HomeMy WebLinkAboutCHANGE ORDER - BID - 5893 DRAKE ZIEGLER IMPROVEMENT.. Change Order Form Engineering Department PROJECT TITLE: Drake & Ziegler Phase I Improvements PROJECT NUMBER: 30523280.6 (Bid #5893) CONTRACTOR: Don Kehn Construction, Inc. (PO #5501441) CHANGE ORDER NUMBER: 2 n preparing change orders show in order as separate numbered paragraphs the following: 1: Reason for change. 2. Description of change. 3. Change in contract cost. 4. Change in contract time. 1 &2. See attached sheet for detail. 3. The contract cost will increase by $72.370.99 4. The contract time will be increased by 5 days. ORIGINAL CONTRACT COST $1,207,441.00 TOTAL APPROVED CHANGE ORDERS $10,743.19 TOTAL PENDING CHANGE ORDERS $0.00 TOTAL THIS CHANGE ORDER $72,370.99 TOTAL % OF THIS CHANGE ORDER 5.99% TOTAL C.O. % OF ORIGINAL CONTRACT 6.88% ADJUSTED CONTRACT COST $1,290,555.18 (Assuming all change orders approved) ACCEPTED BY: —' DATE: 6 - 11- O S ACCEPTED REVIEWED I TE: G��S (Engineer) or APPROVED BY: DATE: 7 ( part ent Head) APPROVED BY: DATE: (Pu has g Agent over $ 0,000) cc: Contractor Purchasing Project File Engineering Department • 281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (970) 221-6605 DRAKE AND ZIEGLER PHASE I MOVEMENT PROJECT Don Kehn Construction Additional Flowfill for Deep Utilities - See attached submittal - Item Unit $ / Unit I Total on Kohn Construction Flowfill 1077 CY $ 38.00 1 $ 40,926.On $ 40,926.00 Additional flowfill was used due to larger excavation required to safely install the utilities. Trench boxes and shoring could not be effectively utilized due to the proximity of existing utilities. Posted to Pay Estimate # 3 0 Don Kehn Construction Inc. GENERAL CONTRACTORS CHANGE ORDER PROJECT Drake & Zeigler Phase I Tmprovement DiRfrict City of Fort Collins CHANGE ORDER NO, Issued Date: May19 2005 Muount (t) THE CHANGES AS ENUMERATED BELOW ARE HEREBY AUTHORIZED AND THE CONTRACT WILI. BE ADJUSTED AS INDICATED: Flowfill 1077 c.y. @38.00 $40,926.00 Additional flowfill used due to larger excavation required to safely install the work. Trench boxes and shoring could not be effectively utilized due to the proximity of existing utilities. City of Fort Collins C14iP[lGFGL+S 4iEUWner By: Date: OFFICE USE ONLY: Don Kehn Construction, Inc. Contractorxxxiwmm By: 1 (x Date: - The Contract Sum prior to this Change Order was ........................................... ......... ......................... $ The Contract Sum will be (increased) (decrease([) (unchanged) by this Cltange Order. ...... ............. $ The new Contract Sum including this Change. Order will be . ..................... .................. .................... $ The Contract Tinie will be (increased) (decrcasell) (unchanged) by .................................. .............. PLEASE SIGN AND RETURN ONE. COPY LC15-0210 DRAKE AND ZIEGLER PHASE I IMROVEMENT PROJECT Don Kehn Construction 1 1/2" Washed Rock - See attached submittal - Item Unit / Unit Total on Kenn Construction 1 1/2"Washed Rock134 Tons 14.00 1,876.00 MIAL $ 1,376.00 Additional rock was used due to the over excavation for muck excavation required to install the box culvert. Posted to Pay Estimate # 3 Don Kehn .EEHo..._�1 Construction Inc. GENERAL CONTRACTORS CHANGE ORDER 0 PROJECT Drake & Zeigler Phase I Improvement Project _ City of Fort Collins CHANGE ORDER NO. Issued Date: May 19, 2005 Amount. (t) THE CHANGES AS ENUMERATED BELOW ARE FIEREBY AUTHORIZED AND THE CONTRACT WILL BE ADJUSTED AS INDICATED: 1 1/2" Washed Rock 134 Tons @14.00 $1,876.00 Additional rock used due to the over excavation required to install the box culvert. City of Fort Collins fd XXmXda fdfditXOa�ner By: Date: FOR OFFICE USE ONLY Don Kehn Construction, Inc. Contractor m t5nni m By: Date: The Contract Sum prior to this Change Order c-aas................ ............................. ................................ $ The Contract Sum will be (increased) (decreased) (unchanged) by this Change Order_ . ......... The new Contract Sum including this Change Order will be ..... ................. ................... ................... $ 'I1ie Contract Time will be (increased) (decreased) (unchanged) by .................................................. _ -A* PLEASE SIGN AND RETURN ONE COPY -Arr,�r 1.01sonn DRAKE AND ZIEGLER PHASE 1 IMROVEMENT PROJECT Don Kehn Construction Flyash, Milling, Curb and Gutter Removal and Prep, Cargill Utilities, Rigden Irrigation - See attached submittal - Item Unit $ / Unit Total Don Kohn Construction Additional FI ash 621 SY $ 5.06 $ 3,142.26 Don Kehn Construction Remove Curb, Gutter and S lashblock 327 LF $ 5.75 $ 1,880.25 Don Kohn Construction Mobilization for Milling West End 2 EA $ 600.00 $ 1,260.00 Don Kehn Construction Additional 8" Milling 1840 SY $ 2.30 $ 4,232.00 Don Kohn Construction Removal and Prep for Curb and FI ash 621 SY $ 4.07 $ 2,558.75 Don Kehn Construction Installation of Sewer Service to Cargill 1 LS $ 1,836.00 $ 1,836.00 Don Kehn Construction Installation of Water Service to Cargill 1 LS $ 4;150.00 $ 4,150.00 Don Kehn Construction Flowfill for Car ill Services 120 CY $ 38.00 $ 4,560.00 Don Kehn Construction Addtitional Irrigation for East Side of Rigden 1 LS $ 6,039.73 $ 6,039.73 TOTAL $ 29,568.99 m� .- e e S da s Posted to Pay Estimate # 3 tjft E Don Kehn 1 ---�-. -.1 COnStfUCtlOn Inc. GENERAL CONTRACTORS CHANGE ORDER n PROJECT Drake/Zeigler Road Improvements City of Fort Collins CHANGE ORDER NO. Issued Date: May31, 2005 Amount. (t) _++$29,568.99 THE CHANGES AS ENUMERATED BELOW ARE HEREBY AUTHORIZED AND THE CONTRACT NVILL BE ADJUSTED AS INDICATED: Additional Fly Ash 621 s.y. $ 3,142.26 Additional Removal Curb, Gutter & Splash Block. 327 l.f. 1,880.25 Additional Mobilization for Milling West End. 2 ea. 1,200.00 Additional 8" Milling 1840 s.y. 4,232.00 Additional Removal & Prep for Curb & Fly Ash 621 s.y. 2,528.75 Installation of Sewer Service to Cargill l.s. 1,836.00 Installation of Water Service to Cargill l.s. 4,150.00 Flowfill for Cargill Services 120 c.y. 4,560.00 Additional Irrigation for East Side of Rigden, l.s. 6,039.73 29,568.99 Contractor or OWner Contractor or Owner By: By: — Date: Date: FOR OFFICE USE ONLY The Contract Sum prior to this Change Order was ............................................................................. $_ The Contract Sum will he (increased) (decreased) (unchanged) by this Change Order __.................$ The new Contract Sum including this Change Order will be ... ................... .............. ....... ... .............. $__ The Contract Time will be (increased) (decreased) (unchanged) by ................................................. _ tYii l PLEASI SIGN ^.l`V'D RE'RIRN ONE COPY -'cull 1,0150210 Date Hours for Norm. 31-Mar 1.00 14-Apr 2.00 26-Apr 3.00 27-Apr 4.50 2-May 8.00 3-May 7.00 6-May 4.00 9-May 6.50 20-May 1.00 23-May 2.00 39.00 hr rate $48.00 $1,872.00 Total Labor/Equipment Hours Ryan Hours Ditch Witch/Mini-ex 0.00 2.00 3.00 3.50 4.50 2.00 7.00 7.00 6.00 2.00 3.50 5.00 1.00 2.00 34.00 14.50 $27.00 $45,00 $918.00 $652.50 $3,442.50 Total Parts $1,809.44 Total before 15% $5,251.94 Total project $6,039.73 with 15% added