HomeMy WebLinkAboutCHANGE ORDER - RFP - CITY PLAN UPDATECHANGE ORDER NO.5
PROJECT TITLE: City Plan Update
CONTRACTOR: EDAW
PROJECT NUMBER:
PURCHASE ORDER NO.: 2204769
DESCRIPTION:
1. Reason for Change: Revised Scope of Work more clearly defining the additional task items
identified during the planning process for the implementation of City Plan.
2. Description of Change: The funds allow the Contractor to provide additional assistance in
the implementation of City Plan in regards to infill and redevelopment, per the revised
attached Scope of Work.
3. Change in Contract Cost: None
4. Change in Contract Time: None
ORIGINAL CONTRACT COST
$388,750
TOTAL APPROVED CHANGE ORDERS
$155.260
TOTAL PENDING CHANGE ORDERS
----------
TOTAL THIS CHANGE ORDER
0
TOTAL % OF ORIGINAL CONTRACT, THIS CO.O.:
0%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S
0.150%
ADJUSTED CONTRACT COST
$5449010
(Assuming all change orders approved)
ACCEPTED BY: L DATE: , I
SGllCdl1VG
ACCEPTED BY: A DATE: 7 710�
JPsO'Neill,
r ' Ma r
REVIEWED BY: DATE 9/7/0
S
i tmAdvancePl __-
APPROVED BY:U DATE: L) 7
Purchasing & Risk anagement
cc Purchasing
city plan redevelopment implementation study
EDAW scope of work
June 8, 2005 version
Redevelopment is a major component in realizing the community vision set forth in City Plan. The following scope of
work outlines a process that identifies general issues associated with redevelopment projects, focuses on several key
redevelopment barriers, and prepares a realistic implementation plan in order to make redevelopment a greater part
of Fort Collins' future. Anticipated results will be modifications to codes, policies and standards as needed. Specific
tasks are described below.
Task 1: Project Initiation/City Project Team Organizational Meeting
EDAW will meet with City staff to discuss the objectives of the project and develop a final scope of work, fee, and
schedule. EDAW will also review the charrette scope, public involvement process and a preliminary stakeholders list.
In addition to the formalized City Project Team ("Project Team") meetings and charrette that are detailed as products
in this scope, EDAW will hold project management meetings monthly to review works -in -progress.
Products: Final Scope and Schedule, Preliminary Stakeholders List.
Task 2: Case Study Identification
EDAW will present a brief literature review of the processes and drivers that have stimulated successful
redevelopment projects within other jurisdictions.
The City will provide candidate case studies for Project Team and EDAW review which represent real life, City -
specific examples of redevelopment challenges. Six to eight case studies will be selected for elaboration, including
unsuccessful projects. Of these, two to three will be redevelopment examples nationwide that were completed under
similar circumstances.. A component of the Fort Collins case studies will be a financial analysis of selected projects
to understand the role that present policies and regulations influence economic feasibility.
Products: Project Team Meeting #1, Literature Review Summary, list of six to eight case studies.
Assumptions: The City will provide all of the background data for the Fort Collins case studies, including photos,
point -of -contacts, schedules, economic pro formas, and an introductory narrative for each project. EDAW will provide
a standard case study format for the existing information and financial specialists capable of analyzing pro formas
and other financial statements supplied by the City.
Task 3: Site Tours
EDAW will assist City staff in conducting a one -day tour of infill and redevelopment projects with a group of selected
stakeholders to assess and document on -site conditions The tour will include development within Fort Collins and
other selected communities within the Front Range. A report will be prepared to summarize the results of the site
tours.
Products: 1 day development tour, Tour Summary Memo.
Task 4: Charrette Preparation including Case Studies
EDAW will analyze the case studies identified in Task 2, and will develop "lessons learned" narratives for each case
study during Tasks 4 and 5. Recommendations from each case study will be presented in Task 6.
In consultation with the Project Team, EDAW will prepare key messages and agendas for the Charette. In
preparation for Task 5, EDAW will notify the media, and will prepare notification materials for the City to distribute.
Products: Project Team Meeting #2, notification flyers or postcards, workshop materials and boards
Task 5: Charrette
EDAW will assist staff in holding a 4-day charrette attended by a variety of stakeholders, including developers,
planners, engineers, commercial and residential property owners, public agencies, City staff, and other interested
groups. The purpose of the charrette is to discuss the barriers to redevelopment in the City and possible solutions.
The first two days of the charrette will involve discussions with eight stakeholder groups, each assigned to an area of
expertise, whose task will be to identify barriers and opportunities for successful redevelopment. The following two
days of the charrette will focus on hands-on design exercises that will address the opportunities and constraints to
redevelopment and creation of draft strategies to address substantive design issues and improve the review process.
Three public information meetings with be provided during the course of the charrette. The first meeting will
summarize stakeholder comments and provide a project introduction. The second public meeting will review
preliminary findings of the charrette team and provide opportunity for public review and comment. More refined
information will be provided to the public approximately one week after the second meeting during a final charrette
summary meeting.
EDAW will work with City to develop key messages that will assist in educating citizens on the benefits of
redevelopment. These messages will be incorporated by the City into a powerpoint presentation or brochure. The
City may also prepare an educational website that highlights the benefits of redevelopment in Fort Collins, recent
successful City projects, the project findings to date including national case studies, and other resources.
Products: Charrette and Public Meeting facilitation, key messages for educational materials, Case Study Lessons
Learned Memo, Charrette (incl. Public Meeting) Summary Memo.
Task 6: Strategy Prioritization
Based on the site tours, case studies and charrette, EDAW and the staff team will prioritize several strategies for
which detailed recommendations will be prepared. It is anticipated that the recommendations will be used to adjust
City policies, processes or standards. Potential strategies could include:
Recommendations on City code changes (standards, requirements etc.)
Recommendations on changes in fees or incentives
Overlay zoning suggestions
Policies, standards, fees
Organizational changes
Infrastructure requirement changes
Process modifications
Land use compatibility standards
Products: Project Team Meeting #3, Preliminary Strategies Memo
Task 7: Strategy Review
City Code Committee and Stakeholder Meeting
Under this task, the Project Team will review the draft strategy with emphasis on recommendations requiring inter-
departmental and agency coordination. The Project Team meeting will focus on preliminary recommendations to
overcome specific barriers. This could include such modifications as changes to the land use code or modifications
to land use compatibility standards.
Following the Project Team meeting, EDAW will meet with stakeholders from the development community that were
involved in the charrette and the City Code Committee to suggest general recommendations regarding land use code
changes. The purpose of this meeting is to receive feedback from the private sector regarding any proposed
changes, and to allow the Code Committee to begin drafting the necessary code changes. A City land use specialist
will assist the Code Committee with legal implications and language for key changes.
Products: Project Team meeting #4, meeting with key stakeholders and City Code Committee, and Key Strategy
Recommendations Memo.
Task 8: Draft Charette / Strategy Report
A draft report will be prepared outlining the process, literature review, relationship to other plans, workshop summary,
key issues, Fort Collins case studies, and strategy recommendations to overcome key barriers to redevelopment.
Decisions of the Code Committee will be integrated into the report.
The Project Team will provide comments on the draft report, and staff will provide one set of consolidated comments
to EDAW. EDAW will also participate in two study sessions with the Planning and Zoning Board, City Council, or
other groups.
Products: Project Team Meeting #5, Study Sessions, Draft Report (1 color hardcopy, digital copy)
Task 9: Final Charette / Strategy Report and Action Table
Following the study sessions, EDAW will prepare a final report and action template based on comments from the
Project Team. City staff will assist in providing action items
Products: Final Report (1 color hardcopy, digital copy)