HomeMy WebLinkAboutBID - 5942 LEE MARTINEZ FARM ADDITION (3)1.03 PRELIMINARY PROCEDURES
A. Owner or Architect may initiate changes by submitting a Proposal Request to
Contractor. Request will include:
1. Detailed description of the change, products and location of the change in the
project.
2. Supplementary or revised Drawings and Specifications.
3. The projected time span for making the change and a specific statement as to
whether overtime work is or is not authorized.
4. A specific period of time during which the requested price will be considered
valid.
5. Such request is for information only and is not an instruction to execute the
changes or to stop work in progress.
B. Contractor may initiate changes by submitting a written notice to Architect containing:
1. Description of the proposed changes.
2. Statement of the reason for making the changes.
3. Statement of the affect on the Contract Sum and the Contract Time.
4. Statement of the affect on the work of separate contractors.
5. Documentation supporting any change in Contract Sum or Contract Time as
appropriate.
C. Changes in the work affecting construction cost and/or contract time shall not be
started without a fully executed Change Order or other written authorization (such as a
Work Change Directive) from the Owner and Architect, in accordance with the General
and Supplementary Conditions.
1.04 CONSTRUCTION CHANGE AUTHORIZATION
A. In lieu of a Proposal Request, Architect or Owner may issue a Construction Change
Authorization or a Work Change Directive for Contractor to proceed with a change for
subsequent inclusion in a Change Order.
B. Authorization will describe changes in the work, both additions and deletions, with
attachments of revised Contract Documents to define details of the change and will
designate the method of determining any change in the Contract Sum and any change
in Contract Time.
C. Owner and/or Architect will sign and date the Construction Change Authorization or
Work Change Directive as authorization for the Contractor to proceed with the
changes.
D. Contractor will sign and date the Construction Change Authorization to indicate
agreement with the terms therein.
1.05 DOCUMENTATION OF PROPOSALS AND CLAIMS
A. Support each quotation for a lump sum proposal and for each unit price which has not
previously been established with sufficient substantiating data to allow Architect and
Owner to evaluate the quotation.
1 . Labor and equipment required.
2. Materials required:
a. Recommended source of purchase and unit cost.
b. Quantities required.
3. Taxes, insurance and bonds.
4. Credit for work deleted from Contract similarly documented.
5. Overhead and profit. Refer to Supplemental Conditions of the Contract for
01027 - 2
0237.07
SECTION 01200
PROJECT MEETINGS
PART 1 GENERAL
1.01 REQUIREMENTS INCLUDED
A. Owner shall schedule and administer Pre -Bid and Pre -Construction Conferences.
B. Contractor shall schedule and administer periodic progress meetings and specially
called meetings throughout progress of the work.
1. Prepare agenda for meetings and conduct meetings.
2. Record the minutes, including significant proceedings and decisions.
3. Reproduce and distribute copies of minutes within five (5) days after each
meeting to all participants in the meeting and parties affected by decisions
made at the meeting.
4. Prepare and regularly update an "open items list" to document and track
required decisions and pending changes.
C. Representatives of contractors, subcontractors and suppliers attending meetings shall
be qualified and authorized to act on behalf of the entity each represents.
D. Owner's representative will attend meetings to ascertain that work is expedited
consistent with Contract Documents and construction schedules.
1.02 PRE -CONSTRUCTION MEETING
A. Owner shall schedule and administer the Pre -Construction Conference within five (5)
working days after the date of Notice to Proceed.
B. Location: A central site, convenient for all parties, designated by the Owner.
C. Attendance:
1 . Owner's principal representative.
2. Contractor's project manager and superintendent.
3. Major subcontractors.
D. Agenda:
1. Distribution and discussion of:
a. List of major subcontractors.
b. Project construction schedules.
C. Schedule of Values.
d. Contractor's staging plan.
2. Critical work sequencing.
3. Major equipment deliveries and priorities.
4. Project coordination.
a. Designation of responsible personnel.
5. Procedures and processing of:
a. Field decisions.
b. Proposal requests.
C. Submittals, shop drawings and samples.
d. Change Orders.
e. Applications for Payment.
f. Certified payroll reports for Davis -Bacon wage reporting, if applicable.
6. Adequacy of distribution of Contract Documents.
7. Procedures for maintaining Record Documents.
8. Use of premises:
a. Field office, work and storage areas.
b. Owner's use of site and grounds.
9. Construction facilities, controls and construction aids.
10. Temporary utilities.
11. Safety and first -aid procedures.
12. Security procedures and temporary site or building fencing and enclosures.
13. Housekeeping procedures.
01200 - 1
0237.07
14. Pending changes and substitutions by Change Order.
15. Installation of project sign.
1.03 PROGRESS MEETINGS
A.
Contractor shall schedule and administer regular weekly meetings as determined at
the
Pre -Construction Conference and specially called meetings as required by
progress of the work.
B.
Location of the Meetings: As designated by Contractor and coordinated with the
Owner's principal representative.
C.
Attendance:
1 .
Contractor's project manager and on -site superintendent.
2.
Owner's principal representative.
3.
Architect and his professional consultants, as needed.
4.
Subcontractors as appropriate to the agenda.
5.
Others as appropriate.
D.
Suggested Agenda:
1.
Review of work progress since previous meeting.
2.
Field observations, problems and conflicts.
3.
Review of off -site fabrication and delivery schedules.
4.
Revisions to the construction schedule.
5.
Progress and schedule during succeeding work period.
6.
Review submittal schedules and expedite as required.
7.
Maintenance of quality standards.
8.
Pending changes and substitutions, with review of the proposed changes for:
a. Effect on construction schedule and completion date.
b. Effect on other contracts of the project.
9.
Review of Contractor's application for progress/final payment.
10.
Walk-through inspection of the work in progress by the Owner's
representative, Architect and his consultants, as necessary, and General
Contractor. Subcontractors will only be involved in these walk-throughs as
requested by the Owner or Architect.
END OF SECTION
01200 - 2
0237.07
SECTION 01310
CONSTRUCTION SCHEDULES
PART GENERAL
1.01 REQUIREMENTS INCLUDED
A. Contractor shall prepare and submit to the Owner/Architect estimated construction
progress schedules for the work with subschedules of related activities which are
essential to its progress.
B. Submit revised progress schedules periodically, as determined in the Pre -construction
Conference.
C. Related requirements specified elsewhere:
1. General and Supplementary Conditions, and Conditions of the Contract:
Liquidated Damages.
2. Section 01040, Coordination.
3. Section 01200, Project Meetings.
4. Section 01340, Shop Drawings, Product Data and Samples.
5. Section 01700, Contract Close -Out.
1.02 FORM OF SCHEDULES
A. Type: Schedules will be computer generated, using software specifically designed for
this intent, and shall be capable of automatically adjusting critical path entries.
B. Prepare schedules in a continuous flow, both daily and weekly formats.
1. Provide separate horizontal bar for each trade, supplier or subcontractor.
2. Horizontal Time Scale: Identify the first workday of each week.
3. Scale and Spacing: As required to allow space for notations and future
revisions.
4. Minimum Size: 8-1/2" x 11 ".
C. Format of Listing: Table of Contents of this project manual.
D. Format of Scheduling: Chronological order of the start of each item of work.
E. Identification of Listings: By major specification section numbers as a minimum.
1. Listings shall be complete enough to include each item of work that is sizable
enough to affect either the start of, or completion of, other areas of the work.
1.03 CONTENT OF SCHEDULES
A. Construction Progress Schedule:
1. Show the complete sequence of construction by activity.
2. Show the dates for the beginning and completion of each major element of
construction, based upon the Schedule of Values.
3. Substantial completion, punch list completion, final completion and contract
close-out shall be included.
B. Final Completion Schedule: Contractor shall update the latest progress schedule
through contract close-out.
C. Nothing in these requirements shall be deemed to be a usurpation of the Contractor's
authority and responsibility to plan and schedule the work as he sees fit, subject to all
other requirements of the Contract Documents.
01310 - 1
0237.07
1.04 SUBMISSIONS
A. Submit initial schedule within fifteen (15) days after Award of Contract.
1 . Owner/Architect will review schedules and return review copy within ten (10)
days after receipt, if modifications are required.
2. If required, resubmit within seven (7) days after return of review copy.
B. Submit revised progress schedules with each Application for Payment indicating actual
work progress in comparison to scheduled progress. Schedules will be reviewed at
normally scheduled meetings, as set forth in Section 01200.
C. Submit final schedule with contract close-out documentation.
1.05 DISTRIBUTION OF SCHEDULES
A. Distribute copies of the reviewed schedules to:
1 . Job site file.
2. Owner's representative.
3. Architect.
4. Other concerned parties.
B. Instruct recipients to report promptly to the Contractor in writing any problems
anticipated by the projections shown in the schedules.
END OF SECTION
01310 - 2
0237.07
SECTION 01340
SHOP DRAWINGS, PRODUCT DATA AND SAMPLES
PART GENERAL
1.01 REQUIREMENTS INCLUDED
A. Coordinate and submit shop drawings, product data and samples required by the
Contract Documents.
B. Related requirements specified elsewhere:
1. Conditions of the Contract: Definitions and additional responsibilities of parties.
2. Section 01040, Coordination.
3. Section 01200, Project Meetings.
4. Section 01310, Construction Schedules.
5. Section 01720, Project Record Documents.
6. Division 15, Mechanical, and Division 16, Electrical.
1.02 SHOP DRAWINGS
A. Drawings shall be presented in a clear and thorough manner, with sufficient detail and
completeness to clearly illustrate all conditions of the specific installation.
1. Details shall be identified by reference to sheet and detail, schedule or room
numbers shown on Contract Drawings.
2. Shop drawings shall be returned unreviewed if, in the opinion of the Owner or
owner's consultants, the drawings lack sufficient completeness or clarity to
allow their review.
B. Sheet size for all shop drawings shall be 8-112" x 11", 11" x 17" or 24" x 36".
C. Quantity and Format: Unless otherwise directed by the Owner, provide the following:
1. Shop Drawings: One (1) reproducible and three (3) prints or copies.
D. Cover Sheet: Each copy shall contain the Shop Drawing Identification Form, located at
the end of this Section.
1.03 PRODUCT DATA
A. Preparation:
1. Clearly mark each copy to identify pertinent products or models.
2. Show performance characteristics and capacities.
3. Show dimensions and clearances required.
4. Show wiring or piping diagrams and controls.
B. Manufacturer's standard schematic drawings and diagrams:
1. Modify drawings and diagrams to delete information which is not applicable to
the work.
2. Supplement standard information to provide information specifically applicable
to the work.
C. Quantity and Format: Unless otherwise directed by the Owner, provide the following:
1 . Product Data: Minimum five (5) complete sets.
1.04 SAMPLES
A. Office samples shall be of sufficient size and quantity to clearly illustrate:
01340 - 1
0237.07
1. Functional characteristics of the product with integral related parts and
attachment devices.
2. Full range of color, textures and pattern.
B. Contractor shall coordinate and submit all samples requiring finish, texture or color
selection by the Owner so that these materials may be reviewed by the Owner as a
complete package. The Owner reserves the right to withhold finish and color selections
until all such samples have been submitted.
1.05 CONTRACTOR RESPONSIBILITIES
A. Contractor shall prepare and submit to the Owner a log of shop drawing, product data
and sample submittals, indicating schedules for submission and review of individual
products or equipment.
B. Contractor shall coordinate and make submittals promptly, in accordance with the
approved submittal schedule. The Owner shall not be responsible for delays in the
work caused by the Contractor's failure to make submittals in a timely manner, the
completeness and/or accuracy of such submittals, or failure to allow adequate time for
review of submittals by the Owner or his professional consultants.
C. Contractor shall review shop drawings, product data and samples prior to submission to
Owner. Contractor shall determine and verify:
1. Quantities.
2. Field measurements.
3. Field construction criteria.
4. Catalog numbers and similar data.
5. Conformance with Specifications.
6. Completeness of submittal and compliance with the requirements of this
Section.
D. Coordinate each submittal with requirements of the work and of the Contract
Documents. Contractor shall coordinate submittals between related items of work prior
to purchasing or fabricating.
E. Review of shop drawings and submittals by the Owner/Architect is only for general
conformance with design intent of the project and general compliance with the
information given in the Contract Documents. Contractor shall be responsible for
meeting all requirements of the Drawings and/or Specifications, whether noted in the
Owner/Architect review or not.
F. Notify the Owner/Architect in writing at time of submission of any deviations in the
submittals from requirements of the Contract Documents. The Contractor must submit
in writing any requests for modifications to the Drawings and Specifications. Shop
drawings submitted to the Owner/Architect for this review do not constitute "in
writing" unless it is noted that specific changes are being requested. Changes by
means of shop drawings become the sole responsibility of the Contractor.
G. Begin no fabrication or work which requires submittals until return of submittals with
Owner/Architect approval.
1.06 SUBMISSION REQUIREMENTS
A. Make submittals promptly, in accordance with approved schedule and in such sequence
as to cause no delay in the work or in the work of any other Contractor.
B. Number of submittals required:
1 . Shop Drawings: As specified in paragraph 1.02.C.
2. Product Data: As specified in paragraph 1 .03.C.
3. Samples: Submit one sample or set of samples of each item requested.
01340 - 2
0237.07
4. The Owner reserves the right to withhold review and approval of submittals until
all required copies have been furnished.
C. Submittals shall contain the following information, to be completed on the attached
Shop Drawing Identification Form:
1. Date of submission and the dates of any previous submissions.
2. Project title and number.
3. Contract identification.
4. Names of:
a. Contractor.
b. Supplier.
C. Manufacturer.
5. Field dimensions clearly identified as such.
6. Relation to adjacent or critical features of the work or materials.
7. Applicable standards such as ASTM or Federal Specification numbers.
8. Identification of any deviations from Contract Documents.
9. Contractor's stamp, initialed or signed, certifying to review of submittal,
verification of products, field measurements and field construction criteria and
coordination of the information within the submittal with requirements of the
work and of Contract Documents.
1.07 OWNER RESPONSIBILITIES
A. Upon receipt, Owner shall distribute submittals to his professional consultants as
applicable.
B. Owner and consultants shall review submittals in a timely manner, in accordance with
the requirements of General and Supplementary Conditions.
C. Owner shall return submittals to the Contractor, with stamp indicating approval,
rejection, required revisions, or description of requirements for resubmittal, if applicable.
D. Owner shall retain copy or copies of submittals.
1.08 RESUBMISSION REQUIREMENTS
A. General: Make any corrections or changes in the submittals required by the
Owner/Engineer and resubmit until approved. Resubmittals may be required for the
following reasons:
1. Incomplete or unclear submittals, or submittals which have not first been
reviewed and approved by the Contractor.
2. Lack of required number of copies of product data or shop drawings.
3. Extent of the revisions necessary in the submittal to meet the design intent and
to be properly reviewed.
4. Materials and/or fabrication details that do not meet the design or technical
requirements of the specifications.
5. All color and/or finish selections have not been submitted as a complete
package.
B. Shop Drawing and Product Data: Revise initial drawings or data and resubmit as speci-
fied for the initial submittal. Identify any revisions made.
C. Samples: Submit new samples as required for initial submittal.
01340 - 3
0237.07
1.09 DISTRIBUTION OF REQUIREMENTS
A. Contractor shall distribute reproductions of shop drawings and copies of product data
which carry the Owner/Architect stamp of review to:
1 . Job site file.
2. Record Documents file.
3. Subcontractors.
4. Supplier or fabricator.
B. Architect shall distribute returned copies of shop drawings and product data to:
1. Owner's representative.
2. Consultants, as applicable.
01340 - 4
0237.07
SHOP DRAWING IDENTIFICATION FORM
DATE:
PROJECT:
ARCHITECT: ALLER•LINGLE ARCHITECTS, P.C.
712 WHALERS WAY, SUITE B-100
FORT COLLINS, CO 80525
(970) 223-1820
CONTRACTOR: NAME:
ADDRESS:
PHONE:
SUBCONTRACTOR: NAME:
CONTACT PERSON:
ADDRESS:
PHONE:
PRODUCT(S):
SPEC. SECTION(S):
*STAMP*
END OF SECTION
01340 - 5
0237.07
SECTION 01370
SCHEDULE OF VALUES
PART GENERAL
1.01 REQUIREMENTS INCLUDED
A. Submit to the Owner and Architect a Schedule of Values allocated to the various
portions of the work. Upon request of the Architect, support the values with data
which will substantiate their correctness.
B. Schedule of Values shall be used only as the basis for the Contractor's Applications for
Payment.
C. Related requirements specified elsewhere:
1 . Conditions of the Contract.
2. Section 01026, Application for Payment.
1.02 FORM AND CONTENT OF SCHEDULE OF VALUES
A. Schedule of Values shall be submitted to the Owner/Architect within fifteen (15) days
of Award of Contract.
B. Format: Contractor's standard forms or computer printouts. Identify schedule with:
1. Title of project and location.
2. Architect and project number.
3. Name and address of Contractor.
4. Name of Owner's Representative.
5. Contract designation.
6. Date of submission.
C. Schedule shall list the installed value of the component parts of the work in sufficient
detail to serve as a basis for computing values for progress payments during
construction.
1. List separately the costs associated with the materials and labor for each
component part of the work.
D. Basis: At a minimum, the Construction Specifications Institute 16 standard divisions of
work shall be used as the format for listing component items. Contractor may include
additional listings at their option.
1. Identify each line item with the number and title of the respective major section
of the Specifications.
2. Mechanical and Electrical: Provide separate line items for rough -in and finish
work for all plumbing, mechanical and electrical work.
E. For each major line item, list sub -values of major products or operations under the item.
F. Contractor's overhead and profit shall be listed as a separate line item.
G. The sum of all values listed in the schedule shall equal the total Contract Sum.
END OF SECTION
01370-1
0237.07
established limits, if applicable.
6. Justification for any change in Contract Time.
B. Support each claim for additional costs and for work done on a time-and-material/force-
account basis, with documentation as required for a lump sum proposal plus additional
information:
1 . Name of the Owner's authorized agent who ordered the work and date of the
order.
2. Dates and times work was performed and by whom.
3. Time record, summary of hours worked and hourly rates paid.
4. Receipts and invoices for:
a. Equipment used, listing dates and times of use.
b. Products used, listing quantities.
C. Subcontracts.
C. Document requests for substitutions for products as specified in Section 01600.
D. Support each claim for additional time due to weather -related delays with the following
daily information:
1. Statement of the reason for requesting an extension to the Contract Time due to
the weather, including the materials or trades affected and the adverse effects
of the weather upon these items.
2. Weather conditions at the site of the project for each day requested.
3. Temperature in Fahrenheit at the site for each day requested.
4. Any additional information requested by the Owner.
1.06 PREPARATION OF CHANGE ORDERS
A. Contractor shall prepare each Change Order, unless Owner or Architect is authorized to
prepare Change Orders at the Pre -Construction Conference.
B. Form: Change Order; Owner provided form.
C. Change Order will describe changes in the work, both additions and deletions, with
attachments of revised Contract Documents to define details of the change.
D. Change Order will provide an accounting of the adjustment in the Contract Sum and the
Contract Time.
1.07 LUMP SUM/FIXED PRICE CHANGE ORDER
A. Content of Change Orders will be based on either:
1. Architect's Proposal Request and Contractor's response as mutually agreed
between Owner and Contractor; or
2. Contractor's proposal for a change as recommended by Architect.
B. Owner and Architect will sign and date the Change Order as authorization for the
Contractor to proceed with the changes.
C. Contractor will sign and date the Change Order to indicate agreement with the terms
therein.
1.08 UNIT PRICE CHANGE ORDER
A. Content of Change Orders will be based on either:
1 . Architect's definition of the scope of the required changes.
2. Contractor's proposal for a change as recommended by Architect.
3. Survey of completed work.
B. The amounts of the unit prices to be either:
1 . Those stated in the Agreement.
01027 - 3
0237.07
SECTION 01400
QUALITY CONTROL
PART GENERAL
1.01 REQUIREMENTS INCLUDED
A. General quality control of the materials, equipment and labor for the project.
B. Manufacturer's field services, support, and testing requirements.
C. Related requirements specified elsewhere:
1. Section 01600, Materials and Equipment: Quality of materials and equipment to
be installed in the work.
2. Division 15, Mechanical, and Division 16, Electrical.
1.02 QUALITY ASSURANCE
A. Contractor Qualifications: General Contractor shall have completed at least three (3)
projects of similar size and complexity within the past two (2) years.
B. Manufacturers: Where two or more units of the same class of equipment are required,
these shall be the products of a single manufacturer. However, the component parts of
the system need not be the products of the same manufacturer, unless otherwise
specified.
C. Design Criteria:
1. Design equipment for operations at an elevation of 4,900 feet above mean sea
level, unless otherwise indicated in Division 15 and/or 16.
2. Coordinate details of the equipment with other related parts of the work,
including verification that all structures, piping, wiring and equipment
components are compatible.
3. Design equipment to operate under all conditions of load without objectionable
sound or vibration. Sounds or vibrations noticeable outside of room in which
equipment is installed, or annoying sounds or vibrations noticeable inside room,
will be considered objectionable. Correct conditions considered objectionable to
Architect/Engineer by means of approved vibration eliminators or by replacing
equipment at Owner's option.
4. Nameplates: Provide a permanent operational data nameplate on each item of
power -operated equipment indicating the manufacturer, product name, model
number, serial number, speed, capacity, power characteristics, labels of tested
compliances and similar essential operating data. Locate nameplates in easily
read locations.
D. Design underground piping systems, joints, couplings, valves, vaults and other
appurtenances to function under all conditions of load to be encountered on the site,
including but not limited to:
1. Soils conditions, including expansion and contraction.
2. Water table conditions.
01400 - 1
0237.07
1 .03 QUALITY CONTROL AND WORKMANSHIP
A. Maintain quality control over suppliers, manufacturers, products, services, site
conditions and workmanship to produce work of specified quality.
B. Comply with industry standards, except when more restrictive tolerances or specified
requirements indicate more rigid standards or more precise workmanship.
C. Perform work by persons qualified to produce workmanship of specified quality.
D. Secure products in place with positive anchorage devices designed for the appropriate
loads and sized to withstand stresses, vibration and racking.
1.04 MANUFACTURER'S INSTRUCTIONS
A. When required by individual Specifications section, submit manufacturer's printed
instructions in the quantity specified for delivery, storage, assembly, installation,
startup, adjusting and finishing.
B. Comply with manufacturer's instructions in full detail. Include each step in sequence.
Should instructions conflict with Contract Documents, request clarification from
Owner/Engineer before proceeding.
C. When required by individual Specification section, submit manufacturer's written
maintenance instructions for the Owner's use after occupancy.
1.05 MANUFACTURER'S CERTIFICATES
A. When required by individual Specifications section, submit manufacturer's certificate, in
duplicate, that products meet or exceed specified requirements.
1.06 MANUFACTURERS' FIELD SERVICES
A. When specified in respective Specifications section, require supplier and manufacturer
to provide qualified personnel to observe field conditions, installation and workmanship,
startup, testing and balancing of equipment as applicable and to make appropriate
recommendations.
B. Representative shall submit written report to Owner listing observations and
recommendations.
END OF SECTION
01400 - 2
0237.07
SECTION 01410
TESTING
PART 1 GENERAL
1.01 REQUIREMENTS INCLUDED
A. Materials testing by an independent, approved testing laboratory including, but not
limited to:
1 . Concret2 testing.
2. Compaction testing.
1.04 ACCESS TO SITE AND NOTIFICATION REQUIREMENTS
A. Testing laboratory will be allowed access to the site as required in the performance of
their work. Contractor shall provide testing laboratory at least 48 hours notice prior to
time testing is required prior to the next phase of work.
B. Preservation: If historical or archaeological resources are encountered during
excavation or construction of this project, the Contractor shall stop work and notify the
Owner and the Office of Archaeology and Historic Preservation, Colorado Historical
Society. Work shall not proceed until authorized in writing by the Owner.
1.05 TESTING REQUIREMENTS
A. Concrete:
1. Inspection and testing of concrete mix will be performed by an independent
testing agent contracted separately by the Owner. Contractor will coordinate all
inspection and tests required in this specification directly with Owner's
independent testing agent.
2. Submit proposed concrete mix design to inspection and testing firm for review
prior to commencement of work.
3. Test cylinders shall be taken and materials tested in accordance with require-
ments of Section 03300.
4. If tests indicate that materials do not meet specified requirements, remove
defective work, replace and retest at no additional cost to Owner.
B. Compaction at Foundations, Building Slabs and Utility Trenches:
1 . Testing of compacted fill materials shall be performed by an independent testing
agent recommended by the Contractor and approved by the Owner.
2. Notify the Owner/Architect at completion of each phase of excavation prior to
placement of backfill of all foundations and utility trenches.
3. When work of this Section or portions of work are completed, notify the testing
laboratory to perform density test. Do not proceed with additional portions of
work until results have been verified.
4. If tests indicate that compacted materials do not meet specified requirements,
remove defective work, replace and retest at no additional cost to Owner.
01410 - 1
0237.07
1.06 TESTING FEES
A. Fees for required materials testing will be paid for by the Owner as provided in the
General and Supplementary Conditions.
B. Fees for additional testing required due to improper performance of the work will be
paid by the Contractor.
1.07 TESTING RESULTS
A. Testing laboratory shall furnish copies of the required test results to the following:
1. Owner's representative.
2. Structural Engineer for open -hole inspection, concrete and steel testing.
3. Contractor.
END OF SECTION
01410 - 2
0237.07
SECTION 01510
TEMPORARY UTILITIES
PART GENERAL
1.01 REQUIREMENTS INCLUDED
A. Furnish, install and maintain temporary utility services required for construction.
Remove upon completion of work.
B. Furnish, install and maintain temporary sanitary facilities for use by construction
personnel. Remove upon completion of work.
C. Related requirements specified elsewhere:
1. Section 01060, Regulatory Requirements.
2. Section 01530, Barriers and Enclosures.
3. Section 01560, Temporary Controls.
4. Section 01590, Field Offices and Sheds.
5. Section 01710, Cleaning: Trash removal during construction.
1.02 REQUIREMENTS OF REGULATORY AGENCIES
A. Comply with the current editions of all applicable building codes. Refer to Section
01060.
B. Comply with applicable federal, state and local codes and regulations.
C. Comply with applicable utility company requirements.
1.03 UTILITY FEES
A. Utility charges and expenses for temporary construction usage for the following shall
be paid by the Owner, unless indicated otherwise:
1. Temporary electricity.
2. Temporary construction water until installation and acceptance of the building's
permanent plumbing systems.
3. Temporary heat and ventilation upon start-up of the building's permanent
mechanical systems, when put into service during the construction period as
specified in paragraph 2.03.C.
B. Utility charges and expenses for temporary construction usage for the following shall
be paid by the Contractor, unless indicated otherwise:
1. Installation or connection charge for temporary electricity, water, natural gas,
propane or telephone service.
2. Temporary sanitary facilities.
3. Temporary local and long-distance telephone, including cellular.
4. Temporary heat and ventilation until start-up or use of the building's permanent
mechanical systems, including the cost of fuel used during construction.
01510 - 1
0237.07
PART 2 PRODUCTS
2.01 MATERIALS
A. General: Materials for temporary construction uses may be new or used but must be
adequate in capacity for the required usage, must not create unsafe conditions and
must not violate requirements of applicable codes and standards.
2.02 TEMPORARY ELECTRICITY AND LIGHTING
A. Contractor may utilize existing 120/240V power service in the existing facility if
capacity is such that the use of this resource is adequate to prevent utility outage of
the existing building.
B. Install circuit and branch wiring with area distribution boxes located so that power and
lighting is available throughout the construction area by the use of construction -type
power cords.
C. Provide adequate artificial lighting for all areas of work when natural light is not
adequate for work and for areas accessible to the public.
D. Security Lighting: Provide temporary security lighting for temporary, secure materials
storage area, as may be required by the Owner's or Contractor's Builder's Risk
insurance.
2.03 TEMPORARY HEAT AND VENTILATION
A. Contractor shall provide and maintain, at his own expense, all temporary heating,
including all fuel and required attendance necessary to protect and dry all work during
cold weather.
B. Provide adequate forced ventilation of enclosed areas for curing of installed materials,
to disperse humidity and to prevent hazardous accumulations of dust, fumes, vapors or
gases.
1. Portable heaters shall be standard approved units complete with controls. Do
not store materials near sources of intense heat or open flame.
C. Permanent building heating system may be used upon installation, testing and
acceptance by the jurisdiction having authority over this area of the work, as allowed in
Division 15, Mechanical.
1. The project shall be substantially enclosed and secured with the building's
permanent glazing systems and either construction or permanent hardware.
2.04 TEMPORARY TELEPHONE SERVICE
A. Contractor shall maintain a job site telephone. (Wireless is acceptable). Contractor shall
pay all costs for installation, maintenance, removal and service charges for local calls.
Toll charges shall be paid by the party who places the call.
B. Telephones within the existing facility shall not be used by construction personnel
during the construction period.
2.05 TEMPORARY WATER
A. Contractor may utilize existing water service in the existing facility.
1 . If necessary, Contractor shall tap existing fire hydrant for construction water.
Contractor shall be responsible for acquiring any necessary permit and installing
temporary meter as required by the City of Fort Collins.
01510 - 2
0237.07
2.06 TEMPORARY SANITARY FACILITIES
A. Contractor shall provide sanitary facilities for use by construction personnel in
compliance with current laws and regulations.
1. Service, clean and maintain facilities and enclosures in accordance with local
governing health agencies.
B. Toilet facilities within the existing facility shall not be used by construction personnel
during the construction period.
PART 3 EXECUTION
3.01 INSTALLATION AND OPERATION
A. General: Install and maintain temporary utility services in accordance with
requirements of applicable federal, state and local codes and regulations, and applicable
utility company requirements.
B. Maintain and operate systems to assure continuous service.
C. Modify and extend systems as work progress requires.
3.02 REMOVAL
A. Completely remove temporary materials and equipment when use is no longer required,
or upon completion of the work.
B. Clean and repair damage caused by temporary installations or use of temporary
facilities.
C. Restore permanent facilities used for temporary construction services to original or
specified condition.
1 . Prior to final inspection, remove temporary lamps and install new lamps in all
lighting fixtures used during the construction period.
2. Prior to final inspection, clean permanent filters and replace disposable filters in
all mechanical equipment used during the construction period. Clean ducts,
blowers and coils if units were operated during the construction period without
filters.
END OF SECTION
01510 - 3
0237.07
SECTION 01520
CONSTRUCTION EQUIPMENT AND AIDS
PART GENERAL
1.01 REQUIREMENTS INCLUDED
A. Furnish and maintain required construction equipment.
B. Furnish, install and maintain required construction aids and remove upon completion of
work.
C. Related work specified elsewhere:
1. Section 01046, Access to Site.
2. Section 01510, Temporary Utilities.
3. Section 01530, Barriers and Enclosures.
4. Section 01560, Temporary Controls.
5. Section 01590, Field Offices and Sheds.
PART 2 PRODUCTS
2.01 MATERIALS
A. General: Equipment and construction aids for temporary construction uses may be
new, used or rental equipment, suitable for the intended purpose, but must not violate
requirements of applicable codes and standards.
2.02 CONSTRUCTION EQUIPMENT
A. Provide construction equipment as necessary to facilitate execution of the work,
including but not limited to:
1. Miscellaneous hand tools.
2. Miscellaneous power tools.
3. Goggles, masks, hardhats and other personal safety equipment.
4. Cranes, forklifts and other material handling equipment.
5. Rolling or vibrating plate compactors.
6. Concrete batching and pumping trucks and equipment.
7. End loaders, scrapers, backhoes and other heavy equipment.
8. Air compressors.
9. Portable electrical generators.
10. Mortar batching equipment.
11. Drywall texturing equipment.
12. Paint spraying equipment.
13. Other equipment as required.
2.03 CONSTRUCTION AIDS
A. Provide construction aids and temporary equipment required by personnel to facilitate
execution of the work, including but not limited to:
1 . Scaffolding, staging, ladders and platforms.
2. Stairs, ramps, runways and guardrails.
01520 - 1
0237.07
3. Hoists, platform lifts and chutes.
4. Concrete curing and thermal protection blankets.
5. Drop cloths and other protective materials.
6. Other facilities as required.
PART 3 EXECUTION
3.01 PREPARATION
A. Consult with Owner, review site conditions and other factors which affect construction
procedures and construction aids, including adjacent properties and public facilities
which may be affected by execution of the work.
B. Comply with applicable requirements specified in Divisions 2 through 16.
C. Relocate construction aids as required by progress of construction, by storage or work
requirements and to accommodate legitimate requirements of other subcontractors
employed at the site.
3.02 REMOVAL
A. Completely remove temporary materials, equipment and services:
1. When construction needs can be met by use of the permanent construction; or
2. At completion of the project.
B. Clean and repair damage caused by installation or by use of temporary facilities.
1. Remove foundations and underground installations for construction aids.
2. Grade areas of site affected by temporary installations to required elevations
and slopes and clean the area.
C. Restore permanent facilities used for temporary purposes to specified condition.
END OF SECTION
01520 - 2
0237.07
SECTION 01530
BARRIERS AND ENCLOSURES
PART GENERAL
1.01 REQUIREMENTS INCLUDED
A. Furnish, install, and maintain temporary construction barriers and enclosures.
B. Furnish, erect, and maintain temporary site security fencing and gates.
C. Furnish, erect and maintain temporary safety barricade fencing.
D. Related work specified elsewhere:
1. Section 01030, Alternates.
2. Section 01046, Access to Site.
3. Section 01060, Regulatory Requirements.
4. Section 01510, Temporary Utilities.
5. Section 01520, Construction Equipment and Aids.
6. Section 01560, Temporary Controls: Dust partitions.
7. Section 01590, Field Offices and Sheds.
PART 2 PRODUCTS
2.01 TEMPORARY CONSTRUCTION BARRIERS AND ENCLOSURES
A. General: Provide and maintain for the duration of construction all scaffolds, tarpaulins,
canopies, warning signs, steps, platforms, bridges, and other temporary construction
necessary for proper completion of the work, in compliance with applicable safety and
other regulations.
B. Safety Barricade Fencing: Refer to paragraph 2.08 below.
2.02 TEMPORARY SITE FENCING
A. Prior to commencing work, Contractor shall, at his option, erect and maintain
construction fencing to enclose an area for ground level construction activity, storage
and waste removal, as approved by the Owner.
1. Fencing Materials: Panelized, chain -link fencing with crossed X-type post
supports, minimum 6'-0" high.
2. Refer to the approved staging plan for approximate limits of site area to be
fenced for construction activities and storage.
B. Provide vehicular and pedestrian access gates, with locks, as appropriate for
construction access.
1. Furnish Owner's principal representative with keys to the lock of the primary
access gate.
C. Do not attach temporary fencing to any existing permanent construction, including
buildings, trees, retaining walls, walks or pavements.
D. Promptly remove temporary fencing materials upon completion of sitework, rough
grading and asphalt paving and restore area to original condition. Contractor shall
repair or replace any existing materials or equipment damaged as a part of this work at
no cost to the Owner.
1 . Fencing shall remain in place until building is secured.
01530 - 1
0237.07
2. Those mutually agreed upon between Owner and Contractor.
C. When quantities of each of the items affected by the Change Order can be determined
prior to start of the work:
1 . Owner and Architect will sign and date the Change Order as authorization for
Contractor to proceed with the changes.
2. Contractor will sign and date the Change Order to indicate agreement with the
terms therein.
D. When quantities of the items cannot be determined prior to start of the work:
1. Architect or Owner will issue a Construction Change Authorization or Work
Change Directive directing Contractor to proceed with the change on the basis
of unit prices and will cite the applicable unit prices.
2. At completion of the change, Architect will determine the cost of such work
based on the unit prices and quantities used.
a. Contractor shall submit documentation to establish the number of units
of each item and any claims for a change in Contract Time.
3. Architect will sign and date the Change Order to establish the change in
Contract Sum and in Contract Time.
4. Owner and Contractor will sign and date the Change Order to indicate their
agreement with the terms therein.
1.09 TIME AND MATERIAL/FORCE ACCOUNT CHANGE ORDER/CONSTRUCTION CHANGE
AUTHORIZATION
A. Architect and Owner will issue a Construction Change Authorization or Work Change
Directive directing Contractor to proceed with the changes.
B. At completion of the change, Contractor shall submit itemized accounting and
supporting data as provided in paragraph 1.05, Documentation of Proposals and Claims.
C. Architect will determine the allowable cost of such work as provided in General
Conditions and Supplementary Conditions.
D. Architect and Owner will sign and date the Change Order to establish the change in
Contract Sum and in Contract Time.
E. Contractor will sign and date the Change Order to indicate their agreement therein.
F. Owner must approve in writing and on a daily basis all time and material Change
Orders.
1.10 CONTRACTOR OVERHEAD AND PROFIT
A. General: Allowable limits to the Contractor's and Subcontractors' mark-ups on Change
Orders shall be as established in the Supplementary Conditions of the Contract.
1.11 CORRELATION WITH CONTRACTOR'S SUBMITTALS
A. Periodically revise Schedule of Values and Application for Payment forms to record
each change as a separate item of work and to record the adjusted Contract Sum.
B. Periodically revise the Construction Schedule to reflect each change in Contract Time.
1. Revise subschedules to show changes for other items of work affected by the
changes.
C. Upon completion of work under a Change Order, enter pertinent changes in Record
Documents.
END OF SECTION
01027 - 4
0237.07
2. Fencing shall be removed prior to finish grading, installation of underground
sprinkler system and landscaping.
2.03 MISCELLANEOUS TEMPORARY WALL AND ROOF CLOSURES
A. Provide temporary weathertight enclosure of exterior roof and walls for successive
areas of the building as work progresses to provide acceptable working conditions,
provide weather protection for materials, allowing for effective temporary heating and
to prevent entry of unauthorized persons.
1 . Provide temporary secure and fixed panels for double hung window openings.
2. Enclosures shall be removable as necessary for work and for handling of
materials.
3. Provide enclosures for protection of areas designated for use by Owner during
construction. Refer to Section 01046, Access to Site.
2.04 SAFETY BARRICADE FENCING
A. Prior to commencing any sitework within any street, alley, public sidewalk or other
right-of-way, Contractor shall prepare and submit a traffic lane closure plan to the City
of Fort Collins for approval.
1. Plan shall clearly indicate how both vehicular and pedestrian traffic shall be
safely accommodated and maintained during construction.
B. Prior to commencing such work, Contractor shall erect and maintain protective safety
barricade fencing around the areas of work, as required by the approved plan.
1. Approved Materials: Expanded plastic fencing.
2. Color: Orange, or as approved by the governing agency with jurisdiction over
this work. Refer to Section 01060.
C. Provide adequate room within fenced enclosures for workers and construction
activities.
D. Maintain all required clearances for vehicular and/or pedestrian circulation within public
right-of-ways that will be allowed during the construction period. Refer to Section
01046.
E. Consult with the City of Fort Collins for any additional barricading or public safety
requirements.
F. Promptly remove temporary safety fencing upon completion of work and restore site
area to original condition. Contractor shall repair or replace any existing materials or
finishes damaged as a part of this work at no cost to the Owner.
END OF SECTION
01530 - 2
0237.07
SECTION 01560
TEMPORARY CONTROLS
PART GENERAL
1.01 REQUIREMENTS INCLUDED
A. Furnish, install and maintain temporary facilities required for dust, erosion and pollution
control.
B. Implement and maintain temporary controls required for noise and construction work
hours limitations.
C. Related requirements specified elsewhere:
1. Section 0 10 10, Summary of Work: Special site restrictions.
2. Section 01040, Coordination.
3. Section 01046, Access to Site.
4. Section 01510, Temporary Utilities.
5. Section 01530, Barriers and Enclosures: Cold -weather construction enclosures.
PART 2 PRODUCTS
2.01 MATERIALS
A. General: Materials for temporary controls may be new or used, but must be adequate
in capacity for the required usage, must not create unsafe conditions and must not
violate requirements of applicable codes and standards.
2.02 DUST CONTROL
A. Furnish and maintain such facilities or procedures as may be necessary to prevent air-
borne dust generated by the construction activities of this project from affecting either
the Owner's use of this site or neighboring properties. Implementation of such require-
ments will be at the sole discretion of the Owner or the City of Fort Collins.
B. Furnish materials, erect and maintain temporary dust partitions to seal portions of the
building and equipment to remain in use during the construction period from affected
areas of the project.
1 . Partition Sheeting: Translucent or clear polyethylene sheets, 6-mil thickness
minimum.
C. Partitions shall be attached to the existing building so as not to damage or mar
materials or finishes.
D. Promptly remove temporary partitions upon completion of the work and restore
materials and finishes to original condition. Contractor shall repair or replace any
existing materials or finishes damaged as a part of this work at no cost to the Owner.
2.03 POLLUTION CONTROL
A. Contractor shall take all necessary precautions to prevent spilling or littering of water -
polluting substances. Do not allow any foreign materials to be dumped into any portion
of the sewer or storm drainage collection system or into any water runoff collection
basin. The Contractor shall be responsible for all labor, equipment and materials
01560 - 1
0237.07
necessary to remedy any such pollution as deemed appropriate by governing agencies
with such jurisdiction.
B. No burning of debris or any other air -polluting methods or equipment will be allowed.
All motorized equipment shall be adjusted to minimize exhaust pollution.
C. Contractor shall prevent fumes from roofing materials and equipment from being drawn
into the existing facility's air intake system. Equipment shutdowns shall be scheduled
as specified in Section 01040.
PART 3 EXECUTION
3.01 GENERAL
A. Construction Work Hours: Construction activity will be limited to 7:00 a.m. to 6:00
p.m. Monday through Saturday during the construction period, except as limited in
paragraphs 3.01.6. and 3.02. Sunday or holiday construction will not be allowed
without express written permission of the Owner.
B. Specific activities that may limit the Contractor's working hours, if applicable, shall be
determined at the Pre -Construction Conference.
3.02 NOISE CONTROL
A. Construction activities that generate noise in excess of 85 db shall be limited to hours
as established at the Pre -Construction Conference.
1. Prohibited after 6:00 p.m. every weekday, unless approval is obtained by
Owner.
2. Prohibited on Saturdays, Sundays and holidays, unless approval is obtained by
Owner.
END OF SECTION
01560 - 2
0237.07
SECTION 01580
PROJECT SIGN
PART 1 GENERAL
1.01 WORK INCLUDED
A. Contractor shall prepare, erect and maintain one painted project sign.
B. Restoration and Preservation Projects: A sign acknowledging funding from the
Colorado Department of Transportation and the City of Fort Collins to be erected and
maintained by the Contractor.
C. No other signs or advertisement will be allowed without the Owner's approval.
D. Related work specified elsewhere:
1. Section 09900, Painting.
PART PRODUCTS
2.01 MATERIALS
A. General: The project sign shall be constructed as detailed on the Drawings or attached
hereto.
B. Sign Material: 3/4" thick plywood, A/C, exterior APA, conforming to PS1 standards.
1. Size: Sign shall be cut from nominal 4'-0" x 8'-0" plywood sheet, as detai►ed
on the attached drawing.
C. Posts: 4"x4" Hem -Fir or Douglas Fir, S4S, conforming to PS 20 standards.
PART 3 EXECUTION
3.01 GENERAL
A. Architect shall review signage copy for correctness and completeness prior to beginning
work.
1. Special graphics or logo requirements will be furnished to the sign fabricator by
the Owner and/or Architect.
B. Project sign shall be erected within two (2) weeks of Notice to Proceed and shall
remain on the project site until completion of the project.
C. Location of the sign shall be as arranged at the Pre -Construction Conference.
D. The project sign shall remain the property of the Contractor and shall be promptly
removed upon completion of the project.
E. Colorado Department of Transportation sign shall be removed and returned upon
completion of the project.
3.02 INSTALLATION
A. Embed sign posts minimum 3'-0".
END OF SECTION
01580 - 1
0237.07
SECTION 01600
MATERIAL AND EQUIPMENT
PART GENERAL
1.01 REQUIREMENTS INCLUDED
A. Material and equipment incorporated into the work:
1 . Conform to applicable specifications and standards.
2. Comply with size, make, type and quality specified, or as specifically approved
in writing by the Owner/Architect.
3. Manufactured and Fabricated Products:
a. Design, fabricate and assemble in accordance with the best engineering
and shop practices.
b. Manufacture like parts of duplicate units to standard sizes and gages to
be interchangeable.
C. Two (2) or more items of the same kind shall be identical by the same
manufacturer.
d. Products shall be suitable for service conditions.
e. Equipment capacities, sizes and dimensions shown or specified shall be
adhered to, unless variations are specifically approved in writing.
4. Do not use material or equipment for any purpose other than that for which it is
designed or specified.
B. Provide specified maintenance materials, equipment and tools to the Owner at the
completion of the project.
C. Provide equipment or systems start-up, commissioning and operational testing, as
specified in individual Sections.
D. Related requirements specified elsewhere:
1. Conditions of the Contract.
2. Section 0 10 10, Summary of the Work.
3. Section 01040, Coordination.
4. Section 01340, Shop Drawings, Product Data and Samples.
5. Section 01400, Quality Control.
6. Section 01710, Cleaning.
7. Section 01730, Operating and Maintenance Data.
1.02 MANUFACTURER'S INSTRUCTIONS
A. When Contract Documents require that installation of work shall comply with
manufacturer's printed instructions, contractor shall obtain and distribute copies of
such instructions to parties involved in the installation, including two (2) copies to the
Owner.
1. Maintain one (1) set of complete instructions at the job site during installation
and until completion.
B. Handle, install, connect, clean, condition and adjust products in strict accordance with
such instructions and in conformity with specified requirements.
1. Should job conditions or specified requirements conflict with manufacturer's
instructions, consult with Owner for further instructions. Do not proceed with
work without clear instructions.
C. Perform work in accordance with manufacturer's instructions. Do not omit any
01600 - 1
0237.07
preparatory step or installation procedure, unless specifically modified or exempted by
Contract Documents.
1.03 TRANSPORTATION AND HANDLING
A. Arrange deliveries of products in accordance with construction schedules, coordinate to
avoid conflict with work and conditions at the site.
1. Deliver products in undamaged condition in manufacturer's original containers or
packaging with identifying labels intact and legible.
2. Immediately upon delivery, inspect shipments to assure that materials and
equipment are in compliance with approved submittals, required quantities have
been provided and that products are properly protected and undamaged.
B. Provide equipment and personnel to handle products by methods to prevent soiling or
damage to products or packaging.
1.04 STORAGE AND PROTECTION
A. Preparation for Shipment:
1. Prepare in a manner to facilitate unloading and handling.
2. Provide skids, boxes, crates or other effective shipping devices to protect
materials, fixtures or equipment against damage from rough handling, moisture,
dust, excessive heat or cold.
3. Protect painted surfaces against impact, abrasion, discoloration and other
damage.
4. Apply grease packing or lubricating oil to all bearing and similar items.
5. Tag or mark each item as identified in the delivery schedule or on the shop
drawings. Package or bundle items consisting of multiple similar pieces. Tag or
mark the package or bundle.
6. Include complete packing lists or bills of material with each shipment.
7. Do not ship equipment requiring cranes or special equipment for unloading or
handling without notice or until Contractor is prepared to receive and care for it
properly.
8. Protect electrical equipment, controls and insulation from moisture or water
damage.
B. Store products in accordance with manufacturer's instructions, with seals and labels
intact and legible.
1. Store products subject to damage by the elements in weathertight enclosures.
2. Maintain temperature and humidity within the ranges required by manufacturer's
instructions.
C. Exterior Storage:
1. Store fabricated products above the ground on blocking or skids. Prevent soiling
or staining. Cover products which are subject to deterioration with impervious
sheet coverings. Provide adequate ventilation to avoid condensation.
2. Store wood and wood products above the ground on blocking or skids, and
cover to protect from weather exposure.
D. Arrange storage in a manner to provide easy access for inspection. Make periodic
inspections of stored products to assure that products are maintained under specified
conditions and free from damage or deterioration.
01600 - 2
0237.07
E. Protection after Installation:
1. Protect materials, fixtures and equipment with original protective wrappings
until Substantial Completion of the project, as specified in individual Sections, to
include but not be limited to:
a. Factory -finished wood doors.
b. Custom cabinetry and casework.
C. Toilet and bath fixtures and faucets.
d. Finish hardware items.
2. Provide substantial coverings as necessary to protect installed products from
damage from traffic and subsequent construction operations. Remove when no
longer needed.
1.05 SUBSTITUTIONS AND PRODUCT OPTIONS
A. Products List:
1 . Within thirty (30) days after Award of Contract, submit to Owner a complete
list of major products proposed to be used with the name of the manufacturer
and the installing Subcontractor.
B. Contractor's Options:
1 . For products specified only by reference standard, select any product meeting
that standard.
2. For products specified by naming several products or manufacturers, select any
one of the products or manufacturers named which complies with the
specifications.
3. For products specified by naming one or more products or manufacturers and
"or equal", Contractor shall submit a request for substitutions of any product or
manufacturer not specifically named.
4. Manufacturer's material or equipment listed in Schedules, Specifications or on
the Drawings are types to be provided for establishment of size, capacity, grade
and quality. If other acceptable manufacturers are used, cost of any change in
construction required by their use shall be borne by the Contractor.
C. Contractor shall use any approved equal material or equipment at no additional cost to
the Owner if the material or equipment used in his Bid is unavailable or causes undue
delay in fabrication or delivery.
PART PRODUCTS
2.01 MATERIALS
A. General: Use materials of commercial quality suitable for the anticipated service
conditions.
B. All materials and equipment to be installed in the permanent construction shall be new,
unless otherwise permitted.
C. Unless required otherwise, use components of standard sizes to assure future
availability and permit field installation of repair parts. Make like parts of duplicate
units interchangeable.
D. If requested by Owner, Contractor to provide a Certificate of Material for building
materials that apply to this Project.
01600 - 3
0237.07
2.02 FABRICATION AND MANUFACTURE
A. Workmanship and Materials: Design, fabricate and assemble equipment in accordance
with the best engineering and shop practice.
B. Lubrication:
1. Include lubrication systems which do not waste lubricants, require attention
during startup or shutdown or more frequently than weekly during normal
operation.
2. Furnish sufficient lubricants of the type recommended by the equipment
manufacturer to fill lubricant reservoirs and replace consumption during startup,
testing and operation prior to the Owner's acceptance of the equipment.
C. Drive Units: Refer to Division 15, Mechanical, and/or Division 16, Electrical.
D. Anchor Bolts: (or as specified on drawings by Architect/Engineer)
1. Furnish with each piece of equipment required to be anchored.
2. Minimum Diameter: 3/4", or as indicated on the Drawings.
3. Minimum Length: Provide for required embedment in structural concrete and
extend through concrete base, 1-1/2" of grout, base plate and nuts. Concrete
base will be 4" thick, unless otherwise indicated.
4. Include two (2) nuts with each bolt.
5. Deliver anchor bolts with templates or setting drawings in time for installation
when structural concrete is placed.
E. Equipment Bases: (or as specified on drawings by A/E)
1. Include a cast iron or welded base plate with each pump, compressor and
similar equipment installed on concrete base, if applicable.
2. Design to support both the driven unit and its drive assembly on a single base
plate.
3. Support all equipment to be set on floor with 4" minimum concrete base.
4. Include grout holes and provisions for anchor bolts.
5. Include raised lip all around and a threaded drain connection with base plates for
pumps.
F. Special Tools and Accessories:
1 . Furnish all special tools, instruments and accessories required for proper mainte-
nance.
2. Furnish such special devices as are required for proper lifting and handling.
G. Shop Painting: Refer to Section 09900, Painting.
1. Protect iron and steel surfaces with paint or other protective coating applied in
the shop.
2. Use coating good for anticipated useful life of equipment on surfaces inaccessi-
ble after assembly.
3. Finish exposed surfaces smooth, clean and filled to obtain uniform base for
paint.
4. Apply one (1) or more shop coats of a primer capable of protecting surfaces to
receive finish paint coats after installation.
5. Apply finish coats in the shop with a high-grade oil -resistant enamel on electric
motors, speed reducers, starters and other self-contained or enclosed
components.
6. Do not paint machined, polished or non-ferrous surfaces. Coat such surfaces
with rust -preventive compound, Houghton Rust Veto 334, Rust-Oleum R-9 or
equal.
PART 3 EXECUTION
01600 - 4
0237.07
3.01 INSTALLATION
A. Install equipment with or under the guidance of qualified personnel having the
knowledge and experience necessary for proper results.
B. Arrange work to facilitate maintenance, repair or replacement of equipment. Locate
services requiring maintenance on valves and similar units in front of services requiring
less maintenance. Connect equipment for ease of disconnecting, with minimum of
interference with other work.
C. Locate operating and control equipment, dampers, valves, traps, clean -outs, motors,
controllers, switchgears, drain points, maintenance items and devices for easy access.
Install access panels where units are concealed by finished and similar work.
D. Provide required clearances in front of, and around, equipment as necessary for access
and ventilation. Comply with all applicable codes and regulations.
3.02 PLACING EQUIPMENT IN OPERATION
A. Before starting up each system:
1 . Check each piece of equipment for proper drive rotation, belt tension and any
other condition which may cause damage to equipment or endanger personnel.
2. Clean, blow-out or flush lubricating oil, water systems and other pipelines.
3. Lubricate equipment in accordance with manufacturer's recommendations.
4. Test lubrication system safety interlocks and system performance.
5. Perform final alignment checks under observation of the Owner's principal
representative and, where required, manufacturer's field representative.
6. Demonstrate that no abnormal stresses are transmitted to equipment from
piping, ducts or other attachments.
7. Check anchor bolt tensions, grout and shims. Use calibrated torque wrenches
for tightening anchor bolts. Do not overstress bolts.
B. Place equipment into successful operation in accordance with the written instructions
of the manufacturer or the instruction of the manufacturer's field representative,
including required adjustment, tests and operation checks.
3.03 PERFORMANCE TESTS
A. Tests may be required, whether or not specifically called for, to determine if equipment
will perform as specified or guaranteed. Final acceptance of equipment, or Substantial
Completion of that part of the work, is contingent upon acceptable test results.
B. Do not conduct tests on equipment for which manufacturer's field service is specified,
unless manufacturer's field representative is present and declares the equipment ready
for test.
C. Conduct tests as set forth in the Specifications, unless another manner is approved.
D. Equipment or systems that fail to satisfy the performance requirements shall be
modified or replaced at Owner/Engineer's option. If modifications are allowed, make
modifications necessary to produce an installation which will satisfy the performance
requirements. Retest after modifications or equipment replacement is complete.
Modifications, additional equipment, retesting and structural, piping or electrical
modifications necessary to accommodate modified equipment or replacement
equipment shall be made at no additional cost.
END OF SECTION
01600 - 5
0237.07
SECTION 01700
CONTRACT CLOSE-OUT
PART GENERAL
1.01 REQUIREMENTS INCLUDED
A. Comply with requirements stated in Conditions of the Contract and in Specifications for
administrative procedures in closing out the work.
B. Related requirements specified elsewhere:
1. Conditions of the Contract: Fiscal provisions, legal submittals and additional
administrative requirements.
2. Section 01026, Applications for Payment: Requirements for final payment.
3. Section 01050, Field Engineering: Surveying certificate and final completion
survey.
4. Section 01310, Construction Schedules.
5. Section 01600, Material and Equipment: Maintenance materials.
6. Section 01710, Cleaning.
7. Section 0 17 20, Project Record Documents.
8. Section 01730, Operating and Maintenance Data.
9. Section 01740, Warranties and Bonds.
10. Respective Sections of Specifications: Testing requirements and closeout
submittals required of specific trades or subcontractors.
1.02 SUBSTANTIAL COMPLETION
A. Definition of Substantial Completion: Refer to General and Supplementary Conditions of
the Contract.
B. When Contractor considers that the work is substantially complete, he shall submit to
the Owner:
1. Written notice that the work or designated portion thereof is substantially
complete.
2. "Punch list" of items to be completed or corrected, as determined by the
Contractor prior to inspection by the Owner.
3. Temporary Certificate of Occupancy, or other evidence of acceptance by the
building official or other authority with jurisdiction over the project.
C. Within a reasonable time after receipt of such notice, Owner will make an inspection to
determine the status of completion.
D. Should Owner and/or Architect determine that the work is not substantially complete:
1 . Owner/Architec will promptly notify the Contractor in writing, giving the reasons
therefor.
2. Contractor shall remedy the deficiencies in the work and send a second written
notice of substantial completion to the Owner.
3. Owner or Architect will re -inspect the work, as appropriate.
E. When Owner concurs that the work is substantially complete, he will:
1. Prepare a Certificate of Substantial Completion on Owner -provided form,
accompanied by Contractor's list of items to be completed or corrected as
verified and amended by the Owner.
01700 - 1
0237.07
SECTION 01040
COORDINATION
PART GENERAL
1.01 COORDINATION REQUIREMENTS
A. Contractor shall be responsible for the overall coordination of all civil, landscape and
urban design, architectural, structural, mechanical and electrical components and
systems that are a part of this project.
1. Coordinate components and systems prior to purchasing or fabricating.
2. Coordinate materials, equipment and fixtures supplied by various trades for
compatibility with the final installation.
B. Coordinate all work included in the Construction Documents, including but not limited
to the following construction trades:
1. Demolition.
2. Earthwork, excavation and grading.
3. Onsite utilities, including utilities designed by other jurisdictions.
4. Cast -in -place concrete.
5. Structural steel and metalwork.
6. Carpentry and cabinetwork.
7. Building and roof insulation.
8. Roofing and flashings.
9. Doors, windows and glazing systems.
10. Painting and finishing.
11. Flooring and hard surfaces.
12. Specialties.
13. Equipment.
14. Mechanical and plumbing systems.
15. Electrical systems.
C. Coordinate scheduling, submittals and work of the Drawings and various Sections of
Specifications to assure efficient and orderly sequence of installation of interdependent
construction elements.
D. Coordinate and verify that utility requirement characteristics of operating equipment are
compatible with the building utilities. Interruption of utility services shall be scheduled
with and subject to the approval of the Owner seven (7) business days prior to the
interruption.
E. Coordinate utility locates and utility designs with the City of Fort Collins and other
jurisdictions having authority over the project. Refer to Section 01060.
F. Related requirements specified elsewhere:
1. General and Supplementary Conditions: Contractor's Responsibilities.
2. Section 01010, Summary of Work.
3. Section 01050, Field Engineering.
4. Section 01060, Regulatory Requirements.
5. Section 01600, Materials and Equipment: Substitutions.
6. Section 06100, Rough Carpentry: General project coordination.
01040 - 1
0237.07
2. Submit the Certificate to the Owner and Contractor for their written acceptance
of the responsibilities assigned to them in the Certificate.
1.03 FINAL INSPECTION
A. When Contractor considers the work is complete, he shall submit written certification
that:
1 . Contract Documents have been reviewed, and that the work has been inspected
for compliance with Contract Documents.
2. Work has been completed in accordance with Contract Documents.
3. Corrective or incomplete work has been completed from "punch lists" provided
at Substantial Completion.
4. Equipment and systems have been tested in the presence of the Owner's
representative and are operational.
5. Final cleaning has been completed and project is ready for final inspection.
6. Final Certificate of Occupancy has been issued.
B. Owner will make an inspection to verify the status of completion with reasonable
promptness after receipt of such certification.
C. Should Owner consider that the work is incomplete or defective:
1 . Owner or Architect will promptly notify the Contractor in writing, listing the
incomplete or defective work.
2. Contractor shall take immediate steps to remedy the stated deficiencies and
send a second written certification to Owner that the work is complete.
3. Owner or Architect will re -inspect the work, as appropriate.
D. When the Owner finds that the work is acceptable under the Contract Documents, he
shall request the Contractor to prepare and deliver closeout submittals.
E. Should Architect perform reinspection due to failure of the work to comply with the
claims of status of either Substantial or Final Completion made by the Contractor:
1 . Owner will compensate Architect for such additional services by change order
to the A/E Agreement.
2. Owner will deduct the amount of such compensation from the final payment
due the Contractor.
1.04 SYSTEMS TESTING
A. Contractor shall conduct tests for operational systems and equipment as specified
herein or as required by individual Sections, prior to Final Inspection. Testing of
systems or equipment shall include but not be limited to:
1. Drainage and weathertightness of roofing systems.
2. Domestic water service, natural gas or other pressurized utilities.
1.05 CONTRACTOR'S CLOSE-OUT SUBMITTALS
A. Evidence of compliance with requirements of governing authorities:
1 . Certificate of Occupancy.
2. Certificates of Inspection, including plumbing, mechanical and electrical
systems.
B. Final Completion Schedule: Refer to Section 01310.
C. Project Record Documents: Refer to Section 01720.
D. Operating and Maintenance Data, Instructions to Owner's Personnel: Refer to Section
01730.
E. Warranties and Bonds: Refer to Section 01740.
01700 - 2
0237.07
F. Evidence of Payment and Release of Liens: General and Supplementary Conditions.
G. Test Results: Written approval from the testing agency for systems or equipment
requiring final testing, as specified above.
H. Certifications: Written certifications of material or equipment compliance, as required
by Colorado Department of Transportation.
1.06 FINAL ADJUSTMENT OF ACCOUNTS
A. Submit a final statement of accounting to the Owner. Statement shall reflect all
adjustments to the Contract Sum:
1. The original Contract Sum, including accepted Bid Alternates.
2. Additions and deductions resulting from:
a. Previous Change Orders.
b. Allowances.
C. Unit prices.
d. Deductions for uncorrected work.
e. Penalties and bonuses.
f. Deductions for liquidated damages.
g. Deductions for reinspection payments.
h. Other adjustments.
3. Total Contract Sum, as adjusted.
4. Previous payments.
5. Sum remaining due, including retainage.
B. Contractor will prepare a final Change Order reflecting approved adjustments to the
Contract Sum which were not previously made by Change Orders.
1.07 FINAL APPLICATION FOR PAYMENT
A. Contractor shall submit the final Application for Payment in accordance with procedures
and requirements stated in the Conditions of the Contract and Section 01026,
Applications for Payment.
END OF SECTION
01700 - 3
0237.07
SECTION 01710
CLEANING
PART GENERAL
1.01 REQUIREMENTS INCLUDED
A. Execute cleaning during progress of the work and at completion of the work.
B. Furnish, maintain and service trash removal dumpsters and/or roll -offs.
C. Furnish, maintain and service recycling containers for construction materials, packaging
and waste products.
D. Related requirements specified elsewhere:
1. Conditions of the Contract.
2. Respective Sections of Specifications: Cleaning for specific products or work.
1.02 DISPOSAL REQUIREMENTS
A. Conduct cleaning and disposal operations to comply with applicable codes, ordinances,
regulations and anti -pollution laws.
B. Disposal of waste materials, debris and rubbish shall be at a commercially -operated
recycling center, legal dumpsite or landfill.
1. Contractor shall be responsible for all dump fees and expenses associated with
hauling materials to the landfill.
PART PRODUCTS
2.01 CLEANING MATERIALS
A. Use only those cleaning materials which will not create hazards to health or property
and which will not damage surfaces.
B. Use only those cleaning materials and methods recommended by manufacturers of the
surface material to be cleaned.
C. Use cleaning materials only on surfaces recommended by cleaning material manufac-
turer.
2.02 WASTE REMOVAL CONTAINERS
A. Furnish and maintain recycling, trash and waste removal dumpsters and/or roll -off
dumpsters for the collection of waste materials, debris and rubbish, in quantities
sufficient for the Work.
1. Dumpsters shall be provided with tightly fitted covers to prevent debris from
being blown out.
2. Roll -offs shall not be required to be covered, but shall be serviced frequently
enough to prevent debris from accumulating and being blown out.
3. Individual recycling containers shall be maintained for paper, corrugated
cardboard, and co -mingled containers for glass, plastic, aluminum and steel.
General contractor shall be responsible for ensuring proper separation of
recycled materials and delivery to acceptable recycling centers.
B. Location of roll -offs and trash dumpsters shall be as arranged at the Pre -Construction
01710 - 1
0237.07
Conference.
PART 3 EXECUTION
3.01 PROGRESS CLEANING
A. Execute periodic cleaning to keep the work, the site and adjacent properties free from
accumulations of waste materials, rubbish and windblown debris resulting from
construction operations.
B. Maintain parking areas, access drives and city streets clean from mud and other debris.
C. Remove recycling, waste materials, debris and rubbish from the site periodically and
dispose of at legal commercial recycling centers, dump sites or landfills away from the
site.
3.02 CLEANING PRIOR TO PAINTING
A. Clean interior spaces prior to the start of finish painting and continue cleaning on an as -
needed basis until painting is finished.
B. Schedule operations so that dust and other contaminants resulting from cleaning
process will not fall on wet or freshly finished surfaces.
C. Temporarily seal window and door openings prior to the start of finish painting to
prevent windblown dust and other particulates from impairing wet or freshly finished
surfaces.
3.03 FINAL CLEANING
A. Final cleaning shall be performed by personnel or subcontractors skilled in this work.
B. In general, the extent of final cleaning shall be to remove grease, mastic and adhesives,
dust and dirt, stains, fingerprints, labels and other foreign materials from site -exposed
interior and exterior surfaces.
C. Interior cleaning shall include, but not be limited to:
1. Wash and polish glass, glazing and mirrors. Polish glossy surfaces to a clear
shine.
2. Damp mop all wood floors.
3. Wipe down all finish carpentry, woodwork and cabinetwork.
4. Wipe down and polish toilet partitions, toilet and bath accessories, signage
components and other specialties.
5. Broom clean and dry vacuum all interior sealed concrete floor slabs to be left
exposed. Apply specified finish/sealer.
D. Exterior cleaning shall include, but not be limited to:
1 . Wash and wipe down doors and frames.
2. Wash and polish glass and glazing.
E. Site cleaning shall include, but not be limited to:
1. Broom clean and wash down all areas of exterior concrete flatwork and asphalt
paving.
F. Ventilating Systems:
1. Clean permanent filters and replace disposable filters if units were operated
during construction.
01710 - 2
0237.07
2. Clean ducts, blowers and coils if units were operated without filters during
construction.
G. Prior to final completion or Owner occupancy, Contractor shall conduct an inspection of
the site, all site -exposed interior and exterior surfaces and all work areas to verify that
work of the entire project is clean.
END OF SECTION
01710 - 3
0237.07
SECTION 01720
PROJECT RECORD DOCUMENTS
PART GENERAL
1.01 REQUIREMENTS INCLUDED
A. Maintain at the site one (1) record copy of each of the following documents:
1. Drawings.
2. Addenda.
3. Change Orders and other modifications to the Contract.
4. Approved shop drawings, product data and samples.
5. Field test records.
B. Related requirements specified elsewhere:
1. Section 01340, Shop Drawings, Product Data and Samples.
2. Section 01410, Testing.
1.02 MAINTENANCE OF DOCUMENTS AND SAMPLES
A. Prior to beginning work, separate one (1) clean, complete set of project documents
from construction sets and hold for record document purposes. The Owner will not
furnish additional sets for the Contractor's use at the end of construction, unless
compensated for by the Contractor.
B. Store documents and samples in Contractor's field office apart from documents used
for construction. Provide files and rack for storage of documents.
C. Maintain documents in a clean, dry, legible condition and in good order. Do not use
record documents for construction purposes.
D. Make documents and samples available at all times for inspection by the Owner,
Architect and regulatory agencies.
1.03 RECORDING REQUIREMENTS
A. Record information concurrently with construction progress. Do not conceal any work
until required information is recorded.
B. Drawings shall be legibly marked to record actual construction:
1. Depths of various elements of foundation in relation to finished first floor datum.
2. Horizontal and vertical locations of underground utilities and appurtenances,
referenced to permanent surface locations.
3. Location of internal utilities and appurtenances concealed in the construction,
referenced to visible and accessible features of the structure.
4. Field changes of dimension and detail.
5. Changes made by field order or by Change Order.
6. Details not included in original Contract Documents.
C. Specifications and Addenda shall be legibly marked to record:
1. Manufacturer, trade name, catalog number and supplier of each product and
item of equipment actually installed.
2. Changes made by field order or by Change Order.
01720 - 1
0237.07
1.04 SUBMITTALS
A. At contract closeout, deliver all Record Documents to the Owner.
B. Accompany submittal with transmittal letter containing:
1 . Date, project name and number.
2. Contractor's name and address.
3. Title and number of each Record Document.
4. Signature of Contractor or his authorized representative.
C. Submit one (1) copy of approved data in final form no later than fifteen (15) days after
final inspection or acceptance, but prior to applying for final payment.
D. As -Recorded Documents shall be submitted, reviewed and accepted by the Owner and
Architect prior to the Final Application for Payment being processed.
E. Architect shall prepare and furnish the Owner with one (1) set of reproducible Record
Documents and one (1) compact disc recording the same information, in accordance
with the Contract requirements.
END OF SECTION
01720 - 2
0237.07
SECTION 01730
OPERATING AND MAINTENANCE DATA
PART GENERAL
1.01 REQUIREMENTS INCLUDED
A. Compile product data and related information appropriate for Owner's maintenance and
operation of products furnished for this project.
1. Prepare operating and maintenance data as specified in this Section and as
referenced in other pertinent Sections of the Specifications.
B. Instruct Owner's personnel in maintenance of products and in operation of equipment
and systems.
C. Related requirements specified elsewhere:
1, Section 01060, Regulatory Requirements.
2. Section 01340, Shop Drawings, Product Data and Samples.
3. Section 01700, Contract Close -Out.
4. Section 01720, Project Record Documents.
5. Section 01740, Warranties and Bonds.
6. Division 15, Mechanical, and Division 16, Electrical.
1.02 SUBMITTAL REQUIREMENTS
A. Prepare data in form of an instructional manual for use by Owner's personnel.
B. Format of Submittals:
1. Size: 8-1/2" x 11".
2. Paper: Manufacturer's printed data or neatly typewritten.
3. Drawings:
a. Provide reinforced punched binder tab, bind in with text.
b. Fold larger drawings to size of text pages.
4. Provide fly leaf for each separate product or each piece of operating equipment.
a. Provide typed description of product and major component parts of
equipment.
b. Provide indexed tabs.
5. Cover: Identify each volume with typed or printed title "OPERATING AND
MAINTENANCE INSTRUCTIONS". List the following:
a. Title of project.
b. Identity of separate structure as applicable.
C. Identity of general subject matter covered in the manual.
C. Binders:
1. Commercial quality three-ring binders with durable and cleanable plastic covers,
ring size as required.
2. When multiple binders are used, correlate the data into related, consistent
groupings.
D. Number of Manuals Required: Three (3) copies of each complete manual, including all
general information and plumbing, mechanical, electrical and fire sprinkler sections.
01730 - 1
0237.07
1 .03 CONTENT OF MANUAL
A. Neatly typewritten Table of Contents for each volume arranged in systematic order.
1 . Contractor, name of responsible principal, address and telephone number.
2. List of each product required to be included, indexed to content of the volume.
3. List with each product, name, address and telephone number of:
a. Subcontractor or installer.
b. Maintenance contractor as appropriate.
C. Identify the area of responsibility of each.
d. Local source of supply for parts and replacement.
4. Identify each product by product name and other identifying symbols as set
forth in Contract Documents.
B. Product Data:
1. Include only those sheets which are pertinent to the specific product.
2. Note each sheet to:
a. Clearly identify specific product or part installed.
b. Clearly identify data applicable to installation.
C. Delete references to inapplicable information.
C. Drawings:
1 . Supplement product data with drawings as necessary to clearly illustrate:
a. Relations of component parts of equipment and systems.
b. Control and flow diagrams.
2. Coordinate drawings with information in Project Record Documents to assure
correct illustration of completed installation. Do not use Record Documents as
maintenance drawings.
D. Written text as required to supplement product data for the particular installation:
1. Organize in consistent format under separate headings for different procedures.
2. Provide logical sequence of instruction for each procedure.
E. Copy of each warranty, bond and service contract issued indicating:
1 . Proper procedures in the event of failure.
2. Instances which might affect validity of warranties or bonds.
F. Copy of Material Safety Data Sheets (MSDS) for each product or material.
1.04 MANUALS FOR PLUMBING, MECHANICAL AND ELECTRICAL SYSTEMS
A. Content for each unit of equipment and system as appropriate:
1 . Description of unit and component parts.
2. Operating Procedures:
a. Start-up, break-in, routine and normal operating instructions.
b. Regulation, control, stopping, shutdown and emergency instructions.
C. Summer and winter operating instructions.
d. Special operating instructions.
3. Maintenance Procedures:
a. Routine operations.
b. Guide to "troubleshooting".
C. Disassembly, repair and reassembly.
d. Alignment, adjusting and checking.
4. Servicing and lubrication schedule, with list of lubricants required.
5. Manufacturer's printed operating and maintenance instructions.
6. Description of sequence of operation by control manufacturer.
01730 - 2
0237.07
7. Original manufacturer's parts list, illustrations, assembly drawings and diagrams
required for maintenance.
8. As -installed control diagrams by control manufacturer.
9. As -installed color -coded piping diagrams.
10. Charts of valve tag numbers with location and function of each valve.
11. List of original manufacturer's spare parts, manufacturer's current prices and
recommended quantities to be maintained in storage.
12. Other data as required under pertinent Sections of Specifications.
B. Content for each electric and electronic system as appropriate:
1 . Description of system and component parts.
a. Function, normal operating characteristics and limiting conditions.
b. Engineering data and tests.
C. Complete nomenclature and commercial number of replaceable parts.
2. Circuit directories of panelboards.
a. Electrical service.
b. Controls.
C. Communications.
3. As -installed color -coded wiring diagrams.
4. Operating Procedures:
a. Routine and normal operating instructions.
b. Sequences required.
C. Special operating instructions.
5. Maintenance Procedures:
a. Routine operations.
b. Guide to "troubleshooting".
C. Disassembly, repair and reassembly.
d. Adjustment and checking.
6. Manufacturer's printed operating and maintenance instructions.
7. List of original manufacturer's spare parts, manufacturer's current prices and
recommended quantities to be maintained in storage.
8. Other data as required under pertinent Sections of Specifications.
C. Prepare and include additional data when the need for such data becomes apparent
during instruction of Owner's personnel.
1.05 SUBMITTAL SCHEDULE
A. Submit specified number of copies of approved data in final form no later than fifteen
(15) days after final inspection or acceptance, but prior to applying for final payment.
B. Operating and maintenance manuals shall be submitted, reviewed and accepted by the
Owner prior to the Final Application for Payment being processed.
1.06 INSTRUCTION OF OWNER'S PERSONNEL
A. Prior to final inspection or acceptance, fully instruct Owner's designated operating and
maintenance personnel in operation, adjustment and maintenance of products,
equipment and systems.
B. Operating and maintenance manual shall constitute the basis of instruction.
C. Review contents of manual with personnel in full detail to explain all aspects of
operations and maintenance.
END OF SECTION
01730 - 3
0237.07
1.02 RELATED WORK BY OTHERS
A. Coordinate as required with the Owner for related work, as shown on the Drawings or
specified herein, to be performed by the Owner's own forces or by separate contract
from this project. Refer to Section 01010.
1.03 COORDINATION OF SCHEDULES
A. Coordinate schedule of construction activity with the Owner's continued use of the
facility and site. Refer to Section 01046, Access to Site.
B. Coordinate schedule of construction activity with the Owner and other Contractors as
necessary to facilitate the related work by others described above.
1.04 COORDINATION MEETINGS
A. In addition to progress meetings specified in Section 01200, Contractor shall hold
coordination meetings and pre -installation conferences with personnel and Subcontrac-
tors to assure coordination of work.
1.05 COORDINATION OF SUBMITTALS
A. General: Schedule and coordinate all submittals specified in Section 01340 or other
Sections.
B. Coordinate work of various Sections having interdependent responsibilities for
installing, connecting to and placing in service such equipment.
C. Coordinate requests for substitutions to assure compatibility of space, operating
elements and the effect on work of other Sections.
1.06 COORDINATION OF SPACE
A. Coordinate use of project space and sequence of installation of mechanical and
electrical work which is indicated diagrammatically on the Drawings. Follow routing
shown for pipes, ducts and conduits as closely as practicable, with due allowance for
available physical space; make runs parallel with lines of building. Utilize space
efficiently to maximize accessibility for other installations, for maintenance and for
repairs.
B. In finished areas, except as otherwise shown, conceal pipes, ducts and wiring in the
construction. Coordinate locations of fixtures and outlets with finish elements.
1.07 COORDINATION OF CONTRACT CLOSE-OUT
A. Coordinate completion and cleanup of work of separate Sections in preparation for
Substantial Completion.
B. Assemble and coordinate close-out submittals specified in Section 01700.
C. After Owner's occupancy of premises, coordinate access to the site by various
Sections for correction of defective work and work not in accordance with Contract
Documents to minimize the disruption of Owner's activities.
END OF SECTION
01040 - 2
0237.07
SECTION 01740
WARRANTIES AND BONDS
PART GENERAL
1.01 REQUIREMENTS INCkUDED
A. Contractor shall compile specified warranties and bonds and specified service and
maintenance contracts.
B. Review submittals to verify compliance with Contract Documents.
C. Submit to Architect for review and transmittal to Owner.
D. Related requirements specified elsewhere:
1 . Instructions to Bidders: Bid or Proposal Bond.
2. Conditions of the Contract: Performance Bond and Labor and Material Payment
Bond.
3. Conditions of the Contract: General Warranty of Construction.
4. Section 01700, Contract Close -Out.
5. Section 01730, Operating and Maintenance Data.
6. Respective Sections of Specifications which specify the product.
1.02 SUBMITTAL REQUIREMENTS
A. General: Submit warranties, bonds and service and maintenance contracts as specified
in respective Sections of Specifications.
1. Unless otherwise indicated, all warranties shall be written in the Owner's name,
and shall be transferable to future Owner(s) for the duration of the warranty
period.
B. Assemble warranties, bonds and service and maintenance contracts, executed by each
of the respective manufacturers, suppliers and subcontractors, bound with operating
and maintenance data. Manuals are specified in Section 01730.
C. Number of original signed copies required: Three (3) each, or as required by number of
manuals specified in Section 01730.
D. Table of Contents: Neatly typed in orderly sequence. Provide complete information for
each item.
1. Product or work item.
2. Firm with name of principal, address and telephone number.
3. Scope of warranty, bond or service and maintenance contract.
4. Date of beginning of warranty, bond or service and maintenance contract.
5. Duration of warranty, bond or service and maintenance contract.
6. Provide information for Owner's personnel:
a. Proper procedure in case of failure.
b. Conditions which might affect the validity of warranty or bond.
7. Contractor, name of responsible principal, address and telephone number.
E. Format of Submittals:
1 . Format: Prepare in duplicate packets.
2. Size: 8-1/2" x 11 " punched sheets for standard three-ring binder. Fold larger
sheets to fit into binders.
01740 - 1
0237.07
1.03 SCHEDULE OF SUBMITTALS
A. Submit documents within twenty-five (25) days after inspection and acceptance for
equipment or component parts of equipment put into service during progress of
construction.
B. Otherwise make submittals within twenty-five (25) days after date of Substantial
Completion, prior to final request for payment.
C. For items of work where acceptance is delayed materially beyond date of Substantial
Completion, provide updated submittal within ten (10) days after acceptance, listing
date of acceptance as start of warranty period.
1.04 REQUIRED WARRANTIES AND BONDS
A. Bid or Proposal Bond: Refer to Instructions to Bidders.
B. Performance Bond: Refer to Conditions of the Contract.
C. Labor and Material Payment Bond: Refer to Conditions of the Contract.
D. General Warranty of Construction: Refer to Conditions of the Contract. Unless
modified elsewhere, General Contractor shall warrant all construction materials and
workmanship for a period of one (1) calendar year from the date of Substantial Comple-
tion.
E. Warranties: Provide required warranties for products, materials and equipment covering
defects in materials and workmanship for the time duration(s) specified in individual
Sections. Where no specific warranty is mentioned, provide warranty coverages
normally provided by the manufacturer for that product.
1. Unless otherwise indicated, all warranties shall be written in the Owner's name.
2. All warranties shall be transferable to future Owner(s) for the duration of the
warranty period.
F. Provide warranties and/or bonds for all products and services specified in the Drawings.
F. Optional Bond(s): The Contractor shall retain the right to require Performance and/or
Labor and Material Payment Bonds from any or all of his/her Subcontractors.
G. Maintenance Agreements: None required. However, all Contractors and Subcontrac-
tors shall be required to make service calls as requested by the Owner throughout the
one-year general warranty period, at no additional expense to the Owner.
END OF SECTION
01740 - 2
0237.07
Lee Martinez Farm Admin Addition
City of Fort Collins, Colorado
DIVISION 2 SITEWORK
Section 02070 Selective Demolition
Minor demolition of existing building and site materials, equipment and fixtures, as identified on the
Drawings, and removal from the site.
Section 02080 Hazardous Materials
Upon discovery of asbestos or other hazardous materials within the building, the Contractor shall stop
work in the affected area and notify the Owner.
Section 02100 Site Preparation
Overlot grading and stockpiling of topsoil for reuse during final grading; site clearing and minor site
demolition; finish grading and placement of topsoil prior to landscaping.
Section 02221 Trenching, Backfilling and Compacting
Trenching for utilities, backfilling with approved bedding and backfill materials, and compacting to
minimum standards of Standard Proctor Density (S.P.D.) as required by the Soils Report.
Section 02225 Structural Excavation, Backfilling and Compacting
Excavation for structures to level of original, undisturbed soil; reuse of existing backfill material or
import of structural fill material and compaction to minimum standards of Standard Proctor Density
(S.P.D.) as required by the Soils Report.
Section 02515 Portland Cement Concrete Paving
Exterior Concrete Flatwork: 4,000 psi minimum concrete paving at driveway aprons, trash enclosure and
loading area aprons, and sidewalks, over granular base, thickness as recommended in the Soils Report.
All exterior concrete flatwork to be reinforced with fiber reinforcing.
Section 02810 Underground Irrigation System
The Contractor shall move the irrigation lines as necessary (due to the addition's location) and the
Contractor shall make any repairs necessary due to damage to the irrigation system during construction.
Section 02930 Sodding
Soil preparation and amendment; in areas disturbed during construction, install new sod to match the
existing grass.
7
Lee Martinez Farm Admin Addition
City of Fort Collins, Colorado
DIVISION 3 CONCRETE
Reference Structural S1.0
DIVISION 4 MASONRY
Not used.
DIVISION 5 METALS
Reference Structural S1.0
DIVISION 6 WOOD AND PLASTICS
Section 06100 Rough Carpentry
Reference Structural S1.0.
Exterior and Interior Framing: All wood is to be FSC (Forest Stewardship Council) certified. Contractor is
to provide Architect/Owner with vendor invoices with the COC (Chain of Custody) numbers that comply
with FSC standards. Wood products without submittal of acceptable documentation will be rejected.
Exterior Framing 2x6 @ 16" o.c. Hem -Fir #2 K-D; 2x6 framing.
Interior Framing: 2x4 @ 16" o.c. Hem -Fir #2 K-D; stud grade for non -load bearing walls.
Roof Sheathing: 1 /2" CDX plywood or oriented strand board (OSB), glued and nailed.
Wall Sheathing: 7/16" oriented strand board (OSB) where required for structural bracing.
Corner and Shear Wall Bracing: Let -in steel strap angle braces, if required.
Miscellaneous Furring and Stripping: 1x and 2x Hem -Fir.
Curbs, Sills and Plates: Redwood or pressure -treated Hem -Fir.
Simpson beam and joist hangers, clips and truss connectors.
Section 06170 Prefabricated Structural Wood
Reference Structural S1.0.
Section 06200 Finish Carpentry
Exterior and Interior Framing: 2x6, 2x4, miscellaneous trim and siding. All wood is to be FSC (Forest
Stewardship Council) certified. Contractor is to provide Architect/Owner with vendor invoices with the
COC (Chain of Custody) numbers that comply with FSC standards. Wood products without submittal of
acceptable documentation will be rejected.
Softwood Casings, Base, Standing and Running Trim: Poplar or species to match existing, S4S, plain
sawn, for transparent finish.
Storage shelving: Plastic laminate finished shelving; recessed slotted standards for adjustable shelving
systems.
KI
Lee Martinez Farm Admin Addition
City of Fort Collins, Colorado
DIVISION 7 THERMAL AND MOISTURE PROTECTION
Section 07115 Sheet Membrane Waterproofing
Single -ply membrane waterproofing, self -adhering type, standard T-0" roll width, Ice and Water Shield
by W.R. Grace or equal. Install as shown on the Drawings, or as required by project conditions.
Section 07150 Dampproofing
Asphaltic dampproofing applied to below -grade concrete foundation walls.
1. Liquid -type, spray applied, clear or gray colors only.
Section 07190 Vapor Retarders
6 mil poly vapor barrier where shown on the Drawings.
Section 07200 Building Insulation
Furnish and install the following building thermal and acoustical insulation materials, completely filling
all voids and providing thermal barrier without penetrations:
1. Attic and Exterior Wall Insulation: Faced blanket -type fiberglass batt insulation, R-38 at roof and
R-19 at walls.
2. Acoustical Insulation: Unfaced blankets in all interior walls.
Section 07215 Foundation Insulation
Furnish and install the following building thermal insulation materials for foundation systems:
1. Perimeter Foundation Insulation: 1-1 /2" extruded polystyrene rigid board insulation, adhered to
concrete foundation walls.
Section 07466 Wood Siding and Trim
Wood Siding (Exterior and Interior): 1x6, shiplap siding to match the existing siding. Contractor is to
submit a sample prior to ordering wood. All wood is to be FSC (Forest Stewardship Council) certified.
Contractor is to provide Architect/Owner with vendor invoices with the COC (Chain of Custody) numbers
that comply with FSC standards. Wood products without submittal of acceptable documentation will be
rejected.
Section 07610 Prefinished Metal Roofing
Prefinished 24-gage, corrugated metal roof to match the existing roof, with baked -on Kynar 500 finish (to
match existing finish), with associated flashings, cap, ridge and eave trims, seamless gutters and
downspouts. Neoprene closer strips required at all roof edges.
Secondary Underlayment: Provide single -ply sheet membrane waterproofing as specified in Section
07115. Apply to overhanging roof eaves and valleys, and extend over heated area of roof minimum T-0",
where shown on the Drawings.
Section 07621 Galvanized Metal Flashing and Trim
Prefinished galvanized flashings, valley flashings and wall -to -roof transition flashings, as shown on the
Drawings. New flashings to match the profile of the existing flashings. Provide material gages as follows:
1. Exposed Wall -to -Roof Transition Flashings: 24-gage.
2. Roof Valley Flashings: 26-gage.
Section 07900 Sealants and Joint Fillers
Exterior Areas: One- or two-part polyurethane -based elastomeric sealants.
Interior Areas: One -part general-purpose, non -staining acrylic latex and silicone -based caulk for interior
or exterior use.
4
Lee Martinez Farm Admin Addition
City of Fort Collins, Colorado
DIVISION 8 DOORS AND WINDOWS
Section 08110 Standard Steel Doors and Frames
Exterior Insulated Doors: 16-gage flush -face sheets over insulated foam core.
Interior Steel Doors: 18-gage flush -face sheets over honeycomb core, except use 16-gage over 36" leaf
width.
Steel Frames: 16-gage standard profile, except use 14-gage for all exterior doors and for interior doors
over T-0" width. Provide silencers in door frame for all interior doors not specified to receive smoke
gaskets.
Section 08610 Wood Windows
Fixed and operable sliding, casement- and awning -type prefinished aluminum -clad wood windows, by
Pella, Marvin, Andersen Sierra Pacific, or Kolbe Et Kolbe only, manufacturer's standard color finishes.
Provide double insulated glazing Low-E tinted glass; insect screens on all operable units.
Hardware: All ventilating units are to be provided with manufacturer's standard interior and exterior
vinyl weatherstripping, roto gear operations, locks, locking handles and strikes. All units will be
lockable.
