HomeMy WebLinkAboutRFP - P957 OLD TOWN SQAURE PLAZA RENOVATION (2)1
REQUEST FOR PROPOSAL
CITY OF FORT COLLINS
AND THE FORT COLLINS DOWNTOWN DEVELOPMENT AUTHORITY
for
OLD TOWN SQUARE PLAZA RENOVATION
and
TRIMBLE COURT AND TENNEY COURT ALLEY IMPROVEMENTS
PROPOSAL NO. P957
Request for Proposals
The City of Fort Collins and the Fort Collins Downtown Development Authority are
soliciting proposals from qualified consultants for the design and contract administration
of the renovation of Old Town Square Plaza and for improvements to the Trimble Court
and Tenney Court alleys. The consultant or consulting team will provide all necessary
services to prepare design development plans and construction documentation for
bidding by the City for the renovation of Old Town Square Plaza and for the
redevelopment of the two alleys. Because there is a physical connection between
Trimble Court and the Old Town Square Plaza these projects will be designed together.
Written proposals, five(5) will be received at the City of Fort Collins' Purchasing Division,
215 North Mason St., 2nd floor, Fort Collins, Colorado 80524. Proposals will be received
before 3:00 p. m. (our clock), October 15, 2004. Proposal No. P-957. If delivered, they
are to be sent to 215 North Mason Street, 2nd Floor, Fort Collins, Colorado 80524. If
mailed, the address is P.O. Box 580, Fort Collins, 80522-0580.
Questions concerning the scope of the project should be directed to Kathleen Benedict,
Project Manager at 970-416-2260 or E-mail at kbenedict@fcgov.com , and to Chip
Steiner, Executive Director of the Downtown Development Authority, 970-484-2020, or e-
mail at steinco@frii.com.
.
Questions regarding proposals submittal or process should be directed to John Stephen,
CPPO, CPPB, Senior Buyer, (970) 221-6775 or E-mail jstephen@fcgov.com.
A pre-proposal meeting will be held October 6, 2004 at 10:00 a.m. at 215 N Mason, Main
Floor Community Room.
A copy of the Proposal may be obtained as follows:
1. Download the Bid from the Purchasing Webpage, Current Bids page, at:
www.fcgov.com/purchasing.
2. Come by Purchasing at 215 North Mason St., 2nd floor, Fort Collins, and
request a copy of the Bid.
Sales Prohibited/Conflict of Interest: No officer, employee, or member of City Council,
shall have a financial interest in the sale to the City of any real or personal property,
equipment, material, supplies or services where such officer or employee exercises
directly or indirectly any decision-making authority concerning such sale or any
supervisory authority over the services to be rendered. This rule also applies to
2
subcontracts with the City. Soliciting or accepting any gift, gratuity favor, entertainment,
kickback or any items of monetary value from any person who has or is seeking to do
business with the City of Fort Collins is prohibited.
Collusive or sham proposals: Any proposal deemed to be collusive or a sham proposal
will be rejected and reported to authorities as such. Your authorized signature of this
proposal assures that such proposal is genuine and is not a collusive or sham proposal.
The City of Fort Collins reserves the right to reject any and all proposals and to waive
any irregularities or informalities.
Sincerely,
James B. O'Neill II, CPPO, FNIGP
Director of Purchasing & Risk Management
3
PROJECT DESCRIPTION
I. GENERAL
The City of Fort Collins and the Fort Collins Downtown Development Authority request
proposals for the design and contract administration for the renovation of Old Town
Square Plaza and improvements to the Trimble and Tenney Court allies. The consultant
will provide all necessary services to design the plaza renovation and alley
improvements according to the provisions of this scope of work.
In general terms, this scope consists of preparing design development plans and
construction documentation for bidding by the City for the renovation of the Plaza and
reconstruction of the alleys. The Consultant will assist City staff during the public process
that is a part of the design process. The Consultant will assist City staff with
administration services during construction.
It is the intent of this scope of work to give prospective consultants the needed
information to prepare a proposal for design services. The City’s Project Manager and
the director of the Downtown Development Authority will be available to answer
questions during the proposal process.
II. PROJECT DESCRIPTION
The City of Fort Collins and DDA anticipate renovating the Plaza and reconstructing the
alleys beginning as early as possible after January 1, 2005. Funding through the DDA is
available. Location of the Plaza and alleys to be reconstructed is illustrated on Exhibit
A.
The Old Town Square plaza is twenty years old. Almost constant use by the general
public and by numerous special events necessitate a thorough renovation. The two
alleys are the first in a larger program to turn the downtown alley system into an
integrated pedestrian network. Concept designs developed in the spring of 2004 are
attached as Exhibit B.
III. PROJECT FUNDING AND ESTIMATED BUDGET
Funding for these projects will be provided primarily through DDA resources:
Plaza renovation: $1,000,000 for design and renovation.
Alley redevelopment: $900,000 for renovation.
Funds can be shifted between the two projects depending on cost.
Funding will need to support Staff salary, Consultant design and administration,
construction and contingency.
4
IV. SCOPE OF WORK
The Consultant shall perform or coordinate the following activities as part of the
contractual obligation for this project.
A. DESIGN DEVELOPMENT
1. Prepare base drawings from field surveys showing existing control elevations,
property corners, vegetation, utilities, and any other pertinent information.
2. Prepare a preliminary plan reflecting all available information and design constraints.
The plan shall present alternative design solutions and will serve as a review document
for the City.
3. Present the preliminary plan to the City’s Conceptual Review Team which will include
DDA representation and to the Downtown Development Authority Board of Directors.
Follow-up on various departmental comments and address all concerns in the final plan.
4. Coordinate with any agencies outside of the city, as necessary. The consultant shall
be responsible for informing, gathering information from and responding to all groups
and agencies associated with the project.
5. Attend and assist with public meetings. The consultant will also be required to
participate in City board meetings.
7. Attend review meetings with appropriate city staff including Parks and Recreation and
utility departments with regard to the Plaza and alleys. In addition, attend any necessary
individual meetings with the other City departments.
8. Prepare preliminary construction cost estimates as the project moves through the
master plan and final design process. City staff will continually review the proposed
budget with particular attention at the 50% and 90% design levels.
9. Consultant shall meet or be in contact with the project manager and DDA executive
director on a regular basis throughout the design phase.
10. Upon conclusion of the design development phase, the Consultant will prepare
construction documentation, final cost estimates, and specifications for the project
reflecting all the input obtained from the planning process. Any options or questions
explored during the preliminary phase will be resolved between the City and the
Consultant before proceeding to final design. Cost estimate will be used in budgeting for
park construction.
11. Submit ten sets of construction documentation to the City for approval.
12. All drawing shall be generated on AutoCadd and provided electronically to the City.
AutoCadd shall be on the latest release, AutoCadd 2004. One set of final original Cadd
generated drawings on mylar shall be provided to the City.
5
13. Prepare a rendered Master Plan of the final Old Town Square Plaza design. The
Master Plan shall be mounted and framed for hanging and shall become the property of
the City.
B. DETAILED PROJECT DESCRIPTION
This section is expected to give the Consultant the needed information to prepare a
proposal for services. The extensive description and task list are intended only to guide
the proposal process. Additional refinement of tasks is expected, with explanation, to
suit the individual firm’s needs to competently prepare a proposal. The City’s Project
Manager and DDA executive director will be available to answer questions.
Old Town Square Plaza
1. Physical condition and redesign of plaza elements including:
A. Pavers and paver bed
1) Determine condition of existing pavers and whether they need to
be replaced. Cost restoration (cleaned to near original and
sealed against further damage) and replacement.
2) Determine areas where the paver bed has failed and provide
remedy and cost for remedy.
B. Fountain.
1. Inspect fountain stone and all mechanical and plumbing systems.
2. Recommend necessary repairs
C. Concrete, stone, and play area flat surfaces.
1. Inspect all concrete curbing, banding, flagstone, and soft-surface play
area for structural and aesthetic failure. Design solutions. Cost the
solutions.
2. Some concrete has strip lighting embedded. Assess feasibility and
practicality of replacing. Design and cost replacement.
D. Plaza Furniture including trash containers, freestanding planters, banners,
metal and wood benches, railings, etc.
1) As part of overall design process recommend and cost
repair/replacements for all.
2) Recommendations should address ways to mitigate damage
from dogs urinating (and staining) on fixtures, skateboards, etc.
