HomeMy WebLinkAboutCHANGE ORDER - REQUISITION - 25527Transportation Services
Transportation Planning
CHANGE ORDER FORM
City of Fort Collins
PROJECT TITLE: South College Avenue Bicycle Lanes
PROJECT NUMBER: 41082028.0
CONTRACTOR: Felsburg Holt & Ullevig (PO #4405279)
CHANGE ORDER NUMBER: 1
In preparing change orders show in order as separate numbered paragraphs the following:
1. Reason for change. 2. Description of change.
3. Change in contract cost. 4. Change in contract time.
1. & 2. See attached memo for reason and description of change.
3. The contract cost will increase by $13,505.00
4. The contract time will be extended to September 30, 2006 to accommodate the construction assistance
portion of the contract.
ORIGINAL CONTRACT COST $209,887.00
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
ADJUSTED CONTRACT COST
(Assuming all change orders approved)
ACCEPTED BY:
SUBMITTED BY:
REVIEWED BY:
APPROVED BY:
cc: City Clerk
Contractor
Purchasing
Project File
$0.00
$0.00
$13, 505.00
$223,392.00
DATE: a i a+ r^
'E: 1Z ! 3 0
TE: (2 -/,I(-d -5—
rE: /L//J /dS
Furth :Vinson * FustF loor • !?C?. Box 580 . Fort Collins, CO 80522-0580 • (970) 224-6058 • FAX (910) 221-b239
NA FELSBURG
%4 H O LT &
l ULLEVIG
engineeTing paths to ryanspo-actuon solutions
October 24, 2005
Ms. Kathleen Bracke, AICP
Senior Transportation Planner
City of Fort Collins
215 North Mason Street
Fort Collins, CO 80522
RE: Budget Summary — US 287/South College Avenue Bicycle Lanes
FHU Reference No. 04-143
Dear Ms. Bracke:
This letter is provided to update you on our current budget status and to also provide you with a fee
estimate for additional services you may want for construction assistance. We would like the
opportunity to discuss the contents of this letter with you once you have had a chance to review it.
PROJECT UPDATE
Including the attached invoice, our expenditures have nearly met our project budget of $209,887.
Since the project is still being finalized our expenditures will exceed the budgeted fee. As such, we
are requesting that our project budget be adjusted to reflect the additional design efforts of the
following issues. Please keep in mind that we are almost finished with the project; therefore, this
amount isn't substantial. These issues primarily revolve around our work at the Harmony Center:
• Mail Creek Trail (Harmony Center) Design:
o Numerous design iterations were prepared to meet the desires of the Harmony
Center owner. This work included several iterations of the trail alignment (both
horizontally and vertically) and also evaluations of retaining wall locations and
design parameters. It was also necessary for us to check slope easements related
to impacts to the ROW plans or the need for additional retaining walls.
o Reviews of design concepts prepared by BHA were required to ensure that their
proposed conceptual designs met CDOT, City and ADA requirements.
• Mason Street Acceleration Lane: As you will recall, the Mason Street acceleration lane was
removed from the plan set — post FIR/FOR meeting. Even though removing portions of the
plan set may seem simple, it required time to ensure all references were removed from the
entire plan set and specification package.
• Trail Alternative Analysis at Mail Creek & Fossil Creek: Before submitting the FIR/FOR
Plan Set, we performed a preliminary analysis of trail alternatives at Mail Creek (four
alternatives) and at Fossil Creek (four alternatives) for your review at a Progress Meeting
held on June 3, 2005. The analyses included summaries of impacts, costs, right of way
areas, etc. The analyses were conducted to assess trail alignments that would have the
least amount of impact to the surrounding features and property owners (i.e., avoidance of
trees, right of way impacts, wall impacts, utility impacts, etc.).
0 W,Iv, nl : ('00 Ci't]tt'(lmal. 1 O Sk, I I.I Icl
www. tl 11. I t' 11;(. CU I I I tI)t't&iI 111
October 24, 2005
Ms. Kathleen Bracke, AICP
Page 2
Theoretically, the above listed design iterations and trail alternative analyses should have balanced
the expense expected for the final design of acceleration lanes at Mason and Carpenter Streets.
Unfortunately, the work necessary to satisfy the design objectives for the Mail Creek Trail adjacent
to the Harmony Center and along Mail Creek offset those expenses. In effect, these design
iterations (and final design) were more excessive than if we would have completed the final design
of the Mason Street and Carpenter Road acceleration lanes.
BUDGET SUPPLEMENT REQUEST
It is anticipated that an additional $6,300 is needed to provide you with plans & specifications ready
for advertisement. Table 1 summarizes the anticipated work hours and associated costs. The
costs include trail and wall revisions from comments made on the final check set, submittals of the
plan set and specification package (9 sets to CDOT and 4 sets to the City), project coordination
and project management.
Table 1. Summary of Anticipated Project Completion Costs
Task
Hours
Rate
Cost
Trail Design Revisions
44
$80/ Hour
$3,520
Wall Design Revisions
17
$100/ Hour
$1,700
Project Coordination & Management
7
$801 Hour
$ 560
Other Direct Costs (printing, etc.)
$ 520
TOTAL COST $6,300
ADDITIONAL CONSTRUCTION SERVICES (if requested by the City)
We would like to continue our working relationship throughout the construction of the project and
anticipate that you will need the following services during construction:
• Review shop drawings.
■ Provide as -built drawings summarizing information provided by the Contractor.
■ Respond to City requests of design clarifications, etc.
There is some uncertainty as to the staff needs for this work but we estimate that approximately 4
hours per week would be required for the construction engineering. The current understanding of
approximate construction time is 45 days (9 weeks). Table 2 summarizes the anticipated
construction administration costs.
Table 2. Summary of Construction Administration Costs
Task
Hours
Rate
Cost
Construction Engineering
36
$80/ Hour
$2,880
CADD
10
$70/ Hour
$ 700
Administration
5
$60/Hour
$ 300
Meetings (mileage & attendance
2 Meetings
$240/Meetin
$ 480
Other Direct Costs (printing, etc.
$2,845
TOTAL COST $7,205
October 24, 2005
Ms. Kathleen Bracke, AICP
Page 3
SUMMARY
In summary, we are requesting that our current budget be increased by the following amount to
cover remaining design services and construction assistance (if desired):
Finish Current Design = $6,300.00
Construction Assistance $7,205.00
TOTAL = $13,505.00
As such, we respectfully request an increase in our budget of $13,505 , from $209,887 to $223,392
for these tasks.
I look forward to hearing from you to discuss this matter.
Sincerely,
FELSBURG HOLT & ULLEVIG
XACW,���
Richard R. Follmer, PE, PTOE
Senior Transportation Engineer
kkn
cc: Kyle Lambrecht, P.E.