Change Order Form
if
Basineering Department
PROJECT TITLE: 2005 Street Maintenance Program
PROJECT NUMBER: 320200 (Bid #5839)
CONTRACTOR: Lafarge Northern, Inc. (PO #5502237)
CHANGE ORDER NUMBER: 6
n preparingchange orders show in order as separate numbered paragraphs the o omng:
1'. Reason for change. 2. Description of change. i
3. Change. in contract cost. 4. Change in contract time.
1 &2. See attached sheet for detail.
N
3. The contract cost will increase by $ 23,274.98
4. There will be no, change in contract time.
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O. WOF ORIGINAL CONTRACT
ADJUSTED CONTRACT COST
(Assuming all change orders approved)40
ACCEPTED
SUBMITTED
APPROVED
APPROVED
ACCEPTED BY:
APPROVED BY:
cc: Purchasing
Accounting
Contractor
Project File
Head
(Purchasing Agent over $30,000)
$2,230.388.32
$89,417.46
$0.00
$23,274.98
n
1.04%
5.05%
$2,343,080.76
DATE:
DATE: • to - of
DATE: CJ �L�J `v ✓
DATE:
DATE: 0ns
DATE:
Engineering Department • 281 North College Avenue • P.O. Bo: 580 • Fort Collins, CO 80522-0580 • (970) 221-6605
City of Fort Collins 2005 Asphalt Overlay Project
Lafarge North America -Bid No. 5839
Change Order No.: 6
Date: 811r"5
1 Reason For Change,
a. Additional work was required over the box culverts related to the Utilities project at Dry Creek.
2 Description Of Change:
a. Add additional quantities to accommodate soil treatment and paving over the box culverts.
3 Change In Contract Amount: See Attached
Qty
Unit
Unit Cost
Total Cost
a. 306.20 Asphalt Recycling 5 -10"
202
SY
$
1.48
$
298.96
306.10 Subgrade Preparation
1,300
BY
$
1.56
$
2,028.00
307.10 Class C Fly Ash Delivered & Spread 12" Depth @ 10%
82
TON
$
48.51
$
3,977.82
307.20 Stabilize Subgrade-Tilled, Watered & Compacted
1,300
SY
E
1.91
$
2,483.00
403.40 HBP - Grading SG
280
TON
$
31.33
$
8,772.40
403.30 HBP - Grading S, 64-28 Binder
140
TON
$
40.62
b
5,714.80
TOTAL CHANGE IN CONTRACT AMOUNT
S
23,274.98
4 Change In Contract Time
There Is no change in contract time
TOTAL CHANGE IN CONTRACT TIME
a
0 days