Change Order Form
$ngIneering Depernoent
PROJECT TITLE: 2005 Street Maintenance Program
PROJECT NUMBER: 320200 (Concrete Project Phase II - Bid #5847)
CONTRACTOR: Vogel Concrete (PO#5501541)
CHANGE ORDER NUMBER: 7
n preparing ge orders show order as separate num ere paragrap s
c anin following:
1. Reason for change. 2. Description of change.
3., Change in Contract cost. 4. Change in contract time,
1,&2. See attached invoice for details
3. The contract cost will increase by $12,619.60
4. There is no change in contract time.
ORIGINAL CONTRACT COST $1,379,095,11
TOTAL APPROVED CHANGE ORDERS $132,594.48
TOTAL PENDING CHANGE ORDERS $51,959.40
TOTAL THIS CHANGE ORDER $12,619.80
TOTAL % OF THIS CHANGE ORDER 0.92%
TOTAL G.O. % OF ORIGINAL CONTRACT 14.30°/s
ADJUSTED CONTRACT COST 51,576,288.79
ACCEPTED BY: ��''-'"� v DATE: �� d a ~
REVIEWED BY:
ACCEPTED BY;
APPROVED BY:
APPROVED BY:
cc: Accounting
Purchasing
Contractor
Project File
TE; `� }
(Project Manager - Engineering)
DATE: 11) n • Inr
DATE;
(Purchasing Agent over $30,000)
Engineering Department • 291 North College Avenue, P.O, i3ox 580 • Fort Collins, CO $0522-0580 • (970) 221-6605
OCT-20-2005 THU 01:55 PM CFC ENG. FAX NO. 9702216378 P. 06
2005 Concrete Project - Phase II
Vogel Concrete Bid No. 5847
Change Order No:7
Date: 1011112005
J. Reason For Change:
a. Caulking from the 2004 project was Inadvertently overlooked last year.
b. Additional aggregate base course and patching is required to complete the Work.
2. Description 0fChange:
a. Increase the contract quantity for caulking from the 2004 project to be paid In 2005.
b. Increase the contract quantity for bath patching and aggregate base course.
3. Change In Contract Amount:
Item
Qty
Unit
Unit Cost
Total Cost
a. 608.34 Expansion & Caulking
1175
LF
$ 4.14
S
4,864,50
b. 403.50 Temporary Patching
33
TON
$ 155.10
$
5,118.30
304.07 Aggregate Base Course
100
TON
$ 26.37
$
2,637.00
TOTAL CHANGE IN CONTRACT AMOUNT
$
12,619.90
4. Change In Contract Tlme
a. There Is no changa In contract time.
TOTAL CHANGE IN CONTRACT TIME
0 Days