HomeMy WebLinkAboutCHANGE ORDER - BID - 5942 LEE MARTINEZ FARM ADDITIONSECTION 00950
CHANGE ORDER NO.2
PROJECT TITLE: LEE MARTINEZ FARM ADDITION #5942
PO#:5508157
BID #: 5942
CONTRACTOR: Empire Carpentry
DESCRIPTION: Vestibule, Trench, Extra Electric, Extra Paint
1. Reason for change: Request from City
2. Description of Change:
• Put tile and rubber base in vestibule
• Excavate trench for Qwest
• Supply & install various electrical parts (see attached)
• Paint remainder of building beyond original scope of work
• Paint remainder of doors
3. Change in Contract Cost: Net adds and deducts $ 7,647.15
4. Change in Contract Time: 0 day
ORIGINAL CONTRACT COST $ 160,562.96
TOTAL APPROVED CHANGE ORDER $ 3,393.80
TOTAL PENDING CHANGE ORDER $ 00.00
TOTAL THIS CHANGE ORDER $ 7,647.15
TOTAL C.O% OF ORIGNINAL CONTRACT 6.9%
ADJUSTED CONTRACT COST (Assuming all change orders approved) $171,603.91
ACCEPTED B
ACCEPTED B
Y: DATE: r ?� zc C
Contractor's seutative
Y: DATE:
Yr9ject Manher
APPROVED BY: DATE: it I
Title:
t
APPROVED BY. DATE:
Purchasing Agent over $30,000
cc: City Clerk Architect
rc mmg� Contractor
Project File
Engineer
9/99 Section 00950 Page 1
4/28/2006
# Work Description
Lee Martinez Farm Addition #5942
REQUEST FORM CHANGE ORDER #2
PO#: 5508157
Compiled by: Empire Carpentry 4/28/06
Date Cateaory Companv Price
File Name: Change order RQ #2 4-28-06
Status Date
1
Vestibule
1.1
Tile
2/7/06
Tile
Sunset Tile
1.2
Demo additional SF
2/7/06
Demo
Empire
1.3
Add ruber base
2/7/06
Flooring
Insideout
$1,203.30
APPROVED
2/23/06
2
2.1
Quest trench &
conduit / 2in schdule
40 gray conduit 60
feet
12/27/05
Excavation
Empire
$1,023.75
APPROVED
1/10/06
2.2
APPROVED
with TIME
SHEETS
ADD for tree roots
2/14/06
Excavation
Em ire
$708.75
submitted
3/15/06
3
Electrial add ons
3/28/06
Electric
Brian's
$516.60
APPROVED
4/5/08
4
4.1
Paint Remainder of
building exterior
3/15/061
Paint
I Williams
1 $3,984.75
JAPPROVED
3/22/2006
Paint remainder of
5
5.1
doors
4/13/06
Paint
I Williams
1 $210.00
APPROVED
4/13/2006
TOTAL $7,647.15