E. Lighting, kiosks, signage.
1) Review all plaza lighting (including ground lighting) and
recommend renovation or replacement and cost the preferred
recommendation.
2) Detail renovation and/or redesign of information kiosks and all
signage in the plaza. Cost out the recommendation.
F. Landscaping.
1) Evaluate existing perennial plant materials for replacement
(some trees are dying). Recommend replacements.
2) Redesign entire landscaping theme in the plaza to provide year-
round interest, texture, color, variety. Cost the redesign.
2. Speaker’s Rotunda. Design and site a small “soapbox” rotunda in the plaza. This
is intended to invite/encourage extemporaneous speaking as well as scheduled
lectures.
6
2. Maintenance Program. Write a comprehensive maintenance program for the
entire plaza to ensure that it remains in good condition. This program should
address cycles for repair (e.g. restaining would benches), methods to keep
pavers and flat surfaces clean and in good repair, care of all landscaping, etc.
The Program is meant to be a manual to be used by plaza caretakers for the next
twenty years.
Alleys.
1. Review the concept designs developed by EDAW and included with this RFP.
2. Initiate meetings with affected property owners and businesses to discuss
trash consolidation and proposed designs that will require façade and/or other
easements.
3. Initiate meetings with trash haulers to establish a bidding process for
consolidated services and to discuss equipment and design issues to help
consolidate collection service into one or two locations.
4. Based upon the above, develop final design and construction drawings for the
redevelopment of the two alleys.
CONSTRUCTION
The City anticipates one construction document for bidding and construction. Bid items
shall be a combination of lump sum and individual items.
MEETINGS AND PUBLIC PROCESS
Coordination and review by city and DDA staff will be required throughout the project.
As design progresses, review by other City Departments will be necessary. The
Consultant will be expected to participate in these reviews.
Meetings - It is anticipated that the following meetings will be required, at a
minimum, for this project:
Initial Coordination Meeting: At this meeting the Consultant will be expected to provide a
detailed schedule of the design process, including the work of any sub-consultants,
identifying important milestones in the process and target dates for these milestones.
Progress Meetings: Progress meetings will be held every two weeks during the course of
the project. Meetings may be more frequent at times, if need be.
Utility Coordination: At least four meetings are anticipated to coordinate with affected
utility companies. Prior to meeting with utilities, the City will assist the Consultant in
collecting comments from utilities through the existing utility coordination process.
Public meetings: The City anticipates there will be four public meetings. These will be in
the form of neighborhood meetings using affected property owner and business owner
lists generated by the City and DDA. The City and DDA will be responsible for leading
the public involvement program with the support of the Consultant. The Consultant will
be responsible for development of renderings for the public meetings.
7
The Consultant will be expected to attend 6 city board meetings for review of the project.
Attend one Conceptual Review and one Administrative Review meeting. These projects
are subject to the City’s development process at the Administrative Level.
DESIGN STANDARDS
The City’s current standards for development review, engineering, stormwater, utility
work, and building permits will apply to this project.
FINAL DESIGN AND CONSTRUCTION DOCUMENTS
The Consultant shall prepare detailed construction drawings of the proposed
improvements on 24” x 36”, 3-mil double mat inked Mylar. The final scale of the
drawings will be determined based upon the complexity of the design, but shall not be
smaller than 1” = 50’. Five sets of construction drawings shall be signed and sealed by a
professional engineer licensed in the State of Colorado. The original set of inked Mylar
shall be the property of the City. Drawings shall be also given to the City on Autocad
files on cds. At a minimum, the Construction Drawings shall contain:
1. The date of preparation, scale, north arrow, and legend
2. Project title
3. Title sheet with index
4. Plan and profile sheet(s) including all subsurface drainage and utilities
5. Property ownership, construction easements, and permanent easements(if
required)
6. Existing conditions, including location of all utilities
7. Cross sectional view(s) and construction details of improvements.
8. Landscape Plan
9. Improvements, site plans, grading plans, architectural plans and detail sheets
as needed
The City will prepare the final contract Documents (drawings and specifications)
for bidding of the project through the City of Fort Collins’ Purchasing
Department. Review of the documents by the appropriate City Departments will
be required prior to bidding.
The Consultant shall prepare a Final Design Report (four (4) copies), which will
summarize any major changes from the Preliminary Design decisions.
