HomeMy WebLinkAboutRESPONSE - BID - 5929 CSU TRANSIT CENTERSECTION 00300
BID FORM
PROJECT:5929 City of Fort Collins and Colorado State University Transit Center
Place Ft. Collins
Date 8/23 05
1. In compliance with your Invitation to Bid dated 7/ 21/05 , and
subject to all conditions thereof, the undersigned
a (Corporation, Limited Liability Company, Partnership, Joint Venture,
or Sole Proprietor)" authorized to do business in the State of Colorado
hereby proposes to furnish and do everything required by the Contract
Documents to which this refers for the construction of all items listed
on the following Bid Schedule or Bid Schedules.
2. The undersigned Bidder does hereby declare and stipulate that this
proposal is made in good faith, without collusion or connection with any
other person or persons Bidding for the same Work, and that it is made in
pursuance of and subject to all the terms and conditions of the
Invitation to Bid and Instructions to Bidders, the Agreement, the
detailed Specifications, and the Drawings pertaining to the Work to be
done, all of which have been examined by the undersigned.
3. Accompanying this Bid is a certified or cashier's check or standard Bid
bond in the sum of 5% bid amount ($ )
in accordance with the Invitation To Bid and Instructions to Bidders.
4. The undersigned Bidder agrees to execute the Agreement and a Performance
Bond and a Payment Bond for the amount of the total of this Bid within
fifteen (15) calendar days from the date when the written notice of the
award of the contract is delivered to him at the address given on this
Bid. The name and address of the corporate surety with which the Bidder
proposes to furnish the specified performance and payment bonds is as
follows: EMC Insurance
5. All the various phases of Work enumerated in the Contract Documents with
their individual jobs and overhead, whether specifically mentioned,
included by implication or appurtenant thereto, are to be performed by
the CONTRACTOR under one of the items listed in the Bid Schedule,
irrespective of whether it is named in said list.
6. Payment for Work performed will be in accordance with the Bid Schedule or
Bid Schedules subject to changes as provided in the Contract Documents.
7. The undersigned Bidder hereby acknowledges receipt of Addenda No.
1 through % _.
COLORADO DEPARTMENT OFTRANSPORTATION Project
UNDERUTILIZED DBE GOOD FAITH EFFORT Location
DOCUMENTATION
Date
The Contractor who is the apparent low bidder on a CDOT construction project and has failed to meet the Underutilized DBE (l
contract goals shall use this form to document good faith efforts made to date by said Contractor to attempt to meet these goals.
FAILURE TO FULLY COMPLETE THIS FORM MAY RESULT IN REJECTION OF THE BID.
Each portion of this form is to be addressed in the space provided, or on supplemental sheets. Attach supporting documentation as
required. This completed form and required attachments are to be submitted to the Business Programs Office in the Center for Equal
Opportunity prior to 4:00 p.m. on the day after the day bids are opened. This form may be submitted by FAX (303-757-9019) with an
original copy to follow. An extension may be granted by the DBE Liaison. Solely at its discretion, CDOT may request additional
information and accept additional UDBE participation at any time and prior to the final decision concerning Good Faith Efforts.
I. List sufficient bid items (including portions of bid items) identified as subcontract work to be performed by UDBEs to achieve the
established UDBE participation goal. Indicate the total percentage of work identified for UDBE participation. The total percentage of
subcontract items identified for UDBE participation must equal or exceed the percentage goal established by CDOT.
II. For each subcontract item identified, contact by mail, FAX and/or telephone a minimum of two currently CDOT-certified UDBEs whose
work and function codes match the type of work being solicited. For projects in areas of the state where there are more than two UDBEs
capable of performing identified subcontract items, contact at least two thirds of those UDBEs. If soliciting by telephone, provide a
telephone log of calls, including topic of discussion, date, time, name of person contacted, and the response received. If soliciting by
mail, provide copies of letters to UDBEs and theirresponses. Letters and FAXes must specifically identify the project, the items to be
subcontracted, and the bid date. Letters and "FAXes must provide an address and phone number where specific quantities or details will
be available to bidders. The Contractor shall provide sufficient time to allow the UDBEs to participate effectively in the bidding process.
Submit a detailed explanation addressing failure to provide any of the above.
Original -Business Programs Office, Copy -Contractor OVER Previous editions are obsolete and may not be used CDOT Form 0718 3199
III. List all UDBE and non-UDBE bidders, bid dollar amounts for each bid item, and the name of the successful bidder. Describe how bid
items were broken down to increase opportunities for specific UDBE bidders. If the UDBE bids were rejected, give reasons for each
case. Cost alone may not be adequate justification for failure to use a UDBE bid. If the work is to be counted as a potential UDBE
subcontract item, the Contractor cannot elect to perform that work itself when a UDBE bid is competitive or only UDBE bids are received.
When a non-UDBE bid is significantly lower than a UDBE bid, the Contractor may choose to perform the item itself. Whether a bid is
"competitive" or "significantly lower" will be determined by CDOT. Provide a detailed explanation for failure to provide any of the above.
IV. The efforts required herein are not exhaustive or exclusive. Other factors or types of efforts may be relevant in appropriate cases. In
determining whether Good Faith Efforts have been made, the quantity and intensity of the efforts made as well as kinds of efforts made
may be considered. List any additional efforts to increase UDBE contract participation, such as requesting subcontractors to assist with
providing UDBE participation. Note the results of such efforts.
SECTION 00420
STATEMENT OF BIDDER'S QUALIFICATIONS
Ail questions must be answered and the data giver, must be clear and
comprehensive. This statement must be notarized. If necessary, questions may
be answered on separate attached sheets. The Bidder may submit any additional
information he desires.
1. Name of Bidder: Growling Bear Co., (Inc.)
2. Permanent main office address
3. When organized: May 1974
2330 4th Ave. Greeley, CO 80631
4. If a corporation, where incorporated: Greeley, CO
5. How many years have you been engaged in the contracting business
under your present firm or trade name? 31 Yrs.
6. Contracts on hand: (Schedule these, show_ng the amount of each
contract and the appropriate anticipated dates of completion.)
See Attached current proiects list
7. General character of Work performed by your company:
Demolition,Concrete, Casework
8. Have you ever failed to complete any Work awarded to you? NO
If so, where and why?
9. Have your ever defaulted on a contract? NO
If so, where and why?
10. Are you debarred by any government agency? NO
If yes list agency name.
7/96
Section 00420 Page 1
11. List the more important projects recently completed by your company,
stating the approximate cost of each, and the month and year completed,
location and type of construction.
See Past projects list
12. List your major equipment available for this contract.
Front end loader, Genie 60 ft lift, Skytrak
13. Experience in construction Work similar in importance to this
project:
See Past projects
14. Background and experience of the principal members of your organization,
including officers:
See Resumes
Kelp
Credit available: $ '500),000
Bank reference:Union Colony Bank, Mike Enarav - (970)336-6082
Wiil you, upon request, fill out a detailed financial statement and
furnish any other information that may be required by the OWNER?
Are you licensed as a General
If yes, in what city, county
class, license and numbers?
CONTRACTOR?
and state?
Yes
Ft. Collins, CO What
Do you anticipate subcontracting
Contract? Yes
If yes, what percent of total contract? 95%
and to whom?
Work under this
Are any lawsuits pending against you or your firm at this time? NO
IF yes, DETAIL
7/96 Section 00420 Page 2
21. What are the limits of your public liability? DETAIL
3,000,000
what company? EMC Insurance
22. What are your company's bonding limitations? $25,000,000
23. The undersigned hereby authorizes and requests any person, firm or
corporation to furnish any information requested by the OWNER in
verification of the recital comprising this Statement of Bidder's
Qualifications.
Dated at this day of 200
Growling Bear Co.(.Inc)
Name of B' der
By:
evin S i onaka
Title: President
State of Colorado
)
County of Weld
Kevin Shironaka being duly sworn deposes and says that he
is President of Growling Bear Cn_,(Tnc-_}and that
(name of organization)
the answers to the foregoing questions and all statements therein contained
are true and correct.
Subscribed and sworn to before me this day of
�- 2005.
'
Notary Public �� �'•.••O7•
My commission expires
fi
i
10111�00,`�
7/96 Section 00420 Page 3
SECTION 00430
SCHEDULE OF SUBCONTRACTORS
List all subcontractors for the work items listed below and all subcontractors
performing over 150 of the contract.
ITEM
SUBCONTRACTOR
7/96 Section 00430 Page 1
Growling Bear Co. Inc.
Kevin Shironaka
Owner / President
Equal Employment Opportunity Officer
Education:
1970 University of Northern Colorado
Bachelor of Science in Business Finance
Greeley, CO
Work History:
1974-Present Growling Bear Co. Inc. - Greeley, CO
1968-1974 Everitt Lumber Company - Greeley, CO
Purchasing Agent, Cost Accountant
Construction Salesman
Manager - Fencing Dept.
Kevin Shironaka, a Colorado native and long-time Weld County resident, born in
Denver and raised in Ordway, graduated from University of Northern Colorado with a
Bachelor of Science Degree in Business Finance. He originally founded and has been
the owner and president of Growling Bear Co. Inc. since its inception in 1974. Over the
years, Kevin expanded his general contracting construction business to include not only
Colorado but other states as well, but has chosen to concentrate his and the company's
efforts in the Colorado Front Range.....our "neighborhood".
Kevin not only has expert personal knowledge as to the management of the overall
company but also extensive field experience in the construction of the various projects
undertaken by Growling Bear. He has negotiated commercial projects and has been
the successful bidder on many other projects, both public and private, along the Front
Range from Cheyenne to Pueblo ranging in price from $50,000.00 to $8,000,000.00.
Kevin has been operating his business, hiring locals, and contracting with neighborhood
businesses for 30 years. Under his leadership, the company has grown from a few
employees to sometimes as many as 60 employees.
His long history and solid reputation in the construction arena has afforded Kevin the
ability to recruit the most experienced and capable construction team in Colorado and
he is continually expanding that team.
Growling Bear Co. Inc.
Gary Shironaka
Corporate Secretary/Senior Estimator/Project Manager
Education:
Colorado State University, Ft. Collins, CO
Bachelor of Science
Construction Management Degree
Greeley Central High School
Greeley, CO
OSHA 10 hour class
CPR and First Aid Training
Work History:
2000-Present Growling Bear Co. (Inc.), Greeley, CO
Estimator/Project Manager
Member, Building Trades Advisory Committee, Weld Board of
County Commissioners, 2001 through 2004
1996 -2000 Growling Bear Co.(Inc.) Greeley, CO
Carpenter, Assistant Project Manager
1994-1995 Growling Bear Co. (Inc.) - Greeley, CO
Carpenter
Owner/Architect References:
Ann Yates, Director
Colorado State University
970.491.4939
Toby Trijillo, Project Manager
WAPA US Dept. of Energy
970.461.7286
Cass Beitler, Project Manager
Colorado State University
970.491.0158
Ken Field, Architect
RB+B Architects
970.484.0117
Growling Bear Co., Inc.
Gary Shironaka, continued
Selected Projects:
Centennial Bank Restoration $ 5,754.00
Windsor, CO
CSU Podiums $ 17,495.00
Fort Collins, CO
New East Elementary School $ 8,034,433.00
Greeley, CO
Cheyenne Substation Modifications $ 596,306.00
Western Area Power Administration
Cheyenne, WY
Colorado State University Service Center Remodel $ 223,995.00
Fort Collins, CO
I" United Methodist Church, $ 663,000.00
Brighton, CO
Centennial Bank of the West $ 2,250,000.00
Windsor, CO
Centennial Bank of the West tenant finish $ 54,000.00
Windsor, CO
AT&T Regen Huts: Colorado, Wyoming, $ 4,572,000.00
Nebraska, UT
City of Greeley Various Projects $ 1,400,000.00
Greeley, CO
Growling Bear Co. Inc.
Curtis C. Naibauer
Vice President/Estimator/Project Manager
Education:
Aims Community College
General Education
Greeley, CO
Work History:
1995-Present Growling Bear Co. Inc. - Greeley, CO
Project Manager/Estimator
1990-1994 Thissen Construction Corp. - Greeley, CO
Chief Estimator/Project Manager
1983-1989 Growling Bear Co. Inc. - Greeley, CO
Project Manager/Estimator
Curtis has been with Growling Bear for 16 years and can provide a range of pre -
construction service that includes cost estimating, value engineering, scheduling,
budget updates, and project coordination.
Curtis would be responsible for working closely with the Project Architect to determine
the most cost effective method to accomplish the goals that the Owner has set for his
project.
Owner/Architect References:
Hope Cassidy, Director
Greeley Center for Independence
970.339.2444
Diane Norgren, Owner
Town of Platteville
970.785.2231
Robert Shreve, Architect
Robert Shreve Architects and Planners
970.346.0151
Bob Warren, Mayor
Town of Garden City
970.351.0041
I
CONTRACTOR
BY: Growling Bear Co., (Inc.)
2330 4th Ave.
ADDRESS: Greelev. CO 80631
10)353-6964
8. BID SCHEDULE: /
A. BASE BID (LUMP SUM)$
BASE BID IN WORDS-H,, _ ,j /-i; ILII„��A, ,_,( Dollars
B. ALTERNATES
$-J 2,11. Exterior stair canopy: ADD to base bid
$2. Skylights at entry vestibule: Use Stone in lieu of
stucco and plaza level new addition pending acceptable match:
7 ADD to base bid
� $ I�3. Provide roll down grilles @ plaza & lower level: ADD to base
bid
$,4. Use Stone in lieu of Stucco, and plaza level new addition
pending acceptable match: ADD to base bid
$ Interior electrical fixture upgrade: ADD to base bid
$6. Extend Elevator to upper floors and provide all upper level
renovation as noted: ADD to base bid
S_ $77. Electric door openers at handicapped restroom, Lower Level as
noted: ADD to base bid
$�y 8. Fire Main upgrade pending flow test report, as noted: ADD to
base bid
7
Curtis C. Naibauer, continued
Weld County Social Services — Addition $ 1,275,000.00
Greeley, CO
Q-Lube — New Construction $ 250,000.00
Greeley, CO
First National Bank of Johnstown — New Construction $ 876,800.00
Johnstown, CO
Union Pacific Railroad Depot — Remodel $ 195,700.00
Greeley, CO
Weld County Hazardous Waste Treatment $ 275,000.00
Center - Dacono, CO
Monfort Portions Office Addition $ 753,000.00
Greeley, CO
Hugh M. Woods Contractor Sales Addition $ 94,000.00
Greeley, CO
Bonell Good Samaritan Hospital Addition $ 177,000.00
Greeley, CO
Sharlyn Court Duplexes - New Construction $ 18500.00
Greeley, CO
Highland Daycare Center - New Construction $ 531,500.00
Ault, CO
Peterson AFB Building #845 Renovation $ 2,746,000.00
Peterson AFB, Colorado Springs, CO
Remodel of Inmate Space - Weld County Jail $ 1,800,000.00
& Communications Center, Greeley, CO
Island Grove Regional Treatment Center $ 1,100,000.00
Greeley, CO
Mary Blair Elementary Addition $ 1,400,000.00
Namaqua Elementary Addition $ 1,600,000.00
Curtis C. Naibauer, continued
UNC Frasier Hall Life Safety Upgrade $ 1,300,000.00
Greeley, CO
First Christ Church Addition $ 850,000.00
Greeley, CO
Northern Colorado Medical Center Addition $ 750,000.00
Poudre Valley Hospital Addition $ 950,000.00
Fort Collins, CO
Platteville Town Hall, Platteville, CO $ 600,000.00
Cameron Elementary School Addition $ 435,000.00
Greeley, CO
L
Growling Bear Co. Inc.
Donald D. Myers
Superintendent
Education:
Work History:
1998-Present
Walsenburg High School, CO
High School Diploma
Growling Bear Co. Inc. - Greeley, CO
Superintendent
1978-1998 Whitlock Construction
Superintendent (also managed satellite office in
Montrose, Colorado for 3 years
1976-1978 University of Southern Colorado
Superintendent
1971-1976 Whitlock Construction
Carpenter Foreman
Don has worked commercial construction for over 30 years. In that time he has
amassed a long resume of completed projects including medical buildings, school
additions/renovations, banks, assisted living facilities, big box stores, and multi -family
projects.
Owner/Architect References:
B.J Dean, Director
Island Grove Treatment Center
970.356.6664
Steve Seefeld, Project Manager
City of Fort Collins
970.221.6227
Toby Trijillo, Project Manager
WAPA, US Department of Energy
970.461.7286
Shaun Moscrip, Architect
Aller-Lingle Architects
970.223.1820
"A,
Growling Bear Co. Inc.
Don Myers, continued
Selected Projects:
CU Renovation to Behavioral Genetics $ 375,610.00
Tenant finish 5,00 SF space
University of Colorado Boulder
Newsom Hall Exterior Fagade $ 116,735.00
Siding and Concrete Restoration
Colorado State University
Lincoln Center Roof Replacement/ $ 332,226.00
HVAC Upgrade
Ft. Collins, CO
Cheyenne Substation Modifications $ 596,306.00
Cheyenne, WY
Island Grove Treatment Center $ 1,682,726.00
Outpatient Clinic
Greeley, CO
Warren Air Force Base Youth Center $1,150,000.00
New Construction, Cheyenne, WY
Ft. Lupton Community Center $ 1,295,861.00
Ft. Lupton, CO
Centennial Bank of the West $ 951,978.00
Ft. Collins, CO.
Boone NGLN AT &T $ 975,390.00
Boone, CO
The Chateau at Sharmar Village $ 3,500,000.00
Pueblo, CO
Willy School 10,OOOsf K-12 School $ 800,000.00
REI-J Schools — Montrose CO $12,000,000.00
Various Schools from 20,OOOsf — 40,000 sf
Hoehme School Addition & Gymnasium $ 2,800,000.00
Growling Bear Co. Inc.
Don Myers, continued
Home Base Stores, New Construction $ 6,000,000.00
Highlands Ranch, CO
Centennial High School, Ball Fields $ 1,000,000.00
Home Base, (new construction) $ 4,500,000.00
Track Facility- All new construction
Colorado Springs, CO
New laundry and Kitchen $ 5,000,000.00
Federal Prison Facility
Canyon City, CO
Church Addition- Montrose, CO $ 2,500,000.00
Hospital Remodel- Montrose, CO $ 1,500,000.00
Wal-Mart Addition- Montrose, CO $ 1,500,000.00
Wal-Mart- Gunnison, CO $ 9,000,000.00
Fire Station, Peterson Air Base $ 1,500,000.00
Colorado Springs, CO
Motor Pool & Resurfacing $10,000,000.00
Ft. Carson, CO
Dining Room & Kitchen Renovation, Norad $ 3,000,000.00
Wal-Mart New Construction $2,500,000.00
North Pueblo, CO
Wal-Mart New Construction $2,500,000.00
South Pueblo, CO
Wilson Almont Mortuary- Canon City, $ 1,200,000.00
Freed Middle School Addition and Kitchen $ 1,300,000.00
Colombian Middle School 2 story Addition $ 1,200,000.00
South Park Elementary Addition $ 1,500,000.00
Monte Vista Schools Remodels/Additions $5,000,000.00
Growling Bear Co. Inc.
Don Myers, continued
Summitville Gold Mine, $ 1,000,000.00
Summitville CO
Abex Rail Mill Addition & Roofing $ 5,000,000.00
Comanche Power Plant $ 3,000,000.00
(metal buildings)
Motor Inn & Restaurant, $ 1,500,000.00
Trinidad CO
Lathrop Rare Boys Ranch Renovation $ 4,000,000.00
Elementary School Addition, $ 1,900,000.00
La Junta, CO
Astoca Apartments, 10-stories $ 6,500,000.00
Pueblo, CO
Growling Bear Co. Inc.
Glen A. Hoopes
Superintendent
Education:
Paradise High School
Paradise, KS
Inventory Supply School,
Warren AFB, WY, June — Aug. 1956
United States Air Force
Airman First Class 1956 —1960
Plan Reading and General Estimating Course
Work History:
1997 — Present Growling Bear Co. Inc. - Greeley, CO
Superintendent
1989-1997 Clark Construction Co., Loveland, CO
Superintendent
1987-1989 Professional Design Builders, Loveland, CO
Superintendent
1978-1987 Clark Construction Co., Loveland, CO
Superintendent
1974-1978 Professional Design Builders, Loveland, CO
Vice-President/Owner
1968-1974 Clark Construction Co., Loveland, CO
Superintendent and Foreman
1966 — 1968 Beisner Construction, Loveland, CO
Carpenter
Growling Bear Co. Inc.
Glen Hoopes, continued
References:
Cass Beitler Joe Ashcraft
CSU Project Manager Morganti Group Architects
970.491.158 970.667.4000
Mike Rush Ken Field
Aller Lingle Architects RB+B Architects
970.223.1820 970.484.0117
Selected Projects:
CSU Chemistry Remodel $264,868.00
Fort Collins, CO
CSU Corbett Hall Dining Center $ 675,324.00
Fort Collins, CO
CSU Stallion Lab $ 292,911.00
Fort Collins, CO
CSU Equine Lab $ 364,901.00
Fort Collins, CO
Stephens Center, Assisted Living Facility $ 822,000.00
Greeley, CO
New East Elementary School $ 8,034,433.00
Greeley, CO
Brentwood Middle School, gym addition $ 995,701.00
Greeley, CO
McGraw Elementary School $ 8,000,000.00
Fort Collins, CO
Fireside Elementary School $ 5,000,000.00
Louisville, CO
Rock Creek Elementary School $ 30,000,000.00
Superior, CO
Growling Bear Co. Inc.
Glen Hoopes, continued
Southwest Elementary School $4,000,000.00
Fort Collins, CO
Bennett Elementary School $2,000,000.00
Fort Collins, CO
Church of the Latter Day Saints Several Million
Greeley, Fort Collins, Longmont,
Littleton, and Aurora, CO
Quick Lube (New Construction) $ 265,000.00
Evans, CO
Bonnell Good Samaritan Center Remodel $ 295,000.00
Greeley, CO
John Evans Middle School (Remodel) $ 250,000.00
Greeley, CO
Shopko Stores
Fort Collins, CO $ 2,500,000.00
Longmont, CO $ 2,500,000.00
North Range Behavioral Health Center $ 1,017,000.00
Greeley, CO
Boulder Ranger Station $ 1,135,000.00
Boulder, CO
Center for Independence $ 504,680.00
Greeley, CO
World Savings Bank $ 835,333.00
Fort Collins, CO
Projects in Progress as of 07/19/2005
Growling Bear Co., Inc., 2330 4th Avenue, Greeley, CO 80631 Phone: (970) 353-6964 Fax: (970) 353-6974 page 1
WORK ON HAND % Work
Contract Scheduled W/Own
Project/Location/Description Owner Architect/Engineer Amount Start Completion Forces
Johnstown Station
Johnstown Station Development Group
Wyatt & Associates
$ 1,895,578.00 Apr'05 Oct'05 25%
Johnstown, CO
19563 East Main Street #202
1865 S. Pearl Street
Construction of a 2 story core and shell retail
Parker, CO 80138
Denver, CO 80210
building. 32,000 SF. Extensive site work,
Pete Wells, Larry Graves
Jeff Anderson, Architect
structural steel framing and cmu veneer
303.756.5585
303.698.1717
Walter Self Senior Housing
Boulder County Housing Authority
Manning Architects, Inc.
$ 1,405,303.00 June'05 Jan'06 15%
Lyons, CO
3182 N. Broadway
2020 20th Street
Costruction of 2 new 6 plex houses and 1
Boulder, CO 80302
boulder, CO 80302
community building approx. 11,000 SF. Site
Scott Simkus, Development Planner
Jim Manning, Architect
work, wood framing, plumbing and electrical
303.441.1707
303.442.7042
CU Renovation to Behavioral Genetics PH2
University of Colorado Boulder
Coover Clark & Associates
$ 146,734.00 May'05 Jul '05 35%
Boulder, CO
Boulder, CO
455 Sherman Street Suite 205
Tenant finish of a 3000 SF office space
Larry Krook, Project Manager
Denver, CO 80203
in an existing facility
303.492.4082
John Krieg, Architect
303.783.0040
CU Renovation to Behavioral Genetics
University of Colorado Boulder
Coover Clark & Associates
$ 375,610.00 Jan'05 Jul '05 20%
Boulder, CO
Boulder, CO
455 Sherman Street Suite 205
Tenant finish of a 4000 SF animal lab
Larry Krook, Project Manager
Denver, CO 80203
in an existing facility
303.492.4082
John Krieg, Architect
303.783.0040
CSU Chemistry XRD Lab Remodel
Colorado State University
Slater Paul Architects
$ 156,293.00 Aug 05' Nov 05' 25%
CSU Main Campus
Facilities Management North
One Central Park 1515 Arapahoe St
Remodel of 3065 Sf of lab space for offices
Jon Feiman, Project Manager
Suite 400, Denver CO 80202
and new lab.
970.491.0159
303.607.0977
CSU Podiums
Colorado State University
CSU Classroom Technical Services
$ 11,117.00 Jan'05 Dec'05 100%
Provide small and large podiums as
Purchasing, Alyesworth Hall
Office of Instructional Services
required for 2005
Larry Bauer, Purchasing Agent
Andre Smith, Chief Engineer
6 Large, 2 Small
970.491.6166
970.491.1325
5
C. UNIT PRICES
1. $ GO -ADD Trash/Ash Receptacle:
$ 3 'DEDUCT ADD or DEDUCT, one trash/ash receptacle per specifications,
install complete.
2. $41,C22�-ADD Flagstone veneer per specifications:
$ --O - DEDUCT ADD or DEDUCT, one square foot of 4" flagstone veneer
per specifications, installed complete.
3. $4) �j_ADD Thin veneer flagstone veneer (approved match):
$ _..p _ DEDUCT ADD or DEDUCT, one square foot of thin veneer flagstone
veneer (approved match), installed complete.
4. $ yJ(,- ADD Electrical outlets:
$DEDUCT ADD or DEDUCT, on electrical outlet per spec. complete.
5. $ADD Data outlets:
$J-s _ DEDUCT ADD or DEDUCT, one data outlet per spec. complete.
6. $ Ny y_ADD ADD or DEDUCT, one LF of upper and lower cabinet p. lam
$1?,2• DEDUCT millwork spec, complete
7. $ y ADD ADD or DEDUCT per sf of interior wall demolition
$ . ] S DEDUCT
8. $12t�_ADD ADD or DEDUCT per sf of new gyp. bd. studs interior wall
$ _O_ DEDUCT
9. $ 3.20 ADD ADD or DEDUCT per sf of interior painting
$ •50 DEDUCT
10.$ _gy-ADD ADD or DEDUCT each typical 6" X 6" room sign
$_2S-DEDUCT
ll.$�=ADD #1 ADD or DEDUCT per sf carpet, Types 1, 2, 3, and 4.
$ 2. 5oDEDUCT #1
$ 8 ADD #2
$ 2 _ --2bDEDUCT #2
$ADD #3
$(j DEDUCT #3
$__ADD #4
$2 DEDUCT #4
12.$ 2 y - ADD ADD or DEDUCT per sf ceramic tile 2" X 2" installed price
$ L 5"ODEDUCT
l3.$,3,2,0- ADD ADD or DEDUCT each 2ft X 2ft terrazzo tile
$_`DEDUCT
14.$90' ADD ADD or DEDUCT per square yard concrete paving
Projects in Progress as of 07/19/2005
Growling Bear Co., Inc., 2330 4th Avenue, Greeley, CO 80631 Phone: (970) 353-6964 Fax: (970) 353-6974 page 2
Work on Hand % Work
Contract Scheduled W/Own
Project/DescriptioNLocation Owner Architect/Engineer Amount Start Completion Forces
Island Grove Village Apartments
Island Grove Village Apartments
Island Grove Village Apartments $ 131,000.00 May'05 Aug 05' 50%
119 14th Ave.
119 14th Ave, Greeley, Co
119 14th Ave, Greeley, Co
Greeley, Cc 80631
Craig Allen, Manager 970.356.2808
Craig Allen, Manager 970.356.2808
Replace several doors in the Existing Facility
Borge Villumsen, Owners Agent
Borge Villumsen, Owners Agent
970.352.2931
970.352.2931
LDS Pavillion
Church of Jesus Chrict of Latter Day Saints
Krueger Architects and Planners Inc. $ 43,476.00 Apr'05 Aug 06 90%
Loveland, CO
3263 Fraser Street, Suite 1
407 North Lincoln Ave, Suite 103
Construction of an 1800 Sf concrete pad,
Aurora, CO 80011
Loveland, CO 80537
earthwork, landscaping, and electrical for
Jeff Scott, Project Manager
Jeff Krueger, Architect
the construction of an outdoor shelter
303.798.3970
970.613.1788
Growing Our Co, Inc., 23M 4th Avenue, Greeley, CO finki Plane: (970) 3534M Fax: (970) 353-6974 Page 1
Pralset/DaecrbtbNLocalbn
Owner
ArchNaeflEnalneer
Final
Contract
Amount Start
Cone-
lsdon
% of work
With Own
Forces
New West Bank
New West Bank Colorado, ldc.
Robert Shreve Architects & Planners
PM:
f 1,309,573.00 Nov'04
June'05
25%
Eaton, CO
3459 N. 20ah Street Suite 114
801 8t h Street, Suite 120
Kevin Shironaka
Design Build of new bank tastily
Greeley, CO 80634
Greeley, CO 60631
Superintendent:
10,000 SF New site development and
Ph: (970) 356.0703
Robert Shreve, Architect
Ride Denning
utilities. 2 sexy facility, wood framed
Leroy Leavitt, Owner
970.346.0151
Dowdy Lake Vault Tons
USDA Forest Service R-21RMRS
USDA Forest Service R-2IRMRS
PM:
f 317,072.00 Sept'04
June'05
80%
Red Feathers Lake Area
240 West Prospect Rd
240 West Prospect Rd
Kevin Shironaka
Construct 7 new SST Vault tontels and
Fort Cdnns, CO W526
Fort Collins. CO 80526
Superintendent:
remove 7 existing vaults
Linda Torgensen COR
Christina Scofield Contract Specialist
Don Myers
970.498.1174
970.498.1174
Truscott Elementary Cabinet Replacement
Loveland, CO
Replace cabineoy in Trusoott Elementary
with new custom cadnsts, re anwtated tops
new book shelves, and new, plain tops
Evans Municipal Swimming Pod
3315 15th Ave
Evans, CO
Remodel Swimming pod area. New Shower
Valves, and coiling dais DesignlBuild
CSU Chemistry Third Floor Remodel
CSU Main Campus
Remodel of 16W SF lab space. Laboratory
fume hosts, epoxy resin tops, and wood
casework.
CSU Corbett Dining Han Renovation
CSU Main Campus
Renovation to existing dining facility new
food service equipment and interior design
CSU UCA Concert Has Dressing Rooms
CSU Main Campus
Renovation to 663 SF to add 3 restrooms and
4 dressing rooms to the basement area
Evans Carwnntty Center Renhodel
1100 37th St
Evans, CO
Renhodel Existing 500 Sf space to add 6
Offices. Design Build project
Farmers Bank
Aull, CO
Design Build addition to existing bank
5000 SF wood framed single story taaliy
and renovation to existing space
Thompson School District
2890 N Monroe
Loveland, CO 80538
Tim Mangkha, Project Manager
970.613.5382
Cary of Evans
1100 37th Street
Evans, CO
Dan Maples, Recreation Supervisor
970.476-1127
Colorado Slate University
Facilities Management North
Jon Famiar. Project Manager
970.491.0159
Colorado Slate University
Facilities Management North
Bill Conn, Project Manager
970.491.0145
Colorado State University
Facilities Management North
Cass Beitler, Project Manager
970.491.0158
Thompson School District
PM: f
2890 N Mamoe
Curtis Nsibauer
Loveland, CO 80538
Superintendent:
Tracy Burtnett, CPPO
Eric Morehead
970.613.5151
Growling Bear Co. (Inc.)
PM: f
2330 4th Ave
Gary Shironaka
Greeley, Co 80831
Superintendent:
970.363.6964
James Holman
Slater Paul Architects
PM: f
One Central Paris 1515 Arapahoe St
Curtis Naibauer
Suite 400, Denver CO 80202
Superintendent:
303.607.0977
Glen Hopes
CCMK Architecture PM:
31a East Oak Street Curtis Naibauer
Fort Collins, CO 80524-2915 Superintendent:
Tom Killed, Architect Glen Hopes
970.493.1220
Stater Paul Architects PM
One Central Park 1515 Arapahoe St Curtis Naibauer
Suite 400, Denver CO W202 Superintendent:
303.607.0977 James Holman
City of Evans
Growling Bear Co. (Inc.)
1100 37th Street
2330 4th Ave
Evans, CO
Greeley. Cc W631
Brian Store, Recreation Superintendent
970.353.6964
970-475-1128
Farmers Bank
Robert Shreve Architects & Planners
1191st Street
801 60h Street, Suite 120
Aunt, CO
Greeley, CO W631
Fred Bauer, Owner
Robert Shreve, Architect
970.834.2121
970.346.0151
Projects Completed Last 5 Years
PM:
Gary Shironaka
49,963.00
May'05
Jul V5
100%
23,721.00
Apr'05
Jun'05
85%
264,868.00
Dec'04
June'05
35%
f 752,546.00
Dec'04
Apr'05
35%
f 73,606.00
Feb'05
Apr 05'
60%
f 22,351.00
Feb'05
Mar'05
85%
PM: f 560,871.00 Aug'04 Jan V5 35%
Kevin Shironaka
Superintendent:
James Holman
Growlprg Bear Co., Inc., 2330 4th Avarua, Greeley, CO 508311 Phone: (970) 3534964 Fax: (970) 35"974 page 2
Final %of Work
Contract Comp- With Own
ProlecVDescrbtbNLocatlon Owner AmhttecUEnalnaer Amount Start town Fore"
FSV Stairs and Handicap Ramp
Fort Saint Main, Platteville, CO
Renove old wood stairs and replace with
welded aluminum stairs arid ramp
CSU Stallion lob Renodel 8 Addition
CSU Footfalls Campus
Remodel 6400 sf and additon 15M at
New entrances bed into existing building
new laboratory casework and counter tops
CSU Equine Reproduction Lab
CSU Foothills Campus
Ft. Collins, CO
New 3500 SF classroom building 2 story
wood framed, new utilities and sitework
Island Grove Village Apartments
119 14M Ave.
Greeter, Cc 80631
Remodel and Upgrading of existing
Facility Design Build Project
Atmos Energy
120011th Ave
Greeley, Cc W631
Design Build, I0,000 SF facility
Interior remodel adding new office spaces
Church of Jesus Christ of Latter Day Saints
Greeley, CO
Sidewalk Replac ents
Replace sidewalk and add steel handraits
to church entrances
GCI Elevator Tower Design Bold
2780 281h Avenue
Budd elevator tower and machine room on
the exterior of buddklg, includes new
handicap elevator and card security system
Atinos Energy
1200 110n Ave
Greeley, Cc 80631
Remodel skylight system and repair
interior drywall, Design Build
Flamm Del Sol
Greeley, CO
Provide rod enclosure over balk in cooler
Bechtel BWXT Idaho, LLC (BBWI)
Growling Bear Co. (Inc.)
2625 Fremont Ave
2330 4th Ave
Who Falls, ID 83415
Greeley, CO 80631
Dave Macdonald, SA, 208.536.9990
970.353.6964
Frederick Borst, STR,
Colorado State University
Morgenti Group, Inc
Facilities Management North
2903 Aspen Dr, Suite B
Cass Beider, Project Manager
Loveland, CO 80538
970.491.0158
Joe Ashoraft, Architect
970.667.4000
Colorado State University
Ader Ungle Architects P.C.
Facilities Management North
712 Whalers Way, Suite 8-100
Steve Keiss, Project Manager
FL Collins. CO 80525
970.491.0017
Mike Rush, Architect
970.223.1820
Island Grove Village Apartments
Island Grove Village Apartments
11914th Ave, Creaky, Cc
11914th Ave, Greeley, Cc
Crap Allen, Manager 970.3562808
Craig Allen, Manager 970.356.2808
Borge Villunlsen, Owners Agent
Borge ViSumsen, Owners Agent
970.3522931
970.352.2931
Auras Energy
Growling Bear Co. (Inc.)
1200 11ti1 Ave
23304th Ave
Greeley, Cc 80831
Greeley, Cc 80631
Glen Norman, Operations Manager
970.353,6964
970.304.2077
Lurch of Jesus Christ of Latter Day Saints
Bryan Keys and Associates
3263 Fraser Street, Suite 2
417 South Cascade Avenue
Aurora. CO a0011
Colorado Springs. CO S0903
Malcom Hum , Project Manager
719.634.3761
303.371.2873
Greeley Center for Independence
Growling Bear Co. (Inc.)
2780 280t Avenue
2330 4th Ave
Greeley, 00 80634
Greeley, Cc WWI
Hope Cassidy, Director
970.353.6964
970.339.2444
Arrtos Energy
Growling Bear Co. (Inc.)
1200 11th Ave
2330 41h Ave
Greeley, Cc WWI
Greeley, Co S0631
Glen Norman, Operations Manager
970.353.6964
970.304.2077
Catholic Charities
John Dangler & Associates
480 Linden Center Drive, PO Box 2262
5336 Highcastle Court
Ft Collins, CO 80522
Ft. Collins, CO W525
Ernie Gkon, Exec. Director
970-223.1512
970.484.5010
Jahn Dangler, Architect
Projects Completed Last 5 Years
PM:
Kevin Shironaka
Superintendent:
Jimmy Metcalf
PM:
Curtis Naibauer
Superintendent:
Glen Hoopes
PM:
Curtis Naibauer
Superintendent:
Glen Hoopes
PM:
Curtis Naibauer
Superintendent:
Rick Denning
PM:
Kevin shironaka
Superintendent:
James Holman
PM:
Gary Shironaka
PM:
Kevin Shironaka
Superintendent:
wck Denning
PM:
Kevin Shironake
Superintendent
James Holman
PM:
Kevin Shironaka
$ 32,352.00
Jan'05
Feb' 05
10%
$ 362,667.00
Apr '04
Nov'04
35%
$ 399,996.00
Apr '04
Nov'04
35%
$ 1,102,877.00
Apr '04
Sept 04'
25%
$ 160,496.00
Jul 04'
Oct 04'
46%
$ 8,959.00
Oct 04'
Oct 04'
100%
5 96,914.00
Aug 04'
Sept 04'
16%
$ 99,961.00
Jul 04'
Oct'04
35%
$ 11.644.00
Aug 04'
Aug 04'
50%
Growling Bear Co., Inc., 23M dth Avenue, Greeley, CO 00631 Phone: (970) 3534964 Fax: (970) 3534974
ProlecUDescrlptlOrAAcation Owner Archhact(Engineer
page 3
Final % of Work
Contract Comp- With Own
Amount Start lotion Forces
CSU Portable Scull Panels
Colorado State University
Slater Paul Architects
PM:
$ 8,587.00 Sept '04 Oct'04 100%
CSI1 LICA Conch Hall
Facilities Management Noll
One Central Park 1515 Arapahoe St
Curbs Naibuaer
Build 4 - T x 8' portable sound absorbtion
Cass Bolder. Project Manager
Suite 400, Denver CO 80202
panels for the LICA Concert Hall
970.491.0158
303.607.0977
CSU UCA Concert Hall Restroom Remodel
Colorado State University
Slater Paul Architects
PM:
$ 65,743.00 Jul 04' Jul 04' 85%
Remodel Existing historic bathroom for
Facilities Management North
One Central Park 1515 Arapahoe St
Curbs Naibauer
ADA compliance. 650 SF Electrical
Cass Beilkr, Protect Manager
Suite 400, Denver CO 80202
Superintendent:
upgrades, New plumbing fixtures
970.491.0158
303.607.0977
Don Myers
CSU Podiums
Colorado State University
CSU Classroom Technical Services
PM:
$ 19,014.00 Feb'04 Sept '04 100%
Provide smao and large podiums as
Purchasing, Myesworth Hall
Office of Instructional Services
Gary Shironaka
required
Larry Bauer, Purchasing Agent
Dave James. Telecom Specialist
6 large, 14 small
970.491.6166
970.491.6080
CSU LICA Concert Hall Sound Cabinets
Cokxado State University
Slater Paul Architects
PM:
$ 18,259.00 Jul 04' Aug 04' 100%
Colorado State University
Facilities Management North
One Central Park 1515 Arapahoe St
Gary Shimnaka
Provide new casework cabinets with
Cass Beater, Project Manager
Suite 400, Denver CO 8=2
sound ebsorbtion panels
970.491.0158
303.607.0977
CSU Newsom Hell Fxlencr Facade
Colorado State University
Colorado State University
PM:
$ 124,238.00 June'04 Jul'04 85%
Colorado State University
Facilities Management North
Operation Management
Curtis Naibauer
Repair exterior concrete and 19,000 SF
Bill Conn, Project Manager
Ken Maninolich, Project Supervisor
Superintendent:
of new exterior siding and painting
970.491.0164
970.491.0866
Don Myers
Centennial Bank Restoration
Centennial Bank of the West
Centennial Bank of the West
PM:
$ 5,754.00 May'04 June'04 100%
4650 Royal Vista Circle
4650 Royal Vista Circle
4650 Royal Vista Circle
Gary Shironaka
Fort Collins. CO 50525
Fort Collins. CO 80525
Fort Collins, CO B0525
Replace damaged base and trim in
(970) 454-4141
(970) 4544141
basement
Bill Farr, CEO
Bill Fan, CEO
MLS Properties
Mike Shoop
Growling Bear Co. Inc.
PM:
$ 283.726.00 Dec-'03 Mar'04 15%
928 10m S.
Us? w 11 at.
2330 4th Ave
Curtis Naibauer
Greeley, CO
Greeley. CO WWI
Greeley, CO
Superintendent:
Design Build Tenant Finish
970-353-6964
Pick Denning
Stephen's Center
Greeley Center for Independence
Lamy E. Seek Associates
PM:
$ 845,316.00 Aug'03 Mar'04 15%
277412778 Reservkr RD
2780 28th Avenue
2308 West 298h Street
Curtis Naibauer
Greeley, CO 80634 -
Greeley, CO W634
Greeley, CO 80631
Superintendent:
7000si Indepogenl Living Facility
Hope Cassidy, Director
Wray Seek, Architect
Glenn Hoopes
1500sf activity Center Design Build MEP
970.339.2444
970.353.6363
VA Medical Canter 3rd Floor Re ov.
VA Medical Center
Tobin & Associates, PC
PM:
$ 481,992.00 Aug V3 Mar 04' 15%
New electrical, mociamieel, medical
2360 E. Pershing Blvd.
209 E. 208h Street
Curtis Naibauer
gas distribution system, rorse.ab &
Cheyenne, WY W001
Cheyenne, WV 82003-2420
code blue system. all finishes.
Jane Golding, Contracting Officer
Ken Tobin, Architect
307.778.7329
307.632.3144
Projects Completed Last 5 Years
Growling Bear Co., Inc., 2330 4th Avenue, Greeley, CO 00ti31 Plana: (970) 353.6964 Fax: (970) 3534974 page 4
Final %of Work
Contract Comp- With Own
PrWectlDescrlptbNLoeatbn Owner ArchttectlEnbinot r Amount start lotion Forces
Cheyenne Substation Mods.
US Dept. of Energy
US Dept. of Energy
PM:
400 Mc Felond Drive
Western Area Power ASSOC.
Western Area Power Assoc.
Gary Shironaka
Cheyenne, WY
5555 E. Crossroads Blvd
SW E. Crossroads Blvd
Superintendent:
New 2500 of control building and
Loveland, CO 80538
Loveland, CO 80538
Don Myers
demo of existing facility
Toby Trijillo 970.461.7286
Virgil Downing 970-461.7267
Uncoln Center
City of Fort Collins
Alter-t..irgle Architects, P.C.
PM:
HVAC end Roof Replacanent
215 N. Mason Street
712 Whalers Way, Bldg. B-100
DR Shelton
New roof and mechanical platform
Fort Collins, CO 80522
Fort Collins, CO 80525
Superintendent:
Steve So~, Project Manager
Shaun Moscrip, Architect
Don Myers
970-221 M7
970-223-1820
Greeley LDS Church
LDS Church
TSP Five, Mc.
PM:
Rernove old and install new boiler,
3263 Fraser St., Suite 1
8751 E. Hampden Ave. Suite A-1
DR Shelton
Misc. landscaping, concrete and
Aurora. CO 80011
Denver, CO 80231
Mechanical room deck
Ron Humphries, Representative
Jeff Krueger, Architect
303.798.3970
303-695.1997
Plo>a del Sol Farm Labor Housing
Catholic Chanties
John Dangler 5 Associates
PM:
Greeley, CO SD631
460 Linden Center Drive, PO Box 2262
5336 Hghcestle Court
Kevin Shianaka
42 Farm Housing units
Ft Collins, CO 80522
Ft. Collins, CO 80525
Superintendent:
and 1 Community Center
Ernie Gran, Exec. Director
970-223.1512
Junior Morgan
_
970-484-5010
John Danger, Architect
St. Marys Catholic Church
St. Marys Catholic Church
St Marys Catholic Church
PM:
Greeley, CO
2222 23rd Ave.
2222 23rd Ave.
Junior Morgan
Chillerl8ai er replacement
Greeley, CO 80631
Greeley, CO 80631
Bank of Colorado Branch Bank
Bank of Colorado
The Morganti Group
PM:
3640 West 10th Street
5628 West 19m Street rig -
2903 Aspen Drive, Suite 8
Junior Morgan
Greeley, CO 80634
Greeley, CO 80634
Loveland CO 00538
Superintendent:
Tenant Finish
Greg Ludlow, Branch Manager
Marvin Morganti, President
Phil Hershman
970.506.0100
(970) 667.4000
Heath Middle School
Weld Cty. Sdad Dist. 06
Kkpp Colussy Jenks DuBois
PM:
222316th Avenue
2204 Rh Avenue
1512 Latimer Street
Junior Morgan
Grossly, CO
Greeley, CO W631
Denver, CO 80202
Superintendent:
Interior Remodel
J.W. Nelson, Facilities Supervisor
Sam Miller, Architect
Rick Denning
970.348-6400
(303)893.1990
Wyoming Dept. of Transportation
Wyoming Dept. of Transportation
Wyoming Dept. of Transportation
PM:
Miaoware Room Renovations
5300 Bishop Blvd.
5300 Bishop Blvd.
Kevin Shironska
Interior Remodel
Cheyenne, WY 82009
Cheyenne, WY 82009
Superintendent:
Hans Hehr, Ass t Purchasing Manager
Hans Hehr, ASHY Purchasing Manager
Dennis Nelson
370.777.4106
370.777.4106
Colorado East Bank and Trust
Colorado East Bank and Trust
Wedgewood Development Co.
PM:
207 1st Ave
207 1st Ave
P.O. Box 431
Junior Morgan
La Salle, CO
La Salle, CO
La Salle, CO
Superintendent:
Interior Demo and Remodel
970-284-0211
Phil Hershman
Projects Completed Last 5 Years
$ 626,970.00
Mar'03
Mar'04
40%
6 369,502.11
Aug'03
Jan'04
10%
$ 111,191.00
Aug'03
Dec'03
10%
$ 1,260,800.30
May03
Dec'03
16%
$ 26,850.00
Oct'03
Ded03
30%
$ 188,241.00
Jun V3
Sep'03
25%
$ 127,106.00
Jun'03
Aug V3
15%
$ 167,765.00
Mar'03
June'03
10%
$ 82,420.00
Feb-03
Jun-03
75%
Growling Bear Co., Inc., 2330 4M Avenue, Greeley, CO 90931 Phone: (970) 363.6964 Fax: (970) 353-6974 Page 5
Final %of Work
Contract Comp- With Own
PMIoct Wacrlo9onnAcation Owner ArchlteeVEnalne it Amount start lotion Forces
Bella Romero Elementary School
Weld Cty. School Dist. 06
1400 20th St.
2204 5th Avenue
Greeley, CO 80631
Greeley, CO 80631
New Construction 72,000 SF
J.W. Nelson, Facilities Supervisor
2 Story
970.348.6400
New West Bank Colorado, Inc.
New West Bank Colorado, Inc.
3459 N. 20M Street Suite 114
3459 N. 20th Street Suite 114
Greeley, CO 80634
Greeley, CO 80634
Remodeb7enant Fkriah
Ph: (970) 356-0703
Construct new Dive thru
Leroy Leavitt, Owner
Island Grove Regional Treatment
Island Grove Regional Trtrnt. Ctr.
1513 11 th Avenue
1140 -M' Street
Greeley, CO 80681
Greeley, CO 80631
New Construction Medical Facility
Ph: 970.355.6654
2 Story, 15,000 al.
B.J. Dean, Exec. Director
World Savings Branch Bank
World Savings and Loan Assoc.
12100 Washington Street
1901 Harrison Street
Thornton, CO 80241
BM Floor
New Construction Banc Facility
Oakland, CA 94612
Don Gracey 510.446.4008
Fire Station No. 1
Eaton Fire Protection Oistnct
50 S. Maple
224 1 at Street
Eaton, CO 80615
Eaton, CO W615
New construction of 12,000 SF
Warren Milne, Fire Chief
Metal Building
970.454.2115
Plativille Town library
Town of Plattev9k
504 Marion Avenue
400 Grand Avenue
Platteville, CO Sow
Platteville. CO 80851
Design Build Library Addition and
Diane Norgren
Remodel
970.785.2231
CSU USC 51h Floor Remodel
Colorado State University
510 Howes Street
Office of Advance Services
Ft. Collins, CO 80523
510 University Services Center
Remodel 7000 SF
Fort Collins, CO 80523.7114
Ann Yates 970.491.4939
John Evans Middle School
Weld County School Dist. 06
2900 ISM Ave.
Facilities
Greeley, CO Swil
J.W. Nelson, Facilities Supervisor
Drainage Improvements
970348.6400
Edema renovation
Dorn 248 Renovation
Operational Contracting Division
F.E Warren Air Force Base
Building JIM
Cheyenne, WY
F.E. Warren AFB
Interior Renovation; to Historic Donn
Cheyenne, WY 82005
Building
Charles Melvin
RUB Architects
PM:
315 E. Mountain #100
Gary Shironaks
Ft. Collins, CO 80524
Superintendent
Ken Field Architect
Glen Hoopes
970.484.0117
Clyde L. Schroeder
PM:
2000 Wadsworth Blvd. Suite 111
Junior Morgan
Lakewood, CO 80214
Superintendent
Clyde L. Schroeder Architect
Rids Denning
(303)814.1350
Roberts Architects
PM:
5312 W. gM St. Dr., #100
Dennis Nelson
Greeley, CO 80634
Superintendent
970.353.7232
Don Myers
Cart Cross. Architect
Lane 6 Smart PM:
400 N. Loop 1604 East Junior Morgan
Suite 310 Superintendent
San Antonio, TX 78232 Dale Graham
Charles Benson 210.491.9553
Roberts Architects PM:
5312 W. 9M St. Dr. #100 Junior Morgan
Greeley, CO WWI Superintendent
Wayne Roberts, Architect Phil Hershman
970.353.7232
Robert Shreve Architects & Planners
PM:
80180 Streel, Suite 120
Curbs Nsibauer
Greeley, CO WWI
Superintendent:
Robert Shreve Architect
Rids Denning
970.346.0151
Colorado State University
PM:
Facilities Management
Gary Shimnake
Colorado State University
Superintendent:
Fat Collins, CO 80523.6030
Phil Hershman
Cass Better Project Manager 970.491 .01 58
Pickett Engineering
PM:
808 8th Street
JR Morgan
Greeley, CO 80631
Superintendent:
970356.6362
Phil Hershman
Operational Contracting Division
Building SM
F.E. Warren AFB
Cheyenne, WY 82005
Charles Melvin
Projects Completed Last 5 Years
$ 8,133,225.00
Jun'-02
Jun'-03
10%
$ 301,068.00
Dec.'02
Jun.'03
30%
$ 1,760,736.00
Sep.'02
Jun:03
18%
$ 818,488.00
Nov' 02
May '03
10%
$ 1,479,713.00
Jul'-02
Mar'-03
30%
$ 292,403.00
May'02
Sep.'02
35%
$ 260,141.00
Mar.'02
Sep.'02
25%
9 118,487.00
Jun -rot
Sep-'02
85%
PM: S 3,445,274.00 Apr-00 Sep-02
Dennis Nelson
Superintendent:
Scott Sauer
25%
Growling Bear Co, Inc., 2330 4th Avenue, Greeley, CO BOMi Phone: (970) 353.6964 Fax: (970) 3534974 page 6
Final %of Work
Contract Comp. With Own
Pr0leetrWscrlOtkuJLocatbn Owner Archl ectfEnolneer Amount Start lotion Forces
Salvation Army Fence
The Salvation Army
Greeley, CO
Cal60mia Corporation
Fence around Early Childhood Ed. Ctr.
