HomeMy WebLinkAboutCHANGE ORDER - BID - 5839 ASPHALT OVERLAY PROJECT 2004 (3)11 � Change Order Form if Basineering Department PROJECT TITLE: 2005 Street Maintenance Program PROJECT NUMBER: 320200 (Bid #5839) CONTRACTOR: Lafarge Northern, Inc. (PO #5502237) CHANGE ORDER NUMBER: 6 n preparingchange orders show in order as separate numbered paragraphs the o omng: 1'. Reason for change. 2. Description of change. i 3. Change. in contract cost. 4. Change in contract time. 1 &2. See attached sheet for detail. N 3. The contract cost will increase by $ 23,274.98 4. There will be no, change in contract time. ORIGINAL CONTRACT COST TOTAL APPROVED CHANGE ORDERS TOTAL PENDING CHANGE ORDERS TOTAL THIS CHANGE ORDER TOTAL % OF THIS CHANGE ORDER TOTAL C.O. WOF ORIGINAL CONTRACT ADJUSTED CONTRACT COST (Assuming all change orders approved)40 ACCEPTED SUBMITTED APPROVED APPROVED ACCEPTED BY: APPROVED BY: cc: Purchasing Accounting Contractor Project File Head (Purchasing Agent over $30,000) $2,230.388.32 $89,417.46 $0.00 $23,274.98 n 1.04% 5.05% $2,343,080.76 DATE: DATE: • to - of DATE: CJ �L�J `v ✓ DATE: DATE: 0ns DATE: Engineering Department • 281 North College Avenue • P.O. Bo: 580 • Fort Collins, CO 80522-0580 • (970) 221-6605 City of Fort Collins 2005 Asphalt Overlay Project Lafarge North America -Bid No. 5839 Change Order No.: 6 Date: 811r"5 1 Reason For Change, a. Additional work was required over the box culverts related to the Utilities project at Dry Creek. 2 Description Of Change: a. Add additional quantities to accommodate soil treatment and paving over the box culverts. 3 Change In Contract Amount: See Attached Qty Unit Unit Cost Total Cost a. 306.20 Asphalt Recycling 5 -10" 202 SY $ 1.48 $ 298.96 306.10 Subgrade Preparation 1,300 BY $ 1.56 $ 2,028.00 307.10 Class C Fly Ash Delivered & Spread 12" Depth @ 10% 82 TON $ 48.51 $ 3,977.82 307.20 Stabilize Subgrade-Tilled, Watered & Compacted 1,300 SY E 1.91 $ 2,483.00 403.40 HBP - Grading SG 280 TON $ 31.33 $ 8,772.40 403.30 HBP - Grading S, 64-28 Binder 140 TON $ 40.62 b 5,714.80 TOTAL CHANGE IN CONTRACT AMOUNT S 23,274.98 4 Change In Contract Time There Is no change in contract time TOTAL CHANGE IN CONTRACT TIME a 0 days