HomeMy WebLinkAboutCHANGE ORDER - REQUISITION - 23748 PLEASANT VALLEYCHANGE ORDER NO. 1
PROJECT TITLE: PLEASANT VALLEY LAKE & CANAL TRAIL
CONTRACTOR: Naranjo Civil Constructors
PROJECT NUMBER: 5903
PURCHASE ORDER NO.: 5503123
DESCRIPTION: Description of change
1. Reason for change: Added safety rails to bridge and new drawings for bridge approval
2. Description of Change:
1) CWR 1.1 - Bridge Safety Rail Addition $ 741.85
2) CWR 1.2 - New set of drawings from redlines $ 200.00
3. Change in Contract Cost: $ 941.
4. Change in Contract Time: no change
ORIGINAL CONTRACT COST $ 72,515.00
TOTAL APPROVED CHANGE ORDER $ _
TOTAL PENDING CHANGE ORDER $ _
TOTAL THIS CHANGE ORDER $ =-941.85
TOTAL % OF ORIGINAL CONTRACT, THIS C.O. 0.01%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S 0.01%
ADJUSTED CONTRACT COST $73,456.85
(Assuming all change orders approved)
ACCEPTED BY: / ✓Y� (/V- DATE: 7_ /. p 5
Contractor's Representative
ACCEPTED BY:
Project Manager
REVIEWED BY:
Title:
APPROVED BY:
Title:
APPROVED BY:
Purchasing Agent over $30,000
cc: City Clerk Architect
Contractor Engineer
Project File Purchasing
DATE: 71ik 05
DATE:
DATE:
DATE: