CHANGE ORDER NO. #1
PROJECT TITLE: Old Town Alleyways
CONTRACTOR: Technology Constructors
PROJECT NUMBER: 5912
PURCHASE ORDER NO.:. 970205.5283
DESCRIPTION: Weather Delays, Unit Price Clarification & Wall Stabilization
1. Reason for change: There have been 5 weather days noted to date, 10/4, 10/5, 10/10. 10/11 and 10112/05.
Unit Price for pavers "A" has been modified to unit Prices Al, A2 and A3 .
The Walt Stabilization cost will be $14,565 for current conditions and additional brick
repair at $41/sf additional scaffolding at $160/8' tower.
2. Description of Change: There have been 5 weather days noted to date, 10/4, 10/5, 10/10.
10/11 and 10/12106. Unit Price for pavers "A"
has been modified to unit Prices All, A2 and A3 .
The Wall Stabilization cost will be $14,565 for current conditions
and additional brick repair at $41/sf additional scaffolding at $160/8'
tower. Jbh A1-7
3. Change in Contract Cost: $14,565.00'
4. Change in Contract Time: 5
ORIGINAL CONTRACT COST $936,920.00
TOTAL APPROVED CHANGE ORDER
TOTAL PENDING CHANGE ORDER $0.00
TOTAL THIS CHANGE ORDER $14,565.00
TOTAL % OF ORIGINAL CONTRACT, THIS C.O. 1.55%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S 1.55%
ADJUSTED CONTRACT COST $9611,486.00
(Assuming all change orders approved)
ACCEPTED
Contractors
ACCEPTED
Project Man
Mane
BY: DATE: "// 7' ��
Representative
BY: DATE:'
REVIEWED BY:
Title:
APPROVED BY:
Title:
APPROVED BY:
Purchasing Agent over $30,000
oe: CIy Clark Arrhiteol
Contractor Engineer
Project Flle Purchasing
DATE:
DATE: / / �.�
DATE: