HomeMy WebLinkAboutCHANGE ORDER - REQUISITION - 24185" SEP-12-2005 MON 02:18 PM CFO ENG, FAX N0. 9702216378 P. 04 Change Order Farm Znll snag Department PROJECT TITLE: 2005 Street Maintenance Program PROJECT NUMBER: 320200 (Concrete Project Phase II - Bid #5847) CONTRACTOR: Vogel Concrete (PO #5501541) CHANGE ORDER NUMBER: 4 n preparing Change orders show to onder as separate numbered paragraphs the Tollowing. 1. Reason for change. 2. Description of change. 3: Change in contract cost. 4. Change in contract time. 1.82. See attached invoice for details 3. The contract cost will increase by $40,119.72 4. There is no change in contract time. ORIGINAL CONTRACT COST $1,379,095.11 TOTAL APPROVED CHANGE ORDERS $46,735.76 TOTAL PENDING CHANGE ORDERS $45,739.00 TOTAL THIS CHANGE ORDER $40,119,72 TOTAL % OF THIS CHANGE ORDER 2,91% TOTAL C.O. % OF ORIGINAL CONTRACT 9.61% ADJUSTED CONTRACT COST $1,511,689.59 ACCEPTED BY: REVIEWED BY: ACCEPTED BY: APPROVED BY: APPROVED BY: co: Accounting Purchasing Contractor Rojoct File d�az DATE: ( ctor's Rep esenta ' e) DATE: J,ect Engi er w DATE (Project Manager - Engineering) DATE: DATE: (Purchasing Agent over $30,000) iEngineering Department , 281 North College Avenue • P.O. Box 550 - Fort Coitigs, CO 80522-0580 - (970) 221-6605 SEP-12-2005 MON 02:18 PM CFC ENG, FAX NO. 9702216378 P. 05 2005 Concrete Project - Phase II Vogel Concrete Bid No. 5847 Change Order No: 4 Date: 902005 1. Reason For Change: a. Additional concrete repair was added in the Golden Meadows area during construction. 2. Description Of Change: a. Add quantities to the contract for additional concrete repair. 3. Change In Contract Amount: Item oty Unit Unit Cast Total Cost a. 304.07 Aggregate Base Course 150 TON $ 26.37 $ 3,955.50 403.50 Temporary Patching 40 TON $ 155.10 $ 6,204.00 608.03 Apron - R & R 510 5F $ 6,02 $ 3,376.20 608,06 Driveover Curb, Gutter and 6" Sidewalk - R & R 365 LF $ 37.22 $ 14,328.70 608.08 Driveover Curb, Gutter & Drive Approach - R & R 173 LF $ 37.22 $ 6,439.06 008,10 Vertical Curb, Gutter & 64 Sidewalk - R & R 58.5 LF $ 41.38 $ 2,419.56 608.22 Pedestrian Access Ramp, Driveover Curb - R & R 50 LF $ 44.46 $ 2,223,00 60826 Truncated Dome Panel (2' X 2') 30 SF $ 39.00 $ 1,172.70 TOTAL. CHANGE IN CONTRACT AMOUNT $ 40,119.72 4. Change In Contract Time a. 6 daye are added to the contract TOTAL. CHANGE IN CONTRACT TIME 6 Days R5643500A Shipped From VOGEL CONCRETE 1313 BLUE SPRUCE DR, SUITE B FORT COLLINS CO 80524-2001 Ordered 09/12/2005 Freight Requested 09/12/20050rder Taken By Delivery REQUISITION 09/12/2005 CITY OF FORT COLLINS Page - 1 Order Number 24184 - 000 - OR Branch/Plant 1 Ship To ENGINEERING DIVISION CITY OF FORT COLLINS 281 N COLLEGE AVE FORT COLLINS CO 80521 Line Description / Supplier Item Quantity UOM Unit Price Extended Price Branch _.._. _�' Plant 1.000 ,/Lot LS .0000 45,739.00 410 2005 Street Maintenance Per CO #3 to PO #5501541. Account Number Buyer Number 320200.526700 4 Totals 45,739.00 SEP-12-2005 MON 02:17 PM CFC ENG, ," FAX NO. 9702216378 P. 02 E� Engineering Department Change Order Form PROJECT TITLE: 2005 Street Maintenance Program PROJECT NUMBER: 320200 (Concrete Project Phase II - Bid #5847) CONTRACTOR: Vogel Concrete (PO #5501541) CHANGE ORDER NUMBER: 3 n prepanng change orders show to order as separate numbered paragraphs the following: 1. Reason for change. 2. Description of change. 3: Change in contract cost. 4. Change in contract time. 1.&2. See attached invoice for details 3. The contract cost will increase by $45,739.00 4. There is no change in contract time. ORIGINAL CONTRACT COST $1,379,096.11 TOTAL APPROVED CHANGE ORDERS $46,736.75 TOTAL PENDING CHANGE ORDERS $0,00 TOTAL. THIS CHANGE ORDER $45,739.00 TOTAL. % OF THIS CHANGE ORDER 3,32% TOTAL C.O. % OF ORIGINAL CONTRACT 6,7fY ADJUSTED CONTRACT COST $1,471,569.87 ACCEPTED BY: b-'74'z Z� z DATE: f REVIEWED BY. / �,L_/ Ili Yy� DATE: I ri ACCEPTED BY: PATE: �'•/Z• (Project Manager- Engineering) APPROVED BY: APPROVED BY: cc: Accounting Purchaslnrg Convartor Project File DATE: DATE: (Purchasing Agent over $30,000) Engineering Department, 231 North College Avenue, Y.O. Box 590 - Fort Collins, CO 80522-0590 (970) 221-6605 SEP-12-2005 MON 02:17 PM CFC ENG, FAX NO. 9702216378 P. 03 2005 Concrete Project - Phase II Vogel Concrete Sid No. 5847 Change Order No.: 3 Date: 9/8/2005 1, Ronson For Change: a• Additional traffic control is necessary on Mulberry Street between College and Whitcomb to avoid multiple trafllc control companies working in the same area. The concrete traffic control company will be ut lized for all construction phases including oonerete, milling and paving, and asphalt overlay at this location. Also, additional traffic control Is needed in the Golden Meadows area, due to added concrete repairs. 2. Description Of Change: a. Add traffic control quantities to the contract for all construction phases. 3. Change In Contract Amount: Item Qty Unit Unit Cost Total Cost a. 614.03 Channsliring Banells 1500 DAY/EA $ 0.75 $ 1,125.00 614.00 Type III Barricade Without Light 600 DAYI A S 3,70 $ 2,220.00 614.07 Size A Sign With Stand 1000 DAY/EA $ 1.33 $ 1,330,00 614.03 Size B Sign With Stand 1100 DAY/EA $ 1.54 $ 1,694.00 614,11 Cane With Reflective Strip 3000 DAY/EA $ 0.63 $ 1,890.00 614.17 Treffic Control Supervisor 200 HR $ 33.00 $ 6.600.00 614.18 Flagging 1600 HR $ 19.30 $ 30,880.00 TOTAL CHANGE IN CONTRACT AMOUNT $ 45,739.00 4. Chango In Contract Time a. There is no change in contract time TOTAL CHANGE IN CONTRACT TIME 0 Days