Loading...
HomeMy WebLinkAboutCHANGE ORDER - BID - 5951 OAK STREET PLAZAPROJECT TITLE: CONTRACTOR: PROJECT NUMBER: PURCHASE ORDER NO.: DESCRIPTION: 1. Reason for change: 2. Description of Change: CHANGE ORDER NO.1 OAK STREET PLAZA RENOVATION J-2 Contracting Co. 5951 Extension in Contract Time Change in contract time due to R.O.W. vacation and funding appropriation 1) Add 30 days to the length of the contract, pushing the Final $ Completion for the Project to July 15, 2006 3. Change in Contract Cost: 4. Change in Contract Time: 30 days ORIGINAL CONTRACT COST $ TOTAL APPROVED CHANGE ORDER $ - TOTAL PENDING CHANGE ORDER $ TOTAL THIS CHANGE ORDER $ - TOTAL % OF ORIGINAL CONTRACT, THIS C.O. 0.00% TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S 0.00% ADJUSTED CONTRACT COST $0.00 (Assuming all change orders approved) ACCEPTED Contractor's ACCEPTED BY: Project Manager REVIEWED BY: Title: APPROVED BY: Title: DATE: 3 8 0.6 DATE: 'T l - DATE: DATE: APPROVED BY: DATE: Purchasing Agent over $30,000 cc: City Clerk Architect Contractor Engineer Project File Purchasing