time for completion when bid
Actual completion time
Brief discussion of any unusual factor is encouraged (e g owner initiated delays
additions to the work etc ) Provide both an owner reference and consulting
engineer reference for cited protects
5 Partnering experience
Describe any experience by the firm or key staff with similar
owner/engineer/contractor teams Describe the firm s experience in Partnering
both formal and informal Highlight any Partnering experience by key staff
proposed for this protect Provide references for cited experience
6 Safety record
Provide the firm s OSHA reportable accident rate and current workman s
compensation insurance multiplier for the last 3 years Provide the OSHA
reportable accident rate on protects managed by the proposed superintendent or
protect manager over the three year period (depending on who is assigned site
safety responsibility in the contractor organization)
5
7 Subcontractors
Based on the description of the work in this request describe which portions of
the work will be performed by subcontractors
8 Design phase cost
Provide hourly rates to be applied to the proposed key staff (and subcontractors
if necessary) for assistance to the owner/engineer design team during the design
phase Anticipated hours and schedule are outlined in the Project Requirements
above Identify how expenses related to providing this assistance will be
charged
9 Construction cost factors
Establish in detail the factors which will be used in determining the negotiated
maximum construction price These factors shall be comprehensive in
establishing all costs to be applied to direct protect labor and materials in
determining the construction cost Commitments shall include
Overhead and profit (combined) margin for general office activities on the
base bid cost
Overhead and profit (combined) margin for field office activities on the
base bid cost
° Subcontractor markup on base bid cost to General Contractor
Materials and equipment markup on base bid cost
° Any additional factors applied to protect labor or materials to determine
the base bid cost
Change order markup including supervision allowance labor and
material markups and overhead and profit percentages as a percent of
labor and materials cost for any changes in the work following contract
award
10 Financial statement
Provide a recent financial statement (audited if possible) including balance sheet
and income statement showing
Current assets
Other assets
Current liabilities
0
Other liabilities
Fixed assets and equipment
11 Banking reference
Provide the name address and phone number of the firm s banking reference
12 Bonding company
Provide the name address and phone number of the firms bonding agent
Provide a letter from the bonding agent indicating the firm s bonding capacity is
adequate to undertake this work
13 Insurance company
Provide the name address and phone number of the firm s insurance agent(s)
Provide certificate of insurance outlining coverage and policy limits Can this
coverage be extended for work on this protect? Can coverage be increased?
Can City be listed as an additional insured? Are there any current claims that will
affect coverage limits available to the City for this protect?
14 List three (3) current references of similar work Include firm name address and
telephone number
15 Prior to Construction the contractor will be required to sign the City of Fort
Collins Standard Construction Contract This document is available for review in
the Purchasing Office
7
CONTRACTOR REVIEW AND ASSESSMENT
Construction firms will be evaluated on the following qualification criteria Criteria will form the
basis for rating of written proposals as well as oral interviews
Rating scale will be from 1 to 5 (or 10 depending on maximum possible points) with 1 being a
poor rating and the maximum possible points being an outstanding rating
POSSIBLE
QUALIFICATION
STANDARD
POINTS
MAX -MIN
10 - 1
Scope of Proposal
Does the proposal show an understanding of the scope
of the project methodology to be used in the design
and construction phases and the results that are
desired from the project?
10 - 1
Assigned Project
Does the proposed team have the necessary skills and
Team
experience to fulfill the requirements of the project?
Are the key staff available to do the work?
5 1
Safety Record
OSHA Illness/Injury Rate "OSHA Lost Work Day
Incidence Rate and Workman s Comp Experience
Modification Rate Insurance multiplier
10 - 1
Firm Experience
Has the firm worked on projects similar in scope to this
-Design
project? Has partnering been used as a basis in
--Construction
design and construction of other projects? Was this
work of a high quality in nature?
5 1
Design Phase Cost
Are the proposed design cost rates reasonable and
competitive)
10 - 1
Construction Cost
Do the proposed construction cost factors compare
Factors
favorably with industry standards and other firms
construction cost factors?
10 - 1
Firm Capability
Does the firm have experience equipment manpower
and finances to complete the work?
10 - 1
Construction
Do the referenced projects reflect favorably in respect
Performance
to completion within the contract schedule cost and
number of change orders and claims?
5-1
Motivation
Has the firm shown an interest in work and a
commitment to the successful completion of the
project?
Reference Evaluation
The City of Fort Collins will check references for overall performance timetable completeness
budget and job knowledge of selected projects/references A satisfactory/unsatisfactory rating
shall be given to each reference contacted