CHANGE ORDER NO.
PROJECT TITLE: APP Police Facility Project
CONTRACTOR: Andrew Dufford/Chevo Studio
PROJECT NUMBER:
PURCHASE ORDER NO.: 5506269
DESCRIPTION: APP Contract — Police Facility Project
1. Reason for change:
Continue with the design phase of this APP project. See attached Scope of Work
2. Description of Change: See Scope of Work
Artist will create the needed documents for fabrication.
3. Change in Contract Cost: Additional $5,900.
4. Change in Contract Time: None
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.:
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S:
ADJUSTED CONTRACT COST
(Assuming all change orders approved)
ACCEPTED BY:
ACCEPTED BY:
_ Project
REVIEWED BY:
Title:
0a,
5 900
5,900
$ 22,450
DATE:' �o
DATE:
DATE:
APPROVED BY: DATE:
Title:
APPROVED BY:
cc: Purchasing
Purchasing Agent over $15,000
DATE:
Andy Dufford / Chevo Studios
4441 West 30Tff Ave. Denver, Colorado 80212 (303) 477-3780
andy@chevostudios.com
May 26, 2006
SCOPE OF WORK: Police Facility Museum & Art Infrastructure Detailing:
This phase of work has two areas of focus. The first is to detail the infrastructure required for the interior
and exterior water features. The second task is preliminary graphic design of the museum wall elements
to allow us to finalize pricing and construction of the museum elements.
TEAM MEETINGS
I've budgeted for seven meetings. The first meeting is a strategy meeting for developing a process and
timeline. Two meetings are for me to coordinate with the Fountain subcontractor. Three additional
meetings will allow us time with Neenan Construction and the city representatives for coordination of
electrical and plumbing for the water features. I've also budgeted for two meetings with the police team
for development and review of the graphic design of the interior museum elements.
*7meetings @ 4 hours 28 hours @ $50/hour $1400
PLUMBING AND ELECTRICAL LAYOUT
These costs and hours are allocated to pay the fountain subcontractor and his engineer to develop final
specifications for the necessary infrastructure. (These hours are in addition to the meetings outlined
above)
*Infrastructure specifications 15 hours @ $50/hour $750
GRAPHIC DESIGN OF MUSEUM ELEMENTS
During this phase we will use the images scanned from the museum collection to create the preliminary
layouts of the officer wall at the entrance and the collage elements on the lobby wall. These graphic
profiles will be used to obtain final pricing on all museum elements
*Graphic Design and Pricing 75 hours @ $50/hour $3750
TOTAL COST FOR OUTLINED WORK: 1 $5900