HomeMy WebLinkAboutCHANGE ORDER - REQUISITION - 27234AUG-03-2006 THU 08:16 AM OR ENG, FAX N0, 9702216378 P. 01 Change Order Form PROJECT TITLE: S. Taft Hill Rd. Improvements - Horsetooth Rd. to Harmony Rd. PROJECT NUMBER: 30521100.6 CONTRACTOR: Aggregate Industries (PO #6603341) CHANGE ODDER NUMBER: 2 In preparing change orders show in order as separate numbered paragraphs the following: 1. Reason for change. 2. Description of change. 3. Change in contract cost. 4. Change in contract time. 1&2. See attached sheet for detail. 3. The contract will increase by $1,820.00 4. Thom will be no change In contract time. ORIGINAL CONTRACT COST TOTAL APPROVr�Q CHANGE ORDERS TOTAL PENDING CHANGE ORDERS TOTAL. THIS CHANGE ORDER TOTAL % OF THIS CHANGE ORDER TOTAL. C.O. % OF ORIGINAL CONTRACT ADJUSTED CONTRACT COST (Assuming all change orders approved) 0.18% 0.18% $1,031.432.60 $0.00 $0,00 $1,820,00 $1,033,252.50 ACCEPTED BY: Contractors DATE:. (contractor's Representative ACCEPTED BY: "_ _ /� �^ .r .rrti — DATE: (Proje#:t Hager) / REVIEWED BY: _ _ _ _ _._ DATE: APPROVED HY: 1 0' DATE: �1(0apdrtment Head) APPROVE.[) BY: _ __ DATE: (Purchasing Agent Aver $30,000) cc: Purchasiria Accounting Contractor Pfojoct File Aggregate Industries - WRC, Inc. Change Order No. 2 SOUTH TAFT HILL ROAD IMPROVEMENTS - HORSETOOTH TO HARMONY SCR 38E) Date 7/3112DDB I Item I item Description I Unit I Quantity I unit Price ($) I Item Prics (S) I CHANGE ORDER NO.2 604 MANHOLE (72 INCH DIAMETER) EACH 2 S 3,500.00 $ 7,000.00 604 603 DELETE MANHOLE (60 INCH DIAMETER) V.ADS PIPE EACH LF 2 50 $ (2,800.OD) S 12. 00 $ (5,600_D0 $ 600.00 202 202 DELETE REMOVAL OF TREE (UP TO 24") REMOVE BUSH, SW CORNER OF CR 38E AND TAFT EACH EACH 1 1 S (620.013 3 275.00 $ (620.00 $ 276.00 202 TRIM TREES ALONG SPRINGFIELD CT APARTMENTS LS 1 $ 165.D0 S 165.00 TOTAL S 1,820.aa -n x z 0 co -J o N N rn o m aJ O MD