HomeMy WebLinkAboutCHANGE ORDER - REQUISITION - 2676505/31/2006 11:12 FAX 970 221 6534 CITY OF FORT COLLINS 9 001/002
SECTION 00950
CHANGE ORDER NO.3
PROJECT TITLE: LEE MARTINEZ FARM ADDITION #5942
PO#: 5508157
BID #: 5942
CONTRACTOR: ,Empire Carpentry
DESCRIPTION: Final Change Order
I. Reason for change: Request from City
2. Description of Change:
Install ceiling fan silo store.
• XTRA concrete to extend sidewalk
• Landscape (sod & rock)
• XTRA gutter, downspouts & splash blocks
3. Change in Contract Cost Net adds and deducts S 3,066.23
4. Change in Contract Time: 0 day
ORIGINAL CONTRACT COST $ 160,562.96
TOTAL APPROVED CHANGE ORDER $ 11,040.95
TOTAL PENDING CHANGE ORDER $ 00.00
TOTAL THIS CHANGE ORDER $ 3,066.23
TOTAL C.O.% OF ORIGNINAL CONTRACT 9.8%
A.DAMED CONTRACT COST (Assuming all change orders approved) 5174,670.14
ACCEPTED B
ACCEPTED BY
APPROVED B
Title -
DATE: DATE: �J 6
Contractoorr's Repre en ' e
� DATE: I (O OG
Project Manager
r/
Y: - DATE:
APPROVED BY: nvx/,�— DATE:
Purchasing Agent over $30,000
cc: City Clerk Archi[ect
urc Contractor
Project File
Engineer
9/99 Section 00950 Pagel