Loading...
HomeMy WebLinkAboutCHANGE ORDER - REQUISITION - 24785NOV-18-2005 FRI 02:02 PM CFO ENG. FAX NO, 9702216378 P. 05 Change Order Farm $aginetr'i¢g Department ' PROJECT TITLE: Trilby Rd. & Ziegler Rd. Improvements PROJECT NUMBER: 30523285.6 (Bid #5927) CONTRACTOR: Gerrard Excavation (PO #5505947) CHANGE ORDER NUMBER: .2 _ 1. Reason for change. 2. Description of change. 3. Change in contract cost. 4. Change In contract time. 18,2. See attached sheet for detail. 3. The contract cost will Increase by $ 4,478.46 4. There will be no change in contract time. ORIGINAL CONTRACT COST W1,372.43 TOTAL APPROVED CHANGE ORDERS ($14,715.60) TOTAL PENDING CHANGE ORDERS $0.00 TOTAL_ THIS CHANGE ORDER $4,478.45 TOTAL % OF THIS CHANGE ORDER 0.53% TOTAL C.O. %'OF ORIGINAL CONTRACT -1.22% ADJUSTED CONTRACT COST $831,135.28 (Assuming all change orders approved) ACCEPTED BY: 1 DATE: (Co etor's Re ntative) ~ DATE: t REVIEWED BY: Y_ sP ject ngineer} ACCEPTED BY:"f �/ f% l = %�� DATE: �I I G CCU (Pro]ect Manger- Engineering) ACCEPTED BY: �� DATE: (Department Head - Engineering) APPROVED BY: cc: Contractor Purchasing ProJOCL File DATE: (Purchasing Agent over $30,000) Et►gineertng Deportment d 281 Nortb College Avenue - P.O, 001580 • Fart Cultins) CO 805224580 • (970) 221-6605 NOV-18-2005 FRI 02:02 PM CFC ENG. FAX NO. 9702216378 P. 06 MAW4E ORUER-.r•02 7.„, q DRAKE AND ZIEGLER PHASE I MOVEMENT PROJECT 11 "UrA ALE wt VA Gerrard Excavating Additional Items for the project, - See attached submittal Please refer to the attached change order request. 1. As a part of a negotiation to lease the adjacent property for a staging area, we had agreed to haul off a pile of tires on the property. 2. Many residents have complained during the construction of this project regarding the mud and rock that is constantly left in the bike lanes. This is our share of the cleanup as agreed with the School District due to their site cleanup- 3. Additional message boards were used due to a change of scope for the traffic operations on this project during the paving operations. ' 4. Originally, we had not anticipated having to flyash the cul-de-sac. The conditions of the soil after utility connections were made, required this area to be Ilyashed. Posted to Pay Estimate # 2