Engineering Department
Change Order Form
PROJECT.TITLE: Timberline Rd, Widening Project
PROJECT NUMBER: 30525270.6 (Bid #5064)
CONTRACTOR' Connell Resources, Inc. (PO #6601742)
CHANGE ORDER NUMBER: i
rn preparing c ange oRlers show In order as separate numbered paragraphs the following:
1. Reason for change. 2. Description of change.
3. Change in contract cost. 4. Change In contract time.
1$2. Seo'attachad sheet for detail.
3. The contract cost will Increase by $31,547.DD
4. There will be no change in Contract time,
ORIGINAL CONTRACT COST
$5,277,545.27
TOTAL APPROVED CHANGE ORDERS
$0.00
TOTAL PENDING CHANGE ORDERS
$0.01)
TOTAL THIS CHANGE ORDER
$31,547.00
TOTAL % OF THIS CHANGE: ORDER
0.00%
TOTAL C.O. °/. OF ORIGINAL CONTRACT
0.60%
ADJUSTED CONTRACT COST
$6,309,192.27
(Assuming all change orders approved)
ACCEPTED
ACCEPTED
REVIEWED BY:
APPROVED BY;
DATE: ��...^—
)ATE: v
DATE: 1 e3f
APPROVED BY: lJ _ DATE:
(Purchasing Agent over $30,000)
cc: Contractor
Purchasing
Project File
F.nvineerinv Department • 291 Noah Colleee Avenue, P.O. Box 380 • Fort Collins, CO 80522-0580 , (970) 2214605
APR-19-2006 WED 08:17 AM CFO ENG. FAX NO, 9702216378 P. 02
TIMBERLINE ROAD WIDENING PROJECT - INTERM
Yn. I�nNF���1. •'yit+nq '"�'tr. M!'G�yne' LKaMt JR II'�41 N••M't'tA,M°Y YTI�Ja
Connell Resources Inc,
Additional Water Taps for Sidehill Subdivision
Additional Manhole for Sidehill Subdivision
Correct Manhole bases poured on Sidehill Subdivision
$ea attached submittal
Item
Unit
$1 Unit
Total
Connell Resources Inc. 4' Diameter Manhole
1
$
2.390.00
$
2.390.00
Connell Resources Inc. 8" DIP CL-52 Water Main
260
$
38.00
$
9.880.00
Connell Resources Inc. 24" X 8" Tapping Saddle
2
$
2,990.O0
$
5.980.00
Connell Resources Inc. Flow Fill Backfill in Street
80
$
65.00
5
5.200.00
Connell Resources Inc. 8" Tie to Existing
2
$
2,486.00
$
4,972.00
Connell Resources Inc. Storm Runs #2 & #3
1
$
3,125,00
$
3,126.00
TOTAL
$
31,647.00
�,ROWN FOR'4 GKI
Install two new water lines at STA 30+00 and 36+00 across Timberline Road.
These services were shown on the original plan sheets as existing however
were not present in the field. Manhole at STA 23+40 at the intersection of
Timberline Road and Katandin drive was shown on the original plan sheet as
existing however was not present in the field,
Manhole base and Inverts on Stone Runs #2 & #3 were previously poured
incorrectly by others.
Posted to Pay Estimate No. 1