1. Finish: Manufacturer's standard "Champagne" finish.
Grilles: None.
Finish: Prefinished aluminum clad exterior, electrostatically coated; natural wood interior for stain and
seal - transparent finish. Refer to Section 09930.
Cladding Color: White to match existing.
Section 08700 Finish Hardware
Commercial: Door hardware by Schlage, match City of Fort Collins standards, finished to match existing
hardware, including butt hinges, locksets, latchsets, deadbolts, thresholds, weatherstripping and
specialty hardware items. Provide lever trims at all new doors.
Community Building/Commercial:
1. Group A
Entrance/Exits (Hollow Metal)
1 1 /2 pr.
Hinges
1 ea.
Entry lockset with lever trim - F-81 (451)
1 ea.
Deadbolt - E-2141
1 ea.
Closer - LCN 4000 Series
1 ea.
Threshold
1 ea.
Door Sweep
1 set
Weatherstripping
1 set
Kickplate (stainless steel 12" both sides)
2. Group B Office
1 1 /2 pr. Hinges
1 ea. Lockset, with lever trim - F-81 (451)
1 ea. Stop
3. Group C StoraQe Rooms and Closets
1 1 /2 pr. Hinges
1 ea. Lockset - F-86 (457)
1 ea. Stop
5
Lee Martinez Farm Admin Addition
City of Fort Collins, Colorado
4. Group D Classrooms
1 1 /2 pr. Hinges
1 ea. Classroom lockset with lever trim
1 ea. Closer - LCN 4000 Series
1 ea. Stop
Keying: Provide two (2) sets of keys for each keyed group as follows:
1. Key entries together.
2. Key each office and classroom separately.
3. Key storage rooms together.
4. Key Silo Store separately.
5. Key entire Project to the Owner's existing master key system.
Section 08800 Glass and Glazing
1. Sealed 3/4" or manufacturer's standard thickness insulated glazing, two panes of 3/16" glass with
3/8" air space, at all exterior doors and windows, Low-E tinted. All glass in doors, sidelites or
within T-0" of a door shall be polished tempered glass.
2. 1 /4" polished tempered glass, clear, at all interior doors and sidelites.
0
Lee Martinez Farm Admin Addition
City of Fort Collins, Colorado
DIVISION 9 FINISHES
Section 09260 Gypsum Wallboard Systems
Specify the technical requirements for all gypsum wallboard materials, systems and accessories.
1. Interior partition walls, soffits and ceilings: 5/8" gypsum wallboard; screw installed, taped and
spray -textured.
2. Miscellaneous gypsum wallboard accessories as required for particular applications, including
corner beads, corner mouldings, reveal mouldings and expansion joints.
Section 09330 Quarry Tile
Floor Tile: Match existing tile, 6" x 6" x 1 /2" thick.
Section 09900 Painting
All paints (exterior and interior) shall be in compliance with the Greenseal Document GS-11.
VOC limits: Flat Paint: 50 g/L; Gloss Paint: 150 g/L. The Contractor shall submit cut sheets confirming
VOC and GS-11 compliance.
Approved Manufacturers:
1. Kelly -Moore Paints: Enviro-Cote.
2. ICI Dulux Paints: Lifemaster 2000.
3. Sherwin Williams: Harmony.
4. Benjamin Moore: Ecospec.
5. AFM Safecoat Paints.
One coat primer and two coats finish for various substrates.
1. Exterior Hollow Metal or Ferrous Metal Surfaces:
Primer: Shop prime or inhibitive metal primer.
Finish: Alkyd semi -gloss enamel, two (2) coats.
2. Exterior Painted Wood or Hardboard Surfaces:
Primer: Acrylic latex wall primer.
Finish: Alkyd semi -gloss enamel, two (2) coats.
3. Interior Gypsum Wallboard and Plaster Surfaces:
Primer: Acrylic latex wall primer.
Finish: Acrylic latex satin wall paint, two (2) coats.
4. Interior Hollow Metal or Ferrous Metal Surfaces:
Primer: Shop prime or inhibitive metal primer.
Finish: Alkyd semi -gloss enamel, two (2) coats.
Section 09930 Transparent Finishes
One coat stain/sealer and two coats polyurethane finish for various wood surfaces:
1. Interior Stained Wood Doors, Casings, and Trims:
Primer/Stain: Semi -transparent alkyd -oil interior wiping stain/sealer to match existing wood
casings and trim. Use low VOC stain.
Finish: Clear satin polyurethane finish to match existing wood. Use low VOC finish.
7
Lee Martinez Farm Admin Addition
City of Fort Collins, Colorado
DIVISION 10 SPECIALTIES
Not used.
DIVISION 11 EQUIPMENT
Not used.
DIVISION 12 FURNISHINGS
Section 12512 Window Coverings
1" aluminum slat horizontal blinds for all new windows. No window coverings are required for full lite
entry doors and sidelites. Submit color sample for Architect/Owner approval.
DIVISION 13 SPECIAL CONSTRUCTION
Not used.
DIVISION 14 CONVEYING SYSTEMS
Not used.
DIVISION 15 MECHANICAL
Reference Mechanical Drawings.
DIVISION 16 ELECTRICAL
Reference Electrical Drawings.
END OF SPECIFICATION
1.1
Lee Martinez Farm Admin Addition
City of Fort Collins, Colorado
SECTION 01045
CUTTING AND PATCHING
PART GENERAL
1.01 WORK INCLUDED
A. Requirements and limitations for cutting and patching of the work. Cutting and
patching shall be as required to provide a complete and finished project.
B. Related work specified elsewhere:
1. Section 01600, Materials and Equipment: Substitutions.
2. Section 02070, Selective Demolition.
1.02 SUBMITTALS
A. Submit written request in advance of cutting or alteration which affects:
1 . Structural integrity of any element of the project.
2. Building, fire, life safety or handicapped accessibility compliance of the project.
3. Integrity of weather -exposed or moisture -resistant elements.
4. Efficiency, maintenance or safety of any operational element.
5. Visual or aesthetic qualities of sight -exposed elements.
B. Include in request:
1 . Location and description of affected work.
2. Necessity for cutting or alteration.
3. Description of proposed work and products to be used.
4. Alternatives to cutting and patching.
5. Effect on work of Owner or separate Contractor, if any.
6. Date and time work will be executed.
PART 2 PRODUCTS
2.01 MATERIALS
A. Materials used in cutting and patching shall be those required for, or to match, original
construction.
B. For any change in materials, submit request for substitution in accordance with Section
01600.
PART 3 EXECUTION
3.01 CUTTING AND PATCHING
A. Execute cutting, fitting and patching as required for a complete and finished project.
1. Contractor shall be responsible for cutting and patching as required for the
completion of the work. No cutting shall be done without approval of the
Architect or Owner as to location, method and extent of cutting.
0237.05 01045-1
;,3�'t�YMie
SOILS AND FOUNDATION INVESTIGATION
ADDITION TO THE ADMINISTRATION BUILDING
THE FARM AT LEE MARTINEZ PARK
FORT COLLINS, COLORADO
Prepared For:
CITY OF FORT COLLINS OPERATION SERVICES
117 Mason Street
PO Box 580
Fort Collins, Colorado 80522-0580
Attention: Mr. Steve Seefeld
Facilities Project Manager
Project No. FC03527-125
June 30, 2005
4001 Automation Way I Unit 2D7 I Fort Collins, Colorado 80525
Telephone:970-206-9455 Fax:970-206-9441
TABLE OF CONTENTS
SCOPE 1
SUMMARY OF CONCLUSIONS 1
SITE CONDITIONS 2
PROPOSED CONSTRUCTION 2
INVESTIGATION 2
SUBSURFACE 3
FOUNDATIONS 3
SLAB -ON -GRADE FLOOR 4
STRUCTURAL FLOOR g
WATER SOLUBLE SULFATES 7
SURFACE DRAINAGE 7
LIMITATIONS g
FIGURE 1 - LOCATIONS OF EXPLORATORY BORINGS
FIGURE 2 - SUMMARY LOGS OF EXPLORATORY BORINGS
FIGURE 3 - SWELL CONSOLIDATION TEST RESULTS
TABLE I - SUMMARY OF LABORATORY TEST RESULTS
CITY OF FORT COLLINS OPERATION SERVICES
ADDITION TO ADMINISTRATION BUILDING
THE FARM AT LEE MARTINEZ PARK
CTLIT PROJECT NO. FC03527-125
T
SCOPE
This report presents the results of our soils and foundation investigation
for the proposed addition to the administrative building at The Farm at Lee
Martinez Park in Fort Collins, Colorado. We were retained to investigate the
subsurface conditions at the addition site and to recommend geotechnical design
criteria for design and construction of the addition.
Included in this report are descriptions of the subsurface conditions found
in our borings, our characterization of the engineering properties of the subsoils,
a recommended foundation type(s) for the addition, and other design and
construction details influenced by the subsoils. Our opinions are summarized in
the following paragraphs. More complete descriptions of the subsurface
conditions, results of our field and laboratory investigations and our opinions,
conclusions and recommendations are included in the subsequent sections of
this report.
SUMMARY OF CONCLUSIONS
1. We drilled two borings for the proposed addition. One boring (TH-1)
penetrated 4.5 feet of loose to medium dense, clayey sands over 6
feet of dense, gravelly sands underlain by hard to very hard,
claystone bedrock at 10.5 feet. The second boring (TH-2) penetrated
3 feet of medium dense, clayey sands over 4 feet of stiff, sandy clays
over 2.5 feet of dense, gravelly sands over 2.5 feet of firm, claystone
bedrock underlain by very hard claystone bedrock at 12 feet. The
bedrock was harder at depth. Ground water was not encountered
when the borings were drilled.
2. In our opinion, the addition to the administration building can be
founded on spread footings bearing on the undisturbed natural soils
below frost depth. Design criteria are included in this report.
3. The natural soils or non -swelling structural fill can be the subgrade
for a slab -on -grade floor.
CITY OF FORT COLLINS OPERATION SERVICES
ADDITION TO ADMINISTRATION BUILDING 1
THE FARM AT LEE MARTINEZ PARK
CTL I T PROJECT NO. FC03527-125
T
SITE CONDITIONS
The Farm is an agricultural learning center operated by the City of Fort
Collins with various outbuildings and animal pens designed to simulate an
operational farm. It is located in the southwest corner of Lee Martinez Park in the
northern part of Fort Collins, Colorado. The park is bordered on the north and
east by the Poudre River and much of the park is located in the flood plain of the
river. The Farm is located at a higher elevation than the rest of the park.
The proposed addition will be added to the north side of the existing
administration building at the northwest corner of the parking lot. The existing
building is a single story wood framed structure with exterior wood siding.
Currently the location of the proposed addition is a grassy area with assorted
shrubs and trees. The surrounding area has been developed with sidewalks,
grassy areas and other buildings.
PROPOSED CONSTRUCTION
The proposed office addition will be a one story, wood -frame structure with
exterior wood siding. It will be added to the north side of the existing building and
will include a small ticket office on the east side. At this time the proposed
addition is not expected to have a basement. We have assumed for our analysis
the ground floor of the building will be constructed at the same elevation as the
ground floor of the existing building. We understand that the maximum wall loads
are expected to be 800 pounds per linear foot of wall and the maximum column
loads will be 7 kips. The building may have either a slab -on -grade floor or a
structural floor over a crawl space.
INVESTIGATION
Our field investigation was drilling two borings, TH-1 and TH-2, to 20 feet
and 35 feet deep respectively, in the area of the proposed addition. Locations of
our exploratory borings are shown on Figure 1, attached. The borings were
advanced using 4-inch diameter continuous flight power auger and a truck -
CITY OF FORT COLLINS OPERATION SERVICES
ADDITION TO ADMINISTRATION BUILDING 2
THE FARM AT LEE MARTINEZ PARK
CTL I T PROJECT NO. FC03527-125
IF
mounted rig. Drive samples were taken at intervals as the borings were advanced
with a California drive sampler. Summary logs of our borings are on Figure 2,
attached.
The samples were returned to our laboratory for testing. The samples were
classified by a geotechnicai engineer. Samples were selected and tested for
moisture content, dry density, swell/consolidation and water-soluble sulfates.
Laboratory test results are shown on Figure 3 and are summarized in Table I,
attached.
SUBSURFACE
We drilled two borings for the proposed addition. One boring (TH-1)
penetrated 4.5 feet of loose to medium dense, clayey sands over 6 feet of dense,
gravelly sands underlain by hard to very hard, claystone bedrock at 10.5 feet. The
second boring (TH-2) penetrated 3 feet of medium dense, clayey sands over 4 feet
of stiff, sandy clays over 2.5 feet of dense, gravelly sands over 2.5 feet of firm,
claystone bedrock underlain by very hard, claystone bedrock at 12 feet. The
bedrock was harder at depth. Ground water was not encountered when the
borings were drilled.
FOUNDATIONS
We have considered several type foundations for founding the office
addition, including footings bearing on the natural ground and straight -shaft
drilled piers into the claystone bedrock. In our opinion, spread footings are a
feasible foundation alternative and considerably less costly than piers. For this
reason we have not discussed straight -shaft drilled piers further in this report.
We can provide geotechnicai design criteria for straight -shaft drilled piers, if
requested. We recommend the following criteria for the design of spread
footings.
CITY OF FORT COLLINS OPERATION SERVICES
ADDITION TO ADMINISTRATION BUILDING 3
THE FARM AT LEE MARTINEZ PARK
CTL I T PROJECT NO. FC03527-125
IF
1. Footings bearing on undisturbed natural soils. Where soil is
loosened during excavation it should be removed and replaced with
engineered fill constructed of on -site soils or similar off -site soils,
that have a maximum size of 4 inches and that is placed in 8-inch
maximum loose lifts at 2 percent below to 2 percent above optimum
moisture content and compacted to at least 95 percent of standard
maximum dry density (ASTM D 698).
2. Footings bearing on the natural soils and/or engineered fill can be
designed for a maximum soil bearing pressure of 2,500 psf.
3. Footings should have a minimum width of at least 16 inches.
Foundations for isolated columns should have minimum dimensions
of 20 inches by 20 inches. Larger sizes may be required depending
on load and the structural system used.
4. Exterior footings should be protected from frost action. We believe
30 inches of frost cover is appropriate for this site.
5. Foundation walls for continuous footings should be well reinforced
both top and bottom. We recommend the amount of steel equivalent
to that required for a simply supported span of 10 feet. The soil
bearing pressure can be increased 30 percent for short duration live
loads such as wind loads.
6. Completed footing excavations should be inspected by a
representative of our firm to confirm that the soils are as we
anticipated from our borings. Occasional loose soils may be found
in foundation excavations. If this occurs, we recommend the loose
soils be treated as discussed in Item 1 above.
SLAB -ON -GRADE FLOOR
We have assumed that the finished ground floor elevation will be the same
as the ground floor elevation of the existing building. If a slab -on -grade floor is
selected, it will likely be necessary to place engineered fill inside the foundation
walls to achieve the desired subgrade elevation.
In our opinion, the on -site soils or similar non -expansive off -site soils free
of organic matter or other deleterious materials can be used to construct the
engineered fill under the floor. Engineered fill under the addition floor
constructed of the on -site soils or similar off -site soils should have a maximum
CITY OF FORT COLLINS OPERATION SERVICES
ADDITION TO ADMINISTRATION BUILDING
THE FARM AT LEE MARTINEZ PARK 4
CTL I T PROJECT NO. FC03527.125
Ir
size of 4 inches and should be placed in 8-inch maximum loose lifts at 2 percent
below to 2 percent above optimum moisture content and compacted to at least 95
percent of standard maximum dry density (ASTM D 698). Prior to placing fill, all
vegetation should be cleared from the surface of the natural ground. We suggest
the following recommendations for slab -on -grade, ground floor construction:
1. Slabs should be separated from exterior walls and interior bearing
members with a slip joint that allows free vertical movement of the
slab. Utilities, which pass through the slab, should be isolated from
the slab. Interior partitions should be designed to prevent the
transmission of slab movement to the building frame and interior
walls.
2. A vapor retarder can be placed under the slab -on -grade floor. If the
floor slab is placed directly on the ground, we recommend a plastic
sheet on the ground and the vapor retarder on the plastic sheet with
the concrete placed on top of the vapor retarder. If a capillary rise
"break" is desired we recommend a plastic sheet on the ground, 4-
inch thick free -draining, reasonably well -graded sand or sand and
gravel on the plastic sheet, the vapor retarder on the sand or sand
and gravel with the concrete placed on top of the vapor retarder.
3. Exterior concrete flatwork should be separated from the building.
This concrete should be reinforced to function independent of the
building. Movement of exterior slabs should not be transmitted to
the foundations. Frequent control joints should be provided in the
slab to reduce problems associated with shrinkage. The American
Concrete Institute (ACI) recommendations should be followed.
STRUCTURAL FLOOR
If a structural floor is used over a crawl space, there are design and
construction issues, such as ventilation and lateral loads, that must be
considered.
Crawl space walls should be designed for lateral earth pressures. Many
factors affect the value of the design lateral earth pressure. These factors include,
but are not limited to, the type, compaction, slope and drainage of the backfill, and
the rigidity of the wall against rotation and deflection. For a very rigid wall where
negligible or very little deflection will occur, an "at -rest" lateral earth pressure
CITY OF FORT COLLINS OPERATION SERVICES
ADDITION TO ADMINISTRATION BUILDING 5
THE FARM AT LEE MARTINEZ PARK
CTL I T PROJECT NO. FC03527-125
Ir
should be used in design. For walls that can deflect or rotate 0.5 to 1 percent of
the wall height (depending upon the backfill types), lower "active" lateral earth
pressures are appropriate. Our experience indicates basement walls can deflect
or rotate slightly under normal design loads, and that this deflection results in
satisfactory wall performance. Thus, the earth pressure on the walls will likely be
between the "active" and "at -rest" conditions.
If on -site soils are used as backfill and the backfill is not saturated, we
recommend design of basement walls for the primary care building using an
equivalent fluid density of at least 45 pcf. These values assume deflection; some
minor cracking of walls may occur. If very little wall deflection is desired, higher
design density may be appropriate. Recent experience indicates for similar
subsoils, most basement walls designed with 45 pcf to 50 pcf equivalent fluid
density have performed satisfactorily. We understand recent designs and some
local building code changes have resulted in enhancements including two-way
reinforcement (a mat of steel) in basement walls or other measures, such as
thicker walls. We believe the recent enhancements will improve foundation wall
performance compared to historical practice. The structural engineer should also
consider site -specific grade restrictions and the effects of large openings on the
behavior of the walls.
The required air space depends on the materials used to construct the
floor. Building codes require a clear space of 18 inches above exposed earth if
untreated wood floor components are used. Where other floor support materials
are used, a minimum clear space of 6 inches should be maintained. This
minimum clear space should be maintained between any point on the underside
of the floor system (including beams and floor drain traps) and the surface of the
exposed earth. Utility connections, including water, gas, air duct and exhaust
stack connections to floor supported appliances, should be capable of absorbing
some deflection of the floor. Plumbing that passes through the floor should
ideally be hung from the underside of the structural floor and not laid on the
bottom of the excavation. This configuration may not be achievable for some
CITY OF FORT COLLINS OPERATION SERVICES
ADDITION TO ADMINISTRATION BUILDING 6
THE FARM AT LEE MARTINEZ PARK
CTL I T PROJECT NO. FC03527-125
parts of the installation. It is prudent to maintain the minimum clear space below
all plumbing lines
Control of humidity in crawl spaces is Important for indoor air quality and
performance of wood floor systems. Our scope for this project did not include
providing recommendations to control humidity. Nevertheless, since we are
involved in this type of work we feel we should comment. We believe the best
current practices to control humidity involve the use of a vapor retarder (10 mil
minimum), placed on the exposed soils below accessible sub -floor areas. The
vapor retarder should be sealed at joints and attached to concrete foundation
elements. If desired, we can provide designs for ventilation systems that can be
installed in association with a vapor retarder, to improve control of humidity in
crawl space areas.
WATER SOLUBLE SULFATES
We measured water-soluble sulfate concentrations in a sample of soil from
the building area of 0.02 percent (Table 1). According to the Portland Cement
Association criteria, Type I cement can be used in concrete exposed to the
foundation soils.
SURFACE DRAINAGE
Wetting of foundation soils always causes some degree of volume change
in soils and should be prevented during and after construction. The risk of
wetting the foundation soils can be reduced by planned and maintained surface
grading. We recommend the following precautions be observed during
construction, and that they be maintained at all times after completion of the
addition:
1. Prevent surface water from flowing into footing excavations during
construction.
CITY OF FORT COLLINS OPERATION SERVICES
ADDITION TO ADMINISTRATION BUILDING 7
THE FARM AT LEE MARTINEZ PARK
CTL I T PROJECT NO. PC03527.126
U
2. The ground surface surrounding the exterior of the addition should
be sloped to drain away from the addition in all directions.
3. Backfill around foundation walls should be on -site soils placed in
thin lifts, moisture conditioned to 2 percent below to 2 percent
above optimum moisture content and compacted to at least 90
percent of standard maximum dry density (ASTM D 698). All backfili
that supports pavement or sidewalks should be compacted to at
least 95 percent of standard Proctor maximum dry density (ASTM D
698).
4. Roof downspouts and drains should discharge well beyond the
limits of all backfill. We recommend providing splash blocks at all
downspout locations. Concrete swales can be used to convey
concentrated water flows through paved areas to drains and gutters.
LIMITATIONS
Although our borings were spaced to obtain a reasonably accurate picture
of subsurface conditions, variations in the subsoils not indicated in our borings
are always possible. We should inspect footing excavations to confirm soils are
as we anticipated from our borings
This report was prepared from data developed during our field exploration,
laboratory testing, engineering analysis and experience with similar conditions.
The recommendations contained in this report were based upon our
understanding of the planned construction. If plans change or differ from the
assumptions presented herein, we should be contacted to review our
recommendations.
We believe this investigation was conducted in a manner consistent with
that level of skill and care ordinarily used by members of the profession currently
practicing under similar conditions in the locality of this project. No warranty,
express or implied, is made.
CITY OF FORT COLLINS OPERATION SERVICES
ADDITION TO ADMINISTRATION BUILDING 8
THE FARM AT LEE MARTINEZ PARK
CTL I T PROJECT NO. FC03527-125
2. Fit work tight to adjacent elements. Maintain integrity of wall, roof, ceiling or
floor constructions and finishes. Refinish surfaces to match adjacent finishes.
3. Minimize extent of necessary cutting and patching. Thoroughly explore
alternatives to cutting and patching.
4. Remove and replace defective and non -conforming work.
5. Provide openings in elements of the work for mechanical and electrical
penetrations, work of other trades or Subcontractors.
B. Cutting, patching and fitting shall be performed by personnel or subcontractors skilled
in the particular trades or Sections of the work involved.
C. Perform cutting by methods which will prevent damage to other portions of the work
and provide proper surfaces to receive installation of repair and new work.
D. Perform fitting and adjusting of products to provide finished installation complying with
the specified tolerances and finishes.
END OF SECTION
0237.05 01045-2
T
If we can be of further service in discussing the contents of this report or in
the analysis of the addition from the geotechnical point -of -view, please call.
CTL I THOMPSON, INC.
John J Boulden
Staff Engineer
Frank J. Holliday, PE, CCE
Senior Consultant
JJB:FJH:bIy
(3 copies sent)
2 cc: Aller Lingle Architects, PC
712 Whalers Way
Fort Collins, Colorado 80525
Attn.: Mr. Chris Freeland
1 cc: KL & A
4412 West Eisenhower Boulevard
Suite 200
Loveland, Colorado 80537
Attn.: Mr. Eric Moe
CITY OF FORT COLLINS OPERATION SERVICES
ADDITION TO ADMINISTRATION BUILDING 9
THE FARM AT LEE MARTINEZ PARK
CTL I T PROJECT NO. FC03527-125
GATE
SCALE: 1"=10'
SIDEWALK
W TH•1
U
W O
LL
Z
W
d
0
O
GRASSY AREA
EXISTING BUILDING CONSIDERED IN
THIS INVESTIGATION
LEGEND
TH -1 INDICATES APPROXIMATE LOCATION
O OF EXPLORATORY BORING
CITY OF FORT COLLINS
OFFICE ADDITION TO BUILDING
CTL I T PROJECT NO, FC-03527-125
VICINITY MAP
(FORT COLLINS AREA)
NO SCALE
TH -2 _y
OG
D
r
COVERED
ENTRANCE
Location of Exploratory Borings
S
FIGURE 1
TH-1 TH-2
El. 99 El. 98.5
100
100
7/12
11112
15112
8/12
00,
90
90
w
50/12
29112
w
LL
LL
z
z
a50/8
50/6
w
I>1J
J
LU
80
80
J
w
5016
5016
70 0 70
5015
.E
LEGEND:
QSAND, CLAYEY, LOOSE TO MEDIUM DENSE, MOIST, BROWN (SC)
Fl
CLAY, SANDY, STIFF, MOIST, BROWN (CL)
I GRAVEL, SANDY, MEDIUM DENSE TO DENSE, MOIST TO VERY MOIST, BROWN (SP-GP)
CLAYSTONE, FIRM, MOIST, OLIVE (CL) (BEDROCK)
® CLAYSTONE, HARD, MOIST, GREY (BEDROCK)
DRIVE SAMPLE. THE SYMBOL 7112 INDICATES 7 BLOWS OF A 140-POUND HAMMER
FALLING 30 INCHES WERE REQUIRED TO DRIVE A 2.54NCH O.D. SAMPLER 12 INCHES.
NOTES:
1. THE BORINGS WERE DRILLED ON JUNE 23,2005 , USING 4-INCH DIAMETER
CONTINUOUS -FLIGHT AUGER AND A TRUCK -MOUNTED DRILL RIG.
2. THESE LOGS ARE SUBJECT TO THE EXPLANATIONS, LIMITATIONS AND CONCLUSIONS IN
THIS REPORT.
CITY OF FORT COLLINS SUMMARY LOGS OF EXPLORATORY BORINGS
OFFICE ADDITION TO BUILDING
CTL I T PROJECT NO. FCM27-125 FIGURE 2
7
6
5
4
3
2
1
0
-1
-2
a
z
O
N
z
4
a
X -5
W
a
z
O
W
W
S -7
0
U
-8
DUE
0.1 1.0 10 100
APPLIED PRESSURE - KSF
Sample of SAND, CLAYEY (SC) SAMPLE DRY UNIT WEIGHT= 107 PCF
From TH-2- AT 4 FEET SAMPLE MOISTURE CONTENT= 19.4 %
PROJECT NO. FC03527-125
Swell Consolidation
Test Results FIG.3
TABLE
SUMMARY OF LABORATORY TEST RESULTS TV
NATURAL
SWELL TEST DATA SOLUBLE
LOT DEPTH
NATURAL
DRY
SWELL APPLIED SWELL SULFATES
SOIL TYPE
MOISTUR
DENSITY
PRESSURE PRESSURE
FEET
(%}
PCF
%) PSF PSF
TH-2 4
19.4
107
-1.0
1,000
n/a
0.020
ISAND, CLAYEY SC
CTL I T PROJECT NO. FC03527-125 Page 1 of 1
SECTION 01070
ABBREVIATIONS
PART1 GENERAL
1.01 DEFINITIONS
A. Wherever used in these Specifications, the following abbreviations shall have the
meanings indicated:
AAMA
American Architectural Manufacturers Association
AASHTO
American Association of State Highway & Transportation Officials
ADA
Americans with Disabilities Act
AIA
American Institute of Architects
AISC
American Institute of Steel Construction
AISI
American Iron and Steel Institute
AITC
American Institute of Timber Construction
ANSI
American National Standards Institute
ASME
American Society of Mechanical Engineers
ASTM
American Society for Testing and Materials
AWI
Architectural Woodwork Institute
AWS
American Welding Society
AWWA
American Water Works Association
CDOT
Colorado Department of Transportation
CISPI
Cast Iron Soil Pipe Institute
CRSI
Concrete Reinforcing Steel Institute
CS
Commercial Standard
EEI
Edison Electric Institute
FS
Federal Specifications
IBBM
Iron Body, Bronze Mounted
IBC
International Building Code
IEEE
Institute of Electrical and Electronics Engineers
IRC
International Residential Building Code
ISA
Institute Society of America
IGCC
Insulating Glass Certification Council
LEED
Leadership in Energy and Environmental Design
MBMA
Metal Building Manufacturer's Association
MCC
Motor Control Center
MCIP
Motor Control Instrument Panel
MSL
Mean Sea Level
MSS
Manufacturer's Standardization Society of the Valves and Fittings
NBS
National Bureau of Standards
NEC
National Electric Code
NEMA
National Electrical Manufacturers Association
NFRC
National Fenestration Rating Council
NFoPA
National Forest Products Association
NPT
National Pipe Thread
NRS
Non -Rising Stem
NWMA
National Woodwork Manufacturer's Association
PIMA
Polyisocyanurate Insulation Manufacturer's Association
RPM
Revolutions per minute
01070 - 1
0237.07
SDI Steel Deck Institute
SJI Steel Joist Institute
SMACNA Sheet Metal and Air Conditioning Contractors National Association, Inc.
SPRI Single -Ply Roofing Institute
TCA Tile Council of America
UBC Uniform Building Code
UCBC Uniform Code for Building Conservation
UFC Uniform Fire Code
UL Underwriter's Laboratories
UMC Uniform Mechanical Code
UPC Uniform Plumbing Code
END OF SECTION