HomeMy WebLinkAboutCHANGE ORDER - REQUISITION - 2392208/01/2005 MON 14:22 FAX 970 221 6586 CITY OF FT COLLINS CLRS Q001/001 CHANGE ORDER NO.1 PROJECT TITLES City Park Intersection Moss Rock CONTRACTOR: Campana Construction Corp. PROJECT NUMBER: P.O. 5503361 DESCRIPTION: Actual quantities and items 1. Reason for change: Deduct for clean-up, done by others. 2. Description; a. Less work, credit-$142.00 3. Change in Contract Cost: minus 4. Change in Contract Time: n/a ORIGINAL CONTRACT COST TOTAL APPROVED CHANGE ORDER TOTAL PENDING CHANGE ORDER TOTAL THIS CHANGE ORDER TOTAL & OF THIS CHANGE ORDER -1t TOTAL C.O. OF ORIGNINAL CONTRACT -196 ADJUSTED CONTRACT COST (Assuming all change orders_ approved) ACCEPTED B C ntr or epkesentative ACCEPTED BY: REVIEWED BY: APPROVED BY: Project' Manager Title: Title: $142 . 00 11,130.00 0 0 -142.00 $10,988.00 DATE: 771�- DATE : %f �v S Wt44V DATE: APPROVED BY: DATE: Purchasing Agent over $30,000 ti CC., Architect Contractor Engineer Project File Purchasing