180 E. Ocean Blvd.
Long Beach, CA 90802
Captains Tim/ Sybil Smith
Youth Center Phase If
90 Con s&GCI
7505 Marne Loop
7505 Memo Loop
FE Warren AFB, WY 82005.2960
F.E. Warren AFB, WY 82W5
Metal Building -Gym addition
Richard.8mn-Flight Chief
Brentwood Middle School
Weld County Sdvd Dist. aG
2600 24 Ave CT
1025 9th Avenue
Greeley, CO 80634
Greeley, CO 80831
Gymnasium Addition and Remodel
J.W. Nelson, Facilities Supervisor
of Existing Fatetty
970.348-6400
Franklin Middle School
Weld County Scholl Dist. 05
818 351h Ave
26W 24th Avenue
Greeley, CO SWU
Greeley, CO 80634
M Room Addition and Remodel of
J.W. Nelson, Facilities Supervisor
Existing Facility
970.348-6400
Cheyenne Frontier Days Front Gate
Cheyenne Frontier Days
4610 N. Carey Avenue
4610 N. Carey Avenue
Cheyenne, WY 82001
Cheyenne, WY WWI
New Construction Front Gate
Dale VmKrosigk
and Sitework
307.778.7200
Outdoor Firing Range
Warren Air Force Base
F.E. Warren Air Force Base
Opeationel Contracling Division
New Construction of Shooting Range
Building 6208
Cheyenne, WY 82005
Joe Kirkland
307.773.3321
Agriculture Building (steel)
Lawrence Case
3179 Western Drive
3179 Western Delve
Hudson, CO 80642
Hudson, CO 80642
New Steel Building
Our Saviors LUBnem Church
Our Saviors Luthem Church
Remode0 Addition
1800 21st Ave
18W 21st Ave
Greeley, CO 60631
Greeley, CO 80631
Jennifer, Ownees Manager
970352-4816
Earl Childhood Development Ctr
The Salvation Amy
Location: 1119 6th Saw
1119 6th Street
Greeley, CO 80631
Greeley, CO 80831
New Construction, 7,O00 all.
Captain Ten Smith
970-346-1161
Salvation Amy
PM: $ 59,788.00 Apr-'02 Aug-'02 25%
California Corporation
JR Morgan
180 E. Ocean Blvd.
Superintendent:
Long Beach, CA 90802
Phil Hershman
F.E. Warren AFS
PM: $ 1,186,964.72 Sep•'99 Aug•'02 15%
Cheyenne, WY 82005
Dennis Nelson
Richard Jkon-Flight Chief
Superintendent:
307-773.1006
Don Myers
Robert Shreve Architects & Planners
PM: $ 1,153,861.00 Feb.'02 Aug.'02 35%
001 8th St., Suite 120
Junior Morgan
Greeley. CO WWI
Supenntendent
Robert Shreve Architect
Glenn Hoopes
970.346.0151
Ruben Shreve Architects 6 Planners PM:
801 8th St., Suite 120 Ron Sword
Greeley. CO 80631 Superintendent
Robert Shreve, Architect Doc Shelton
970.346.0151
Noel Griffith Jr. & Assoc. PM:
2515 Warren Ave., 9425 Dennis Nelson
Cheyenne, WY 82001 Superintendent
Dan Johnson Audie Wilson
307.632.4375
Warren Air Force Base
PM:
Operational Contracting Division
Dennis Nelson
Building 8208
Superintendent:
Cheyenne, WY 82005
Billy Holmes
Joe l9rkland
307.773.3321
Wemsman Engineering
PM:
121010th St.
Ron Sword
Greeley, CO 80631
Superintendent:
Steve Wemsman 970.363.4463
Rids Denning
Larry Steel Architects
PM:
2308 W. 291 h St. Suite 101
Curtis Naibauer
Greeley. CO emi
Superintendent:
970353.6363
Glen Hoopes
Roberts Architects
PM:
5312 W. 91h SI.Dr., 81 W
Ron Sword
Greeley. CO 80634
Superintendent:
Wayne Roberts
Junior Morgan
970353-7232
Projects Completed Last 5 Years
$ 277.645.00
Apr.=02
Aug=02
15%
6 514,506.00
Mar.=02
Jul.=02
30%
$ 1,425,229.00
Jul.-01
Apr.-02
30%
$ 62,786.00
Jan.-02
Apr.-02
80%
$ 436,539.00
Aug-'01
Feb-V2
25%
$ 539,008.00
Aug-'01
Jan•'02
25%
Growling Bear Co., Ire„ 23M 4M Avon", Greeley, CO W631 Phone: (970) 3534964 Fax: (970) 353.6974 page 7
Final %or Work
Contract Comp- With Own
ProlectlDesx:rbtlortlLoutbw n Oner ArchkectlErglnser Amount Start letion Forces
Anema Dental Center
DR. Mark Anerra
OR. Mark Anema
PM:
7900 W. 44th Ave
7900 W. 44th Ave
7900 W. 44th Ave
Kevin Shironaka
Wheatridge, CO
Wheytridge , CO
wheatrioge. CID
Superintendent:
Tenant Finish, Medical Facility
Rick Denning
9
Cifford Building (Rm 232 & 234)
Colorado State University
CSU Facilities Management
PM:
Colorado State University
Facilities Management
Facilities Services Center N.
Ron Sword
Remodel of Existing Facility
Foil Collins, CO BM3
Fort Collins, CO 80523
Superintendent:
Helen Boggs Project Manager
Phil Hershman
Entomology Wash Rack
Operational Contracting Division
Operational Contracting Division
PM:
F.E. Warren Air Force Base
Suikfing #M
Building 41208
Dermis Nelson
Cheyenne, WY
F.E. Warren AFB
F.E. Warren AFS
Superintendent:
New Construction
Cheyenne, WY 92005
Cheyenne, WY 92005
Whitey Pandil
Curt Evan
Curt Swan
307-773-6949
307-773-6949
Veteran's Administration
Veterans Administration Center
Tobin and Associates
PM:
VA Medical Center
2360 E. Pershing Blvd.
209 E. 20th Street
Dennis Nelson
Cheyenne, WY
Cheyenne, WY 82001
Cheyenne, WY 82003
Superintendent:
Remodel Fire Safety upgrades of
Jane Jordan
Ken Tobin
Billy Holmes
Medical Facility
307-778.7367
307-632.3144
Renovate Bldg 212
Operational Contracting Division
Operational Contracting Division
PM:
Warren Air Force Base
Building #208
Building #208
Dennis Nelson
Cheyenne, WY
F.E. Warren AFB
F.E. Warren AFB
Superintendent:
Interior Remodel of Historic Building
Cheyenne, WY 82005
Cheyenne, WY a2005
Scott Sauer
Lt. Mark Adams
Lt. Mark Adams
307-773.5916
307-773-5916
Stewart Stevenson Remodel
Stewart Stevenson Power, Inc.
Roberts Architects
PM:
5840 Dahlia Street
5540 DONIS Skeet
5312 W. 9h Street Drive, #100
Ron Sword
Commerce City, CO 80022
Commerce City, CO 80022-3707
Greeley, CO W634
Superintendent:
Design Build Tenant Finish of Existing
303-287-7441
Wayne Roberts
Rick Denning
Facility
David Roth
970-353.7232
City of Greeley
City of Greeley Parks Dept.
Robert Shreve Architects & Planner Inc. PM:
Monfort Park PicniclResbooms
501 N 14th Ave.
801 Bh St. Suite 120
Curtis Naibauer
47th Ave. & 24h Street
Greeley, CO WWI
Greeley, CO W631
Superintendent:
Greeley, Co. WWI
970-350.9393
970,44"151 Bob Shreve & Will Steel Phil Hershman
ShelterlRestroom/Concession Bldg.
City of Greeley
City of Greeley
CCMK Architecture & Planning
PM:
Design Build Various Projects
1000 10h Street
318 East Oak Street
Gary Shironaka
Recreation Center. Senior Center,
Greeley, CO 80631
Fort Collins, CO 00524-2915
Superintendent:
Swimming Pod, & Shoo" Range
Terry Greibe (970)350-9293
970-493-1220, Tom KAW
Junior Morgan
Garden City Town HBO
Garden City Town Government
Robert Shreve Architects & Planners
PM:
62127 Street
621 27th Skeet Road
801 Bth Street, Suite 120
Curtis Nelbauer
Garden City, CO 8=11
Garden City, CO
Greeley. CO 90631
Superintendent:
Design Build New Construction
Bob Warren, Mayor
Robert Shreve, Architect
Cu Nor
3000 of
970.351.0041
970.346.0151
Prajects Completed Last 5 Years
$ 135.617.94
Nov -rot
Jan=02
20%
$ 113,711.00
Jul.-01
Dec.=01
25%
$ 346,827.00
Nov-00
Dec.=01
19%
3
S
$191,179.00 Jun -rot Deo=01 75%
943,097.00 Nov-00 Dec:'01 19%
89,408.00 Oct.=01 Dec.=01 50%
$320,189.00
Feb-'01
Sept'Ot
15%
$ 1,400,845.00
Dec.-00
Juy'01
12%
$ 296,324.00
Jan.-01
Jun.-01
23%
Growling Bear Co., Inc., 2330 4th Avenue, Greeley, CO S0631 Phone: (970) 353411994 Fax: 1970) 353-6974 Page 8
Final %of Work
Contract Comp- With Own
Pro1K:UDSOCII101110111,11LOONtlon Owner ArchilectlEnalneer Amount Start Istion Forces
Fort Lupton Community Center
130 S. Mckinney Ave
Ft. Lupton, CO S0621
New Construction, 12000SF
Steel Building
Centennial Bank of Windsor
4660 Royal Vista Circle
Fort Collins, CO 80525
New Construction 16000SF, 2 story
World Savings Bank
Harmony Center
Fort Collins, CO 80524
New Construction 4000 SF
Brighton United Methodist Church
625 South Brh Avenue
Brighton, CO
2500 SF Addition 9000 SF Remodel
Vauit Toilets
Ansel Watrous Campground
USDA Forest Service
Moraine Pk Amphitheater
Rocky Mountain National Park
Estes Park, CO
Centennial Bank Lending Offices
4630 Royal Vista Circle
Fort Collins, CO 8=5
Tenant Finish 1200 SF
Camelot Apartments
17th Street S 8tm Avenue
Greeley, CO SO631
Addition and Remodel of Existing Facility
Alter Support EquipJVehick
Mount. Shop N103
Buckley a'x Not. Guard
New Building - Greeley
City of Fort Lupton
130 S. McKinley Avenue
Ft. Lupton, CO 80621
970.302.4333
John Swallow
Centennial Bank or the West
4650 Royal Vista Circle
Foil Collins, CO 80525
(970)454-4141
Bill Farr, CEO
World Savings Bank
Harmony Center
Fort Collins, CO 00524
Jerry Kirkpatrick, (610) 446-5030
United Methodist Church
625 South Sth Avenue
Brighton. CO
Les Fraley, Ovmer Representative
303-294.2153
USDA Forest Service- RMRS
240 West Prospect Rd
Fort Collins, CO 80526
Teri Pues
Rocky Mountain National Park
1000 HWY 36
Estes Park, CO 80517
Anne M. Vlktora
970576-1271
Centennial Bank of the West
4650 Royal Vista Circle
Foil Collins, CO 80525
(970)454.4141
Bill Farr, CEO
Greeley Center for Independence
2780 28M Avenue
Greeley, CO 80834
970-339.2444
Hope Cassidy, Director
USPFO P&C, Stop 66
660 S. Aspen Street. Bldg 1005
Buckley ANG Base
Aurora, CO 8011-9551
Michael S Schwamberger
Slater, Paull S Associates PM: E 1,295,667.00 Aug-00 June-'01 22%
1515 Arapahoe St., a400 Pete Farquar
Denver, CO 00202 Superintendent:
303.607.0977 Don Myers
Vaught Frye Architects
401 West Mountain Avenue
Foil Collins. CO 80521
(970)224-1191
Matt Rankin, Architect
Memel Brendle Architects
1743 Wazee Street, Suite 400
Denver, CO 80202
303-292-6927
CCMK Architecture S Planning
318 Fast Oak Street
Fort Collins, CO S0524.2915
Tom Kalert, Architect
970-493-1220
USDA Forest Service
240 West Prospect Rd.
Fort Collins, CO 80526
Teri Pues
Rocky Mountain National Parks
1000 HWY 36
Estes Park, CO 80517
Anne M. ViMora
970.57&1271
Vaught Frye Architects
401 West Mountain Avenue
Fort Collins, CO 80521
(970)224-1191
Mat Rankin, Architect
Larry Steel Associates
2308 W 29th Street Suite 101
Greeley, CO a0631
Lamy Steel, Architect
970.353.6363.
Air National Guard
660 S. Aspen Street, Bldg 1005
Buckley ANG Base
Aurora, CO 50011.9551
Michael S. Schwamberger
Projects Competed Last 5 Years
PM:
Gary Shiruinska
Superintendent:
Audie Wilson
PM:
Curbs Naibauer
Superintendent:
Glenn Hoopes
PM:
Gary Shironaka
Superintendent:
Junior Morgan
E 2,388,548.00 Oct-00 Jun-01 18%
E 838,910.00 Dec. -OD June-'01 16%
E 707,284.00 Jan.-W Jun.-01 71%
PM: E 78,122.00 Jun.=00 Jun.=01 15%
Curbs Nsibauer
PM:
Curtis Nsibauer
Superintendent:
Roger Childers
PM:
Gary Shironaks
PM:
Curtis Naibauer
Superintendent
Glean Hoopes
PM:
Michael Bacidund
Superintendent:
JR Morgan
E 140,462.75
Jul=00
May-'01
20%
S 69,761.00
Apr-01
May-01
30%
E 504,680.00
Jun-00
14OV-00
20%
E 137,000.00
Deo'99
Nov-'00
25%
Growling Bear Co, Inc., 2330 4th Avenue, Greeley, CO SM1 Phone: 4970) 353.6964 Fax: (970) 353.6974
page 9
Final
%of Work
Contract
Comp- With Own
ProlectlDeserbtbNLocanon
Owner
ArchOatflErgineer
Amount
Start
lotion Forces
Peak View 8 Monfort Parks
City of Greeley
City of Greeley
PM:
f
206,120.50
Feb-'OO
Oct -DO 100%
Sidwalks
1300 A Street
1300 A Street
Curtis Naibaw
Greeley, CO 80631
Greeley, CO 80631
Steve Augerot
Steve Augerot
Wyoming Air National Guard
Dept. Of On Army 6 Air Farce
Noel GrilfiOt, Jr. & Associates
PM:
f
753,259.00
Mar-00
Oct-00 15%
Cheyenne, Wy
National Guard Bureau
2515 Warren Avenue, Suite 425
Dennis Nelson
RemodelfReplace Hanger Doors
US Property d Fiscal Officer
Cheyenne, WY
Superintendent:
55W Bishop Blvd.
307-632-2705
Scott Sauer
Cheyenne, WY 82009-3320
Jon A. Morse 307-772-5968
Construct Vault Toilets
Rocky Mountain National Parks
Rocky Mountain National Parks
PM:
f
269,041.95
Dee-439
Oct-100 25%
Lake Irene -McGraw Ranch.
1000 HWY 36
1000 HWY 36
John Tripp
Rainbow Curve- Upper Beaver
Estes Park. CO 80517
Estes Park. CO 80517
Rocky Mountain National Park
Anne M.Viktors
Anne M. Vildora
970576-1271
970.576.1271
Wed County Training Center
Weld County Government
Bley Associates
PM:
f
822,040.00
Feb-00
Oct-00 22%
Greeley, CO
91510th Street
2020 Clubhouse Drive
Curtis Nsibsuer
New S,OOOsf One Story Facility
Greeley, CO SD631
Greeley, CO 80632
Superintendent:
Colored Concrete Split Faced Block
Pat Persichino
Loren Bley, Architect
Phil Hershman
970356.4000 Ext. 4224
970.330-3322
Vault Toilets
USDA Forest Service
USDA Forest Service
PM:
f
110,210.oO
Mar -'CO
Sept•'00 15%
West Lake- Red Feathers
240 West Prospect Road
240 West Prospect Road
Curtis Naibauer
Fort Collins, CO 80526
Fort Collins, CO 80526
Teri Puss
Vault Toilets
USDA Forest Service-RMRS
USDA Forest Service-RMRS
PM:
f
95,346.00
Aug-'99
Sep-W 15%
Laramie River Road
240 West Prospect Road
240 West Prospect Road
Curtis Naibsuer
West Branch Trailhead -Rawah Trailhead
Ft. Collins, CO 80526
Ft Collins, CO 80526
Clear Lake Fishing
Teri Pues
Teri Pues
Rem del
JCP � Company inc.
JCPeniW Company ft.
PM:
f
138.661.00
Jul-00
Sep -DO 20%
US Highway Ave
Greeley Mal
2000 Greeley Mall
Curtis Naibauer
Greeley, CO 90634
Greeley, CO 80631
Greeley, CO 80631
Superintendent:
Remodel of Existing Facility
Jane Anderson
Jane Anderson
Curtis Naibsuer
Hawkstone CluMmouse
Payant Real Estate CO
Growling Bear Co., Inc.
PM:
f
374,433.00
Mar-00
Aug•00 18%
1310 Hewkstone Onus
360 Oak Ave.
2330 4th Avenue
Curtis Nalbauer
Eaton, CO
Eaton, CO 80615
Greeley, CO 90631
Superintendent:
Design Buld New Construction
Barn Payant, Owner
John Sold, Architect
Glenn Hoopes
970.454.3452
970-353.6964
Trinity Lutheran Church
Trinity Lutheran Church
Trinity Lutheran Church
PM:
f
84,392.00
Jun-00
Aug00 35%
3000 35th Ave
3000 35th Avenue
3000 35th Avenue
Curtis Nelbouer
Greeley, COReinadef ��
Greeley, CO 80631
Greeley. CO 110631
Superintendent:
Roper Childers
Projects Completed Last 5 Years
5
$_.2AJIPEDUCT
15.$.L.Zo-- ADD
$ ,. 4b DEDUCT
16 . $ gOt> --ADD
$ -{1 _ DEDUCT
17 . $_ADD
$ /,:5DQ - DEDUCT
18.$ y/_ADD
$ /00- DEDUCT
19.$��ADD
$ DEDUCT
20.$ADD
$_Lyoo-DEDUCT
21.$ W--ADD
$ _.p — DEDUCT
22 . $ 3,. 20 ADD
$ 1. ov-DEDUCT
23.$jp.$oADD
$DEDUCT
ADD or DEDUCT per square yard colored concrete paving
ADD or DEDUCT per sf stucco reveals
ADD or DEDUCT TYPE A-1 Pendant fixture installed complete
ADD or DEDUCT TYPE N-2 Downlight installed complete
ADD or DEDUCT per sf sealed stained concrete
ADD or DEDUCT one 3070 SCWD Door and NM frame complete with
hardware
ADD or DEDUCT one LF of stonefaced knee wall.
ADD or DEDUCT one LF of rubber base
ADD or DEDUCT one LF of tile base
24.$ qO y ADD ADD or DEDUCT one LF of granite base
$DEDUCT
D. ART PRICING:
Artist David Griggs (303) 446-3030, 715 Galapago St. Denver, CO 80204
1. Etched glass railing panels - Detail *12 - Sheet A-7.1 - delivery of
glass from railing mfg to Great Panes Glass Works Inc. - 4410
Washington Ave. - Denver, CO 80216 - 303-294-0927 - artist vendor
will provide the photo emulsion etch & deliver to site upon
completion for installation by General Contractor.
$IN BASE BID (photo emulsion price by other)
2. Layered wall board - Detail #13 - Sheet A7.1 - Bas Relief - Layered
4" MDF. Pre -assembled machine cut panels, typically 214" x 41, to be
delivered to site as panels by artist with placement instructions for
installation. Contractor to install per instructions - artist will
supervise installation. Contractor to paint after installation.
Growling Baer Co., Inc„ 2330 4th.Avenue, Greeley, CO 80831 Phone: (970) 3536964 Fax: (970) 353.9974
page 10
Final
%of Work
Contract
Comp- With Own
ProiectiDesubtbNLoeatlon
Owner
ArchttectlEnoineer
ArWunt Start
leflon Forces
VA Dental Facility
VA Medical Center
VA Medical Center
PM:
f 43,577.00 Nov-99
Jun-00 25%
Cheyenne. WY 82W5
Medical 8 Regional Office Center
Medical 8 Regional Office Center
Dennis Nelson
Remodel of Dental Facility
2360 E. Pershing Boulevard
23W E. Pershing Boulevard
Cheyenne, WY 82W7
Cheyenne, WY 82001
Centennial Bank of the West
Centennial Bank of the West
Wyeti and Associates
PM:
f 951,978.00 Nov-99
May-00 22%
Fort Collins, CO
4650 Royal Vista Circle
1065 S. Pear Street
Michael Bac fund
New C istruction 2 story Facidity
Fort Collins, CO 80525
Denver, CO 90210
Superintendent:
(970) 454-4141
Dennis Wyatt, Architect
Don Myers
Bill Fan, CEO
303696.1717
Centennial Bank
Eaton Bank
Bank Hollings
PM:
f 141,189.00 Mar-00
May-00 15%
Del Camino
2700 47th Ave.
Centennial Bank of the West
Curtis Naithauer
Interior Remodel -Tenets finish
Greeley. CO W634
4650 Royal Vista Circle
Superintendent:
Bill Fair
Fort Collins, CO 80525
Glen Hoopes
970-454-4141
970454-4141
Boyd Lake Vehicle Storage Bldg.
State of Colorado Parks Division
State of Colorado Parks Division
PM:
f 96,714.00 Feb -DO
Apr-00 35%
Boyd Lake State Park
3842 South Mason 0202
3842 South Mason 0202
Curtis Naibauer
Loveland, CO
Fort Collins, CO 80525
Fort Collins. CO W525
New Construction
Mr. Ed Holmberg
Mr. Ed Holmberg
970-2264Ml
970-2266641
Building 207 Renovation
Operational Contracting Division
Operational Contracting Division
PM:
f 1,030,681.00 Aug-99
Apr -DO 19%
F.E. Warren Air Force Base
Building a206, F.E. Warren AFB
Building N208, F.E. Warman AFB
Dennis Nelson
Cheyenne, WY
Cheyenne, WY S2005
Cheyenne, WY 82005
Superintendent:
Remodel of Existing Historic Building
Ms. Darlene Faulkner
Ms. Darlene Faulkner
Billy Holmes
307-773.3917
307-773-3917
VA Outpatient 8 Dental Remodel
Veterans Administration Center
Tobin and Associates
PM:
f 441,871.00 Dec-99
Apr-00 28%
Cheyenne, WY
2360 E. Pershing
"
P.O. eon
Denny Nelson
Remodel Medical Facility
Cheyenne,82W1
Cheyenne. W
WY 82W3
Superintendent
Fran FriMauf/Jane Jordan
enTobin
Ken Tobin, Architect
Dennis Nelson
307-778-7367
307632-3144
Corman Mechanical Inc.
Carman Mechanical Inc.
Growling Beer Co., Inc.
PM:
f 135,163.00 Dec-99
Mar -DO 22%
1040 36th Steel
1040 36m Street
2330 4th Avenue
Curtis Naibauer
Evans, CO 80620
Evans, CO 00520
Greeley, CO W631
Superintendent:
New Construction Sled Building
George Coman
970-3536964
Curtis Naibauer
Boulder Ranger Station
USDA Forest Service
USDA Forest Service
PM:
f 1,503,624.00 Oct-99
Mar-00 19%
Boulder. CO
204 W. Prospect Road
1311 S. College Avenue
John Sohl
New Construction, 2 Story 15,WOSF
Fort COBns, CO OD526.2096
Fort Collins, CO 80524
Superintendent:
Dennis Donovan
Chris Ida
Glenn Hoopes
970498.1024
970498-2742
VA Lobby Renovation .3 Phases
VA Medical Center
VA Medical Center
PM:
f 1,326,675.00 Apr-99
Feb-00 22%
1056 Clermont Street
1055 Clemorrt Street
1055 Clemons Street
Mike Backlund
Denver, CO
Denver, CO
Denver, CO
Superintendent:
Remodel of Existing Medical Facility
Pat Amidon
Pat Amidon
Roger Childers
303-3934690
303-3934690
Projects Completed Last 5 Years
Growling Bear Co. Inc, 2330 4th Avenue, Greeley, CO 90631 Plane: (970) 353.6964 Fax: 1970) 353-6974
page 11
Final %of Work
Contract Comp- With Own
Pralacf/DeserlOtloNLoeation
Owner
ArchitecHEnginser
Amount start Ntlon Fours
GSA 2nd Floor Renovation
General Services Administration
RB+B
PM:
$ 362,162.00 Dec-99 Mar-00 32%
Denver, CO
Public Buildings Service
315 E. Mountain Ave., Suite 100
Michael Backlund
Remodel of Existing Facility
P.O. Box 25546, Bldg. 41
Fort Collins, CO 80524-2913
Superintendent:
Denver Federal Center
Rebecca Spears, Architect
Roger Childers
Denver, CO 80225-0546
970.484-0117
Walton Building Renovation
Weld County Govemment
Bley Associates
PM:
$ 938,462.00 Jan-99 Feb-00 20%
5400 W. 11th Ave
91510th Street
2020 Clubhouse Drive
Curtis Nsibauer
and O SMI
Greeley, CO 80631
Greeley, CO 80632
Superintendent
e�
of Existing
fisting Facility
Pat Persichino
Loren Bley, Architect
Phil Hershman
35,000 SF
970-356-4000 Ext. 4224
970-330-3322
Eaton Country Club
Eaton Country Club
Growling Bear Co., Inc.
PM:
$ 480,611.00 Aug-99 Feb-00 22%
37661 weld county Rd 39
P.O. Box 240
2330 4th Avenue
Curtis Naibauer
Eaton, CO 80815
Eaton, CO 80615
Greeley, CO 80631
Superintendent:
Design Build Addition and Remodel
Rick Colo, Owner
John SON, Architect
Junior Morgan
970454-2106
970-353.6964
Construct Vault Tdlels
Rocky Mountain National Park
Rocky Mountain National Park
PM:
$ 112,377.85 Jun-'99 Jan200 15%
Estes Park
1000 HWY 36
1000 HWY 36
Curtis Naibauer
Rocky Mountain National Parks
Estes Paris, CO 80517
Estes Park, CO 80517
Anne Vrktore
Anne ViWOra
Nederland Post OFce
Centennial Bank Holdings, Inc.
Growling Beer Co., Inc.
PM:
$ 908,117.00 Jun-99 Dec-99 16%
Nederland, Colorado
2700 4m Avenue
2330 4th Avenue
Curtis Nsibsuer
New Construction 7,000 at, lstory
Greeley, CO 80634
Greeley, CO 80831
Superintendent:
R.B. Holmes - President
John Sohl, Architect
Kelly Schimdt
970339-3456
970-353.6964
Rocky Mountain National Park
National Park Service
Rocky Mountain National Park
PM:
$ 297,852.98 -� Nov'99 15%
Vault Toilets -Various locations
Rocky Mountain National Park
1000 ENVY 36
Curtis Naibsuer
in Rocky Mountain Nat. Park
1000 HWY 36
Estes Park, CO 80517
Superintendent:
Estes Park, CO $0517
Charlie Kum
Scott Fabian
Charlie Kurt
Chateau at Sharmar Village
CCMK Architecture iL Planning
Growling Bear Co., Inc.
PM:
$ 3,560,734.24 -� Nov-' 99 20%
Pueblo, CO
318 East Oak St.
2330 4th Ave.
John Sohl
Design Build -New Construction
Ft. Collins, CO W524
Greeley, CO 80631
Superintendent:
Medical Facility
Tom Kakfl, AIA
John Sohl
Don Myers
970-493-1220
970-353-6964
Forest Service - 6 SSTs
USDA Forest Service
USDA Forest Service
PM:
$ 142,645.00 May-99 Nov-99 45%
Various Locations in N. Colorado
240 W. Prospect Road
240 W. Prospect Road
Curtis Naibauer
New construction of 6 Buildings
Fort Collins, Co 80526-2098
Fort Collins, Cc 80526.2098
Superintendent:
Dennis Donovan
Dennis Donovan
Junior Morgan
970-498.1024
970498.1024
GSA
General Services Administration
RS+B
PM:
$ 818,957.00 Jul-99 Oct-99 28%
3nd 6 4th Floor Renovation
Pudic Buildings Service
315 E. Mountain Ave., Ste 100
Michael Backlund
Cheyenne Wyoming
P.O. Box 25546,BWg. 41
Fore Collins, CO 80624.2913
Superintendent:
12,000 at Remodel 6 HVAC upgrades
Denver Federal Center
Rebecca Spears
Roger Childers
Denver, CO 80225-0546
970484-0117
Projects Completed Last 5 Years
Growling Bear Co, Inc, 2330 4th Avenue, Greater, CO a0931 Phone: (970) 3534994 Fax: (970) 3534971
page 12
Final %of Work
Contract Comp- With Own
ProjectlDescriotiordLocation
Owner
ArchkeeMnakrser
Amount Start lotion Forces
Rocky Mountain National Pads
Rocky Mountain National Park
Rocky Mountain National Park
PM:
$ 149.646.02 Apr-'99 Oct-'99 15%
Vault Toilets -Various loca9ons in
1000 HWY 36
1000 HWY 36
John Tripp
Rock Cut
Estes Park, CO W517
Estes Park, CO 80517
Anne Vktcra
Anne Viktora
Donn Building 2"
F.E. Warren Air Force Base
F.E. Warren Air Force Base
PM:
$ 3,014,352.00 Sep-98 Oct-99 30%
F.E. Warren Air Force Base
Building 11208
Building a208
Dennis Nelson
Remodel of Historic Building
Cheyenne, WY 82005,5000
Cneyerare. WY BM550W
Superintendent:
44,000 SF
Darlene Faulkner
Darlene Faulkner
Scott Sauer
307-7733917
307.773.3917
Air Force Academy Hospital ADAL
US Air Farce Academy
U.S. Corps of Engineers
PM:
$ 1,373,664.00 Oct-96 Sep-99 12%
US Air Force Academy
8110 Indusbial Drive, Suite 200
Omaha District
Michael Backlund
Colorado Springs. CO
Cokxado Springs. CO
Superintendent:
7000 SF New Addition and 4000 SF
Carrot Mohr
John Tripp
Remodel
719-333-2735
Centennial Bank
Centennial Bank of the West
J.W. Miller & Associates
PM:
$ 403,300.00 Jul-99 Sep-99 28%
Longmont, Colorado
4650 Royal Vista Circle
230 S. Main
Curtis Naihauer
12000 SF Tenant Finish
Fort Collins, CO 80525
Longmont, CO
Superintendent:
(970) 454-4141
303-772-4118 -
Glen Hoopes
Bill Farr, CEO
Jerry Miller, Architect
Roads Repair Phase III
F.E. Warren Air Force Base
Banner Associates, Inc.
PM:
$ 977,216.00 Jun-98 Sep-99 30%
F.E. Warren Air Force Base
Building #208
Architects & Engineers
Curtis Narbauer
Roads Repair & Lifi ity Upgrades
Cheyenne, WY 82006.5000
620 Plaza CtkM
Superintendent:
Phase III -New Roads. Parking leas, orb
Sue Nagel
Laramte, WY 82070
Dennis Nelson
& gutter, corn Ones, utils. & site lighting
307-773-3917
Buckley Air national Guard
Buckley Air National Guard
Pahl -Pahl -Pahl
PM:
$ 4,534,944.00 18%
Greeley, CO
USPFO for Colorado
1900 Grant Street
Michael Baddund-�'�
High Profile Defense Initiative Mobile
660 S. Allow Street
Denver, CO 80203-4321
Superintendent:
Defense Facility-29,000 of, Hi Security
Aurora, CO 80011.9551
Bob Grubb. Architect
Junior Morgan
Motion Sensors, Manned Guard Sta's
Patty McCauley
303-861-7147
New Construction
303-340-9946
Retaining Wall
Rocky Mountain National Pack
Rocky Mountain National Packs
PM:
$ 161.059.03 Jun-'99 Aug-'99 65%
Trail Ridge Road -Rock Cut
1000 HWY 36
2000 HWY 36
Curtis
Rocky Mountain National Park
Estes Park, CO B0517
Estes Pack, CO 80517
Anne Vildors
Anne Vadors
Building 314 Rergvalion
F.E. Warren Air Force Base
GrovAirg Bear co., Inc.
PM:
9 927,976.00 Apr-99 Jul-99 19%
F>E> Warren Air Force Baas
Building 0208
2330 4th Avenue
Demos Nelson
Design/Build Pr0j.-Histaic Remodel
Cheyenne. WY 82005.5000
Greeley, CO 80831
Superintendent:
HVAC, Elect., Pbg., H.C. Access.
Darlene Faulkner
John SoN, Architect
Whitey Panda
Aerobic and Dance Area - 24.000sf.
307-773-3917
970-353-6964
AT & T Upper Midwest Fiber
AT&T
MCB Architects
PM:
$ 1,310,887.45 Nov-'98 Jul-199 15%
Precast ConcreteP300's
1425 Champs St. Room 100
1790 S. Bellaire St. Suite 800
Curtis Naibauer
Denver, CO 80202
Denver, CO 90222
Ben Lough
303-758.7858
303-620.2191
Projects Completed Last 5 Years
Growling Bear Co, Inc., 2330 4th Avenue, Gnssley, CO OMI Plane: (970) 353.6964 Fax: (970) 353-6974 page 13
Final
-
%of Work
Contract
Camp-
With Own
_ ProlecllDascrlptbNLoeatlon
Owner
ArchltectfErainsar
Amount
Start
lotion
Forces
North Range Behavioral Health
North Range Behavioral Health
Roberts Architects
PM:
$
1,118,92&00
Oct-98
Jun-99
15%
1306 11M Ave
1306 11ih Ave.
WO 9th Street
Curbs Natbeuer
Greeley, Colorado
Greeley, CO 50831
Greeley, CO W631
Superintendent:
New Construction of Medical Facility
Errol E. Wilcox. Director
970-353.7232
Glen Hoopes
15WOSF
970.353.3086
Wayne Roberts, Architect
rUnion
Croft
COH C27t
CollegeColleCredit
Steel& Associates
tesSui
PM:
$
471,952.00
Feb-99
Jun-99
18%
i
2901 venue
2308 West eet, 10/
CurNaibauer
Greeley, CO
Greeley, CO 80631
Greeley, CO a0631
Superintendent
New Construction of 4000 SF Building,
Jody Seestro n
303353-6363
Scott Fabian
Drive Thu, and Sitework
970-351-2434
Larry Steele, Architect
Rodarte Center Addition
City of Greeley
Growling Bear Co., Inc.
PM:
$
221,450.00
Mar-99
Jun-99
21 %
920 A. Street
1300 A. Street
2330 4th Avenue
Curtis Naibauer
Greeley, CO a0631
Greeley. CO
Greeley, CO 80631
Superintendent:
Design Build Remodel of 2500 SF
Bill Sterling
John Sohl, 970353-6964
Phill Hershman
and Addition
970-350-9795
Centennial Area Health Education
Centennial Am Health Education
Growling Bear Co., Inc.
PM
$
403,740. W
Jan-99
May-99
25%
4650 W. 20th Street
1024 91h Avenue, Suite 8
2330 4th Avenue
Curtis Neibauer
Greeley, CO 80634
Greeley, CO 80634
Greeley, CO SMI
Superintendent:
Design Build New Construction of
Dennis Stocker
John SON,Architect
Scott Fabian
5000 SF Building tl Sitework
970-351-0755
970-353-6964
VA Medical Center
VA Medical Center
VA Medial Center
PM:
E
351,479.88
Oct-198
FeV99
15%
2nd Floor Remodel
2360 E. Pershing Blvd
2360 E. Pershing Blvd.
Dennis Nelson
2360 E. Pershing Blvd.
Cheyenne, WY WWI
Cheyenne, WY 82001
Cheyenne, WY SMI
Jane Jordan
Jane Jordan
307.778.7329
307-778-7329
Platte River Steel
Platte River Steel
Wall E. Bedinger
PM:
$
125,067.00
Oct-98
Jan-99
45%
31455 WCR 391/2
31455 WCR 3912
1011 37th Ave. Ct. #101 B
Curtis Natbauer
Greeley, Colorado 50631
Greeley, CO 90631
Greeley, CO 80634
1000 Sf New Addition, Steel Building
970356-2326
970-346-0912
Building 9304Renovabon
F.E. Warren Air Force Base
F.E. Warren Air Force Base
PM:
$
629,051.00
Oct-98
Jan-99
27%
F.E Warren Air Force Base
Building N208
Building #209
Dennis Nelson
Remodel 23,000 SF Historic Building
Cheyenne, WY 82005-5000
Cheyenne, WY 82W5.5000
Sue Negri
Sue Nagel
307-7733917
307-7733917
Projects Competed last 5 Years
Curtis C. Naibauer, continued
Selected Projects:
CU Renovation to Behavioral Genetics, Boulder, CO $ 375,610.00
CSU Corbett Hall, Fort Collins, CO $ 675.324.00
New West Bank, Eaton, CO $ 1,309,573.00
CSU Chemistry Remodel, Fort Collins, CO $ 264,868.00
CSU Equine Lab, Fort Collins, CO $ 364,901.00
CSU Stallion Lab, Fort Collins, CO $ 292,911.00
Island Grove Village Apartments, Greeley, CO $ 1,080,881.00
MLS Properties, Greeley, Co. $ 250,000.00
Stephens Center, Greeley, Co. $ 822,000.00
V A Medical Center, Cheyenne, Wy. $ 467,000.00
Hawkstone Clubhouse, Eaton, Co. $ 375,887.00
Camelot Apartments, Greeley, Co. $ 504,680.00
Weld County Training Center $ 822,040.00
Greeley, Co.
Boulder Ranger Station $ 1,130,000.00
Boulder, Co.
Weld County Walton Building- Renovation $ 850,000.00
North Range Behavioral Health $ 1,150,000.00
Greeley, CO
Upgrade roads and infrastructure $ 1,200,000.00
F.E.Warren Air Force Base, Cheyenne, WY
$ dC Cost of installation and painting
3. Exterior rail panels - Detail #3 - Sheet A3.2- cut steel and copper
sheet - pre -assembled and painted panels, typically 216" x 41511, to
be delivered to site by artist for installation by Contractor. Artist
will provide placement instructions. Panel weight to be confirmed
and installation approved by structural engineer and architect.
Contact artist for panel weights.
$_2 R97—_-Cost to install (Cut panels by other)
$_0 20 Credit to delete horizontal rails as indicated on
elevations
4.Floor Pattern - Detail #2 -- Sheet A1.5 - saw -cut design-- additional
design work on floor as shown on plans to be installed by Contractor.
Artist will provide scaled detail drawings and supervise
installation.
$ Cost to install
9. PRICES
The foregoing prices shall. include all labor, materials, transportation,
shoring, removal, dewatering, overhead, profit, insurance, etc., to cover
the complete Work in place of the several kinds called. for.
Bidder acknowledges that the OWNER has the right to delete items in the
Bid or change quantities at his sole discretion without affecting the
Agreement or prices of any item so long as the deletion or change does
not exceed twenty-five percent (25%) of the total Agreement Price.
RESPECTFULLY
~CS M D:
Signature evin Shironaka Date
President
Title
` License Number (If Applicable)
44'Nid is by corporatio
,rxt evrt,,Gary ronaka _
Address 2330 4th Ave.
Telephone -
COLORADO DEPARTMENT OF TRANSPORTATION
PROJECT NO.
ANTI -COLLUSION AFFIDAVIT
LOCATION
I hereby attest that I am the person responsible within my firm for the final decision as to the price(s) and amount of this
bid or, if not, that I have written authorization, enclosed herewith, from that person to make the statements set out below on
his or her behalf and on behalf of my firm.
I further attest that:
1. The price(s) and amount of this bid have been arrived at independently, without consultation, communication or
agreement for the purpose or with the effect of restricting competition with any other firm or person who is a bidder
or potential prime bidder.
2A. Neither the price(s) nor the amount of this bid have been disclosed to any other firm or person who is a bidder or
potential prime bidder on this project, and will not be so disclosed prior to bid opening.
2B. Neither the prices nor the amount of the bid of any other firm or person who is a bidder or potential prime bidder on
this project have been disclosed to me or my firm.
3A. No attempt has been made to solicit, cause or induce any firm or person who is a bidder or potential prime bidder to
refrain from bidding on this project, or to submit a bid higher than the bid of this firm, or any intentionally high or non-
competitive bid or other form of complementary bid.
3B. No agreement has been promised or solicited for any other firm or person who is a bidder or potential prime bidder
on this project to submit an intentionally high, noncompettive or other form of complementary bid on this project.
4. The bid of my firm is made in good faith and not pursuant to any consultation, communication, agreement or
discussion with, or inducement or solicitation by or from any firm or person to submit any intentionally high, noncom-
petitive or other form of complementary bid.
5. My firm has not offered or entered into a subcontract or agreement regarding the purchase or sale of materials or
services from any firm or person, or offered, promised or paid cash or anything of value to any firm or person,
whether in connection with this or any other project, in consideration for an agreement or promise by any firm or
person to refrain from bidding or to submit any intentionally high, noncompetitive or other form of complementary bid
or agreeing or promising to do so on this project.
6. My firm has not accepted or been promised any subcontract or agreement regarding the sale of materials or
services to any firm or person, and has not been promised or paid cash or anything of value by any firm or person,
whether in connection with this or any other project, in consideration for my firm's submitting any intentionally high,
noncompetitive or other form of complementary bid, or agreeing or promising to do so, on this project.
7. 1 have made a diligent inquiry of all members, officers, employees, and agents of my firm with responsibilities
relating to the preparation, approval or submission of my firm's bid on this project and have been advised by each of
them that he or she has not participated in any communication, consultation, discussion, agreement, collusion, or
other conduct inconsistent with any of the statements and representations made in this affidavit.
8. 1 understand and my firm understands that any misstatement in this affidavit is and shall be treated as a fraudulent
concealment from the Colorado Department of Transportation, of the true facts relating to submission of bids for this
contract.
I DECLARE UNDER PENALTY OF PERJURY IN THE SECOND DEGREE, AND ANY OTHER APPLICABLE STATE OR
FEDERAL LAWS, THAT THE STATEMENTS MADE ON THIS DOCUMENT ARE TRUE AND COMPLETE TO THE BEST
OF MY KNOWLEDGE. _
Contractor's firm or company name
By a'
De
Growling Bear Co., (Inc.)
Title
President
2nd contractors firm or company name. (If joint venture.)
By
Date
Title
.Sworn to before me this � 5 day of, �� pE
` � ````,Nt t II E.Pr ��i, 2M S
'�
.`` •• •.'9i
a antic
�OTgy y Z
� yes i
(n : `•
!✓@LtG
My commission expi
,
'+,Ok ZOLO
NOTE: ihis document must be signed in ink.
1,%%
r �"4
CDOT Form rreoe 1/02
COLORADO DEPARTMENT OF TRANSPORTATION Project No.:
UNDERUTILIZED DBE (UDBE) BID
CONDITIONS ASSURANCE Location:
Instructions: Contractor — Complete and submit this form with your bid. Report only Underutilized DBE (UDBE) participation percentages which
qualify under the contract goal specification for this project.
POLICY
It is the policy of the Colorado Department of Transportation that underutilized disadvantaged business enterprises have maximum opportunity to
participate in the performance of contracts financed with federal, state or local entity funds.
UNDERUTILIZED DBE PARTICIPATION COMMITMENT
1) Will your company's Underutilized DBE (UDBE) participation commitment meet contract goals? ❑ Yes ❑ No
2) Total eligible Underutilized DBE (UDBE) percentage amount from Box A below: %
3 List the UDBE firms, committed work items, and eli ibla UDBE percent of your bid that ou are committing to each
UDBE FIRM NAME
CERTIFICATION
COMMITTED
SUBCONTRACT
ELIGIBLE
EXP. DATE
WORK ITEM(S)
CATEGORY
UDBE %"
_
® Subcontractor
1.
...
i,
❑Supplier ❑Broker
o
/o
2.r (�✓✓U.
/ /
4 , ^' ��'d''^
Subcontractor
❑ Supplier ❑ Broker
p
❑ Subcontractor
3.
/ !
El Supplier ❑Broker
%
❑ Subcontractor
4
/ /
❑ Supplier ❑ Broker
❑ Subcontractor
5.
1 /
❑ Supplier El Broker
%
❑ Subcontractor
❑ Supplier ❑ Broker
BOX A: TOTAL ELIGIBLE UDBE PERCENTAGE AMOUNT:
%
Round percentage amounts to the nearest hundredth
' Additional instructions on how to calculate the actual eligible amounts and percentages for the subcontractor, supplier, and broker categories
are available on the CDOT Form #715 and in the "Counting DBE Participation Toward Contract Goals and CDOT's annual DBE goal" section of the
"DBE — Definitions and Requirements" in the Standard Special Provisions.
I understand that, if my company is determined to be the low bidder for the contract on this project, I must submit a completed
CDOT Form #715 CERTIFICATION OF UNDERUTILIZED DBE PARTICIPATION for each firm listed on this form to the
Transportation Department by 4:00 pm the day after the bids are opened. The actual amounts submitted on each CDOT Form
#715 must equal or exceed the percentage commitments documented on this form. In addition, if my company does not
meet the DBE/UDBE goal for this project, 1 must submit a completed CDOT Form #718 DBE GOOD FAITH EFFORT
DOCUMENTATION before the above stated deadline. CDOT Form #715s submitted for Firms not included on this form, OR
for amounts exceeding those listed on this form, will be accepted but NOT counted as Good Faith Efforts. Only the efforts
the contractor made gEW to the bid opening will count as Good Faith Efforts.
I understand my obligation to abide by the policy stated above. I shall not discriminate on the basis of race, color, age, sex, national
origin, or handicap in the bidding process or the performance of contracts.
I DECLARE UNDER PENALITY OF PERJURY IN THE SECOND DEGREE, AND ANY OTHER APPLICABLE STATE OR
FEDERAL LAWS, THAT THE STATEMENTS MADE IN THIS DOCUMENT ARE TRUE AND COMPLETE TO THE BEST OF MY
KNOWLEDGE.
Company Name: Date:
Growling Bear Co., (Inc.) I Q resit?
Title -
President
Previous editions may not be used CDOT Form 714 08104
COLORADO DEPARTMENT OF TRANSPORTATION
CERTIFICATE OF PROPOSED
Project No.:
UNDERUTILIZED DBE (UDBE)
Project Code (SA#):
PARTICIPATION
Location:
Form #: of
Prime Contractor — Send completed/signed form to the Business Programs Office (instructions on second page).
(Nuit: t: see as LJ-K part 2b.55, and the "DBE -Definitions and Requirements" in the Standard Special Provisions, for further information concerning
counting DBE participation of subcontractors, suppliers and service providers toward the project's UDBE goal.)
PART 1 a — SUBCONTRACT
NAME OF UDBE FIRM
TIER
CERTIFICATION #
EXPIRATION ELIGIBLE UDBE SUBCONTRACTDATE AMOUNT
ACTUAL CONTRACT AMOUNT
ITEMS OF WORK SUBCONTRACTED:
PART 1 b — SUPPLY CONTRACT
If the supplier is a UDBE "Manufacturer" of the item(s):
• ACTUAL UDBE AMOUNT = Entire expenditure for materials and supplies including co
• ELIGIBLE UDBE SUPPLY AMOUNT = I (ACTUAL UDBE AMOUNT) X 100%
r= �
If the supplier is a UDBE 'Regular Dealer' of the item(s): lg
• ACTUAL UDBE AMOUNT = Entire expenditure for materials and su }( co
• ELIGIBLE UDBE SUPPLY AMOUNT = (ACTUAL UDBE AMOK
If the supplier is neither a "Manufacturer' nor a
NAME OF UDBE FIRM
MATERIALS SUPPLIED:
PART 1 c —
CONTRACT
by the firm
services provided by the firm
I - SERVICE / BROKER CONTRACT.
NT
Transportation service `auling) fees/commissions are to be counted toward contract goals in this section (provided the trucker is NOT
classified as a "Manufacturer" or a "Regular Dealer' for the materials supplied). Examples of other services to include in this section
would be brokering, bonding, consulting, security guards, and insurance.
For a UDBE "Service/Broker Contract":
• ACTUAL UDBE AMOUNT = Entire expenditure for services rendered including cost of any materials/supplies provided by the firm
ELIGIBLE UDBE SERVICE FEE AMOUNT = [ (ACTUAL UDBE AMOUNT) — (Cost of any materials and supplies) ]
(NOTE: The amounts that count toward UDBE goals are limited to the compensation retained by the UDBE broker/agent for services rendered, provided
the fee/commission is determined by CDOT to be reasonable and not excessive as compared with fees customarily charged for similar services.)
NAME OF UDBE FIRM
CERTIFICATION #
EXPIRATION
ACTUAL UDBE ELIGIBLE UDBE SERVICE FEE
DATE
AMOUNT AMOUNT
SERVICES RENDERED:
,vy101110 wlllw rrevious edmons may not be used CDOT Form 715 05/03
PART 2 - UDBE PARTICIPATION SUMMARY
A) What is the total dollar value of this proposed subcontract, supply contract, OR service/broker
contract that is eligible for counting toward contract goals?
(NOTE: Provide in actual subcontractor dollars and not prime contract prices)
A>
A = [ TOTAL FROM "ELIGIBLE" COLUMNS IN PART 1 ]
B) What is the total dollar value of proposed subcontracts that are eligible for counting towards
B>
contract goals from prior sheets/forms?
C) What is the accumulative value of proposed subcontracts that are eligible for counting towards
contract goals?
C
C=[A + B]
D) What is the original contract bid total?
D>
E) What is the accumulative percent of contract bid total subcontracted to all underutilized DBEs?
E=[(C + D) X 100]
PART 3 - PRIME CONTRACTOR CERTIFICATION AlkFV
certify that: s
• my company has met the contracted UDBE goals or h it a DOT Form #718, DBE Good Faith Effort
Documentation.
• my company has accepted a proposal from In DSu med above.
my company has notified the proposed f contracted UDBE commitment.
• my company's use of the propose s c . he items of work listed above is a condition of the contract award.
my company will invite the pr Cis a to attend the preconstruction conference.
• my company will not us a s subc Factor for the proposed UDBE subcontractor's failure to perform under a
fully executed subc ny complies with the definitions and requirements section of the DBE Special
Provisions. : F *,
I understa a to, wit the information shown on this form will be considered grounds for contract termination.
I declare under p ty e the second degree, and any other applicable state or federal laws, that the statements
made on this doc true and complete to the best of my knowledge.
Prime Contractor Name: Growling Bear Co., _JInc.) Date: YV 0457
Officer Signature and Title:
FORM INSTRUCTIONS
Prime Contractor: 6. Retain a photocopy for your records.
1. An officer of the contractor(s) must complete this form. 7. Send original to:
2. Include only DBE firms which meet the underutilized criteria in Colorado Department of Transportation
the contract goal specification for this project (i.e., UDBE firms). Business Programs Office
3. Complete ONLY ONE section for Part 1 (1a, 1b, OR 1c) 4201 E. Arkansas Ave.
4. Complete ALL sections of Part 2 and Part 3 Denver, Colorado 80222
5. Submit a separate CDOT Form #715 for EACH proposed UDBE. FAX: (303) 757-9019
Original — Business Programs Office Previous editions may not be used COOT Form 715
PAGE 2