CONSTRUCTION ADMINISTRATION SERVICES
The Consultant will provide assistance during the pre-bid period and aid prospective
bidders in fully understanding the scope of the project and explaining any unusual or
significant features. The Consultant will assist the City in conducting a pre-bid
conference and job-walk with contractors and suppliers. Respond to inquires as directed
by the City. The Consultant will assist the City in the preparation of addendums, review
of proposals and qualifications of contractors and suppliers.
8
The Consultant will provide construction administration assistance as requested by the
City.
For this proposal process the Consultant is to estimate construction administration
services based on the following:
Pre bid process: Consultant Team-
Contact Administration assistance and inspection: Consultant Team-
The Consultant will provide a set of Mylars and a CD to the contractor for preparation of
the “as-built” record drawing set for the completed project.
V. CONSTRUCTION PLANS—City approval, Quality of Work
The Consultant shall be responsible for the professionalism and technical accuracy and
coordination of all services such as designs, drawings, specifications, costs estimates,
and other work or materials furnished to the City by the Consultant under this contract.
The project submitted by the Consultant shall represent the best architectural and
engineering solutions possible for the scope of work in the contract. All work must be in
accordance with the current criteria, guides, and specifications listed in the scope and
shall be in accordance with the best engineering practices. Workmanship shall be neat
with all lines and lettering of uniform weight and clarity for complete legibility and
satisfactory reproduction. Any computer disks submitted must be scanned for viruses
using a commercial virus scanning program. All elements of submittals shall be checked
by the Consultant and such check shall be made by persons other than those preparing
the material and by professional personnel trained in that specific discipline. Error and
deficiencies shall be corrected by the Consultant at no additional charge to the City.
VI. FEES
A. The engineering services will be awarded based on a Not-to-Exceed Time and
Reimbursable Direct Cost Basis Agreement. The Consultant will provide as part of
their proposal a rough order-of magnitude estimate of design fees, based upon the
services described in this proposal. Upon the selection of the Consultant, the final
fee will be negotiated with input form the Consultant based upon how they foresee
the overall project.
VII. SCHEDULE
Advertising September 23, 2004
Award October 22, 2004
Design October to December 2004
Bidding January 2005
Construction February, 2005 – May, 2005
VII. Evaluation and Assessment of Proposal
9
An evaluation committee shall rank the interested firms based on their written
proposals using the ranking system set forth below. Firms shall be evaluated on the
following criteria.
The ranking scale shall be from 1 to 5, with 1 being a poor rating and 5 an
outstanding rating. Recommended weighting factors for the criteria are listed
adjacent to the qualification.
Weighting Factor Qualification Standard
2.0 Scope of Proposal
Does the proposal show an
understanding of the project objective,
methodology to be used, and results
that are desired from the project?
2.0 Assigned Personnel
Do the persons who will be working on
the project have the necessary skills?
Are sufficient people of the requisite
skills assigned to the project?
1.0 Availability
Can the work be completed in the
necessary time? Can the target start
and completion dates be met? Are
other qualified personnel available to
assist in meeting the project schedule if
required? Is the project team available
to attend meetings as required by the
Scope of Work?
1.0 Motivation
Is the firm interested and are they
capable of doing the work in the
required time frame?
2.0 Cost and Work Hours
Do the proposed cost and work hours
compare favorably with the project
Manager's estimate? Are the work
hours presented reasonable for the
effort required in each project task or
phase?
2.0 Firm Capability
Does the firm have the support
capabilities the assigned personnel
require? Has the firm done previous
projects of this type and scope?
VIII Reference Evaluation (Top-ranked firms)
10
The Project Manager will check references using the following criteria. The
evaluation rankings will be labeled Satisfactory / Unsatisfactory.
QUALIFICATION STANDARD
Overall Performance Would you hire this Professional again? Did
they show the skills required by this project?
Timetable Was the original Scope of Work completed
within the specified time? Were interim
deadlines met in a timely manner?
Completeness Was the Professional responsive to client
needs; did the Professional anticipate
problems? Were problems solved quickly
and effectively?
Budget Was the original Scope of Work completed
within the project budget?
Job Knowledge a) If a study, did it meet the Scope of
work?
b) If Professional administered a
construction contract, was the
project functional upon completion
and did it operate properly? Were
problems corrected quickly and
effectively.
11
4.1 Qualification and Standard
QUALIFICATION STANDARD
Overall Performance Would you hire this Professional again? Did
they show the skills required by this project?
Timetable Was the original Scope of Work completed
within the specified time? Were interim
deadlines met in a timely manner?
Completeness Was the Professional responsive to client
needs; did the Professional anticipate
problems? Were problems solved quickly
and effectively?
Budget Was the original Scope of Work completed
within the project budget?
Job Knowledge a) If a study, did it meet the Scope of
work?
b) If Professional administered a
construction contract, was the
project functional upon completion
and did it operate properly? Were
problems corrected quickly and
effectively.
12
PROFESSIONAL SERVICES AGREEMENT
THIS AGREEMENT made and entered into the day and year set forth below, by
and between THE CITY OF FORT COLLINS, COLORADO, a Municipal Corporation,
hereinafter referred to as the "City" and _____, [insert either a corporation, a partnership
or an individual, doing business as____________], hereinafter referred to as
"Professional".
WITNESSETH:
In consideration of the mutual covenants and obligations herein expressed, it is
agreed by and between the parties hereto as follows:
1. Scope of Services. The Professional agrees to provide services in
accordance with the scope of services attached hereto as Exhibit "A", consisting of
_____ (_____) page[s], and incorporated herein by this reference.
2. The Work Schedule. [Optional] The services to be performed pursuant to
this Agreement shall be performed in accordance with the Work Schedule attached
hereto as Exhibit "B", consisting of _____ (_____) page[s], and incorporated herein by
this reference.
3. Time of Commencement and Completion of Services. The services to be
performed pursuant to this Agreement shall be initiated within _____ (_____) days
following execution of this Agreement. Services shall be completed no later than _____.
Time is of the essence. Any extensions of the time limit set forth above must be agreed
upon in writing by the parties hereto.
4. Early Termination by City. Notwithstanding the time periods contained
herein, the City may terminate this Agreement at any time without cause by providing
written notice of termination to the Professional. Such notice shall be delivered at least
13
fifteen (15) days prior to the termination date contained in said notice unless otherwise
agreed in writing by the parties.
All notices provided under this Agreement shall be effective when mailed, postage
prepaid and sent to the following addresses:
Professional: City: With Copy to:
In the event of any such early termination by the City, the Professional shall be paid for
services rendered prior to the date of termination, subject only to the satisfactory
performance of the Professional's obligations under this Agreement. Such payment shall
be the Professional's sole right and remedy for such termination.
5. Design, Project Indemnity and Insurance Responsibility. The
Professional shall be responsible for the professional quality, technical accuracy, timely
completion and the coordination of all services rendered by the Professional, including
but not limited to designs, plans, reports, specifications, and drawings and shall, without
additional compensation, promptly remedy and correct any errors, omissions, or other
deficiencies. The Professional shall indemnify, save and hold harmless the City, its
officers and employees in accordance with Colorado law, from all damages whatsoever
claimed by third parties against the City; and for the City's costs and reasonable
attorneys fees, arising directly or indirectly out of the Professional's negligent
performance of any of the services furnished under this Agreement. The Professional
shall maintain commercial general liability insurance in the amount of $500,000
combined single limits, and errors and omissions insurance in the amount of
___________.
14
6. Compensation. [Use this paragraph or Option 1 below.] In consideration
of the services to be performed pursuant to this Agreement, the City agrees to pay
Professional a fixed fee in the amount of _____ ($_____) plus reimbursable direct costs.
All such fees and costs shall not exceed _____ ($_____). Monthly partial payments
based upon the Professional's billings and itemized statements are permissible. The
amounts of all such partial payments shall be based upon the Professional's City-verified
progress in completing the services to be performed pursuant hereto and upon the City's
approval of the Professional's actual reimbursable expenses. Final payment shall be
made following acceptance of the work by the City. Upon final payment, all designs,
plans, reports, specifications, drawings, and other services rendered by the Professional
shall become the sole property of the City.
6. Compensation. [Option 1] In consideration of the services to be
performed pursuant to this Agreement, the City agrees to pay Professional on a time and
reimbursable direct cost basis according to the following schedule:
Hourly billing rates: _____
Reimbursable direct costs: _____
with maximum compensation (for both Professional's time and reimbursable direct costs)
not to exceed _____ ($_____). Monthly partial payments based upon the Professional's
billings and itemized statements of reimbursable direct costs are permissible. The
amounts of all such partial payments shall be based upon the Professional's City-verified
progress in completing the services to be performed pursuant hereto and upon the City's
approval of the Professional's reimbursable direct costs. Final payment shall be made
following acceptance of the work by the City. Upon final payment, all designs, plans,
reports, specifications, drawings and other services rendered by the Professional shall
become the sole property of the City.
15
7. City Representative. The City will designate, prior to commencement of
work, its project representative who shall make, within the scope of his or her authority,
all necessary and proper decisions with reference to the project. All requests for
contract interpretations, change orders, and other clarification or instruction shall be
directed to the City Representative.
8. Project Drawings. [Optional] Upon conclusion of the project and before
final payment, the Professional shall provide the City with reproducible drawings of the
project containing accurate information on the project as constructed. Drawings shall be
of archival quality, prepared on stable mylar base material using a non-fading process to
prove for long storage and high quality reproduction.
9. Monthly Report. Commencing thirty (30) days after the date of execution
of this Agreement and every thirty (30) days thereafter, Professional is required to
provide the City Representative with a written report of the status of the work with
respect to the Scope of Services, Work Schedule, and other material information.
Failure to provide any required monthly report may, at the option of the City, suspend the
processing of any partial payment request.
10. Independent Contractor. The services to be performed by Professional
are those of an independent contractor and not of an employee of the City of Fort
Collins. The City shall not be responsible for withholding any portion of Professional's
compensation hereunder for the payment of FICA, Workers' Compensation, other taxes
or benefits or for any other purpose.
11. Personal Services. It is understood that the City enters into this
Agreement based on the special abilities of the Professional and that this Agreement
shall be considered as an agreement for personal services. Accordingly, the
Professional shall neither assign any responsibilities nor delegate any duties arising
under this Agreement without the prior written consent of the City.
16
12. Acceptance Not Waiver. The City's approval of drawings, designs, plans,
specifications, reports, and incidental work or materials furnished hereunder shall not in
any way relieve the Professional of responsibility for the quality or technical accuracy of
the work. The City's approval or acceptance of, or payment for, any of the services shall
not be construed to operate as a waiver of any rights or benefits provided to the City
under this Agreement.
13. Default. Each and every term and condition hereof shall be deemed to be
a material element of this Agreement. In the event either party should fail or refuse to
perform according to the terms of this agreement, such party may be declared in default.
14. Remedies. In the event a party has been declared in default, such
defaulting party shall be allowed a period of ten (10) days within which to cure said
default. In the event the default remains uncorrected, the party declaring default may
elect to (a) terminate the Agreement and seek damages; (b) treat the Agreement as
continuing and require specific performance; or (c) avail himself of any other remedy at
law or equity. If the non-defaulting party commences legal or equitable actions against
the defaulting party, the defaulting party shall be liable to the non-defaulting party for the
non-defaulting party's reasonable attorney fees and costs incurred because of the
default.
15. Binding Effect. This writing, together with the exhibits hereto, constitutes
the entire agreement between the parties and shall be binding upon said parties, their
officers, employees, agents and assigns and shall inure to the benefit of the respective
survivors, heirs, personal representatives, successors and assigns of said parties.
16. Law/Severability. The laws of the State of Colorado shall govern the
construction, interpretation, execution and enforcement of this Agreement. In the event
any provision of this Agreement shall be held invalid or unenforceable by any court of
17
competent jurisdiction, such holding shall not invalidate or render unenforceable any
other provision of this Agreement.
17. Special Provisions. [Optional] Special provisions or conditions relating to
the services to be performed pursuant to this Agreement are set forth in Exhibit "_",
consisting of _____ (_____) page[s], attached hereto and incorporated herein by this
reference.
THE CITY OF FORT COLLINS, COLORADO
By: _________________________________
James B. O'Neill II, CPPO, FNIGP
Director of Purchasing & Risk Management
DATE: ______________________________
ATTEST:
_________________________________
City Clerk
APPROVED AS TO FORM:
_________________________________
Assistant City Attorney
[Insert Professