HomeMy WebLinkAboutPrebid - BID - 27059 5983 SOUTH LEMAY AVENUE WIDENING PROJECTw�Zc�o 6`
Vcv. ki L . P eq ee
,:ROb 4!�aeMe 5
ho" j w(t r rat
f� a- t 13,, key
Cava, S-u L C µEKEO-e co)Jly co, LZ3-31 S/
/I ►�-�� �� �►'l_ dar� y�hi ��jr(R, • C tsw� 9 �'1' ' 9 � i/
-nJ1k ems4aaoe-s 546-?343
6rp.rAr d0k. CAS•&*
l"lit�ctntr��n Co nsrtruc�r� dougm-t h � �a C�t-(.t �t� l� • v� 2-t- ��S-Cvl(� l
C U FF n 13 xedt P FCCie)14 c t( ;2 41-6 to
coPc ZIP 763q
- FG z e? -��e
TRAFFIC CONTROL AND
WORK AREA SAFETY:
• TRAFFIC CONTROL:
Traffic Control Plans must be submitted, 2 weeks,
and approved 72 hours prior to the start of
construction and before making each modification.
— Local Residential Access:
• Local access must be maintained at all times to the
adjacent properties and subdivisions.
-- The Contractor shall provide, at the Contractor's
expense, all work area safety control devices. such as
barricades and safety fence around all excavations,
trenches and drop offs.
HIGHLIGHTS FROM
SPECIFICATIONS:
z^*
q
2t11-(hi Rcmod('
1 111.)t `rti & CEO IQf'le
v
Blu(k, in L :dtry
5
----_,_ 202-13 Pulveri (eS
.........._
Asphalt In Pkicc
HIGHLIGHTS FROM
SPECIFICATIONS:
R(,riove F xist;n(t Rip
Rap Had Excess to
Dr3ke & Ziegler Stock
ie in CO[ C ROW'
HIGHLIGHTS FROM
SPECIFICATIONS:
t.
t 1 nholc.ti C.ul .III(!
S
F uc: Ex jiri(j Pipe On
4
ll��
V J(-[ Side Of L(�m,iy
East ide Removo
bra
Both Manholes Less
S
i
Thand Deep
HIGHLIGHTS FROM
SPECIFICATIONS:
�x'�ta4 i3
E VI I T lr r It U„
Y 1
-
Concrete Splrtter Box
HIGHLIGHTS FROM
SPECIFICATIONS:
Coo(, ''r, 5 Ittur &o
202-07 Remwe
,� �� �.. Concrete notch
�s
.. - � gib.. •.
South Lernay Avenue
2006 WIDENING
PROJECT
PRE -BID CONFERENCE
June 2, 2006
City of Fort Collins
Engineering Dept.
Street Oversizing Program
South Lemay Avenue
2006 WIDENING
PROJECT
PRE -BID CONFERENCE
June 2, 2006
City of Fort Collins
Engineering Dept.
Street Qversizing Program
INTRODUCTIONS:
• Street Oversizing Program:
Matt Baker - Program tv,1anager 224-6108
-- Mark Laken - Project Engineer 221-6605ext2907
Quentin Egan -- Constructiori Manager 222-0860 (cell)
Tim Tuttle - Project Engineer 221-6605
- Craig Farver -- Senior Construction Inspector 222-0854 (cell)
INTRODUCTIONS:
• COFC DEPARTMENTS:
John Stephen — Purchasing Acenl 221-G-i 77
Don Bachman —C ,/ Engineer 221-0605
Syl Mireles — Traffic Control Coordinator 221-0815
- Bob Zakely — Watershed Env. SheC 224-6063
• Design: North Star Design
— Michael Oberlander. PE L. SJ 686-9399
ATTENDANCE:
•Please be sure
to- register
BID OPENING:
• When:
- June 16, 2006 at 100 (Our Clock)
• Where:
- 215 North Mason Street (211d Floor)
IMPORTANT MILESTONES:
• AWARD CONTRACT
- Approximately the third week in June
• PRE -CONSTRUCTION MEETING
Mandatory Meetinq Prior to Start of Construction
— Date to be determined after contract is awarded
• CONSTRUCTION START DATE
— July 17, 2006
• SUBSTANTIAL COMPLETION
— October 1. 2006
• FINAL COMPLETION
— 10 working days after substantial completion
SUMMARY OF WORK:
• ZIEGLER ROAD WIDENING
- Lemay Avenue will be reconstructed from
Nassau Way to Carpenter Road, with new
curb & gutter on eastside of Lemay, 600+ LF
Sanitary Sewer 100+ LF Water Line, 2,300 LF
Curb & Gutter and 10,000 Ton Paving
CONSTRUCTION DOCS:
• Lemay Widening 2006:
- Designed By North Star Design
• Sheet # s 1 - 16
HIGHLIGHTS FROM GENERAL
CONDITIONS AND GENERAL REQ'S
• SUPERINTENDENTS:
Thr C;t,nr:r.il l,ontruaur SHALL( ;i lull time So;ennten%lont
whnsr, sole i� to inrmitrx rn'ld rut:nlin,ite All (dicets of the
work
• WARRANTY:
The Contractor will be required to warr,+nty the street improvements 2
years ift('r date of final a�rceptanrc
• CONSTRUCTION HOURS:
The operation of all machinery and vchldr,s must take place between
the hours of.
• 6:30 a.m. thru 6:00 p.m.
• The Contractor may roquest extended hours
Th1F request' - IT u,t bpF,cwod I,v tho city of F,rt (bllin i dnys pnnr
to anv :ecru.
HIGHLIGHTS FROM GENERAL
CONDITIONS AND GENERAL REQ'S:
• CONSTRUCTION SURVEYING:
--- Provided by the Contractor.
• TRAFFIC CONTROL:
-- Provided by the Contractor.
• GEOTECHNICAL AND MATERIALS
TESTING:
— Provided by the Owner. It will be the Contractor's
responsibility to schedule the testing.
HIGHLIGHTS FROM GENERAL
CONDITIONS AND GENERAL REOIS:
• PROJECT MEETING:
(:)rr f ,j :•nu 'r:.it thu r.r,rrslni,Jhr n ,n �ilu. limn 'r, Ir;
rlr turnrinr;(l The TCS will be required to attend all weekly meetings.
• PROGRESS AND SCHEDULE REVISIONS:
Schr:dules shall f)r uhdritwl wwmkly. The schedules for this project is
import,int to thu City of I oil Coihnsl he Conlrw.tor may he rr;quircd h
auhmit addrr m.;I echedulos (if ,p,,r Iit) ra on the progress of the project.
• HAUL ROUTES:
Artemil and Cullrartor streets only. Contractor will not he alloU,e,d to use
residenti,il streets to access IN; silo with tnu:ks haujing materials.
HIGHLIGHTS FROM GENERAL
CONDITIONS AND GENERAL REO'S:
• SITE CLEAN-UP:
— The Construction work and processes
shall be kept and accomplished in a neat,
clean and orderly fashion.
HIGHLIGHTS FROM GENERAL
CONDITIONS AND GENERAL REQ'S:
• SITE CLEAN-UP:
—The Construction work and processes
shall be kept and accomplished in a neat,
clean and orderly fashion.
TRAFFIC CONTROL AND WORK
AREA SAFETY:
• TRAFFIC CONTROL:
— The traffic control for this project will be paid for by the
Lump Sum to the Contractor and will include all costs
for the traffic control associated with this project.
— Message Boards will be paid for by the Day
A total of 4 message boards for 6 days will be required to
inform the surrounding public of upcoming roadway
information.
- Flagging on this job shall be paid for Lump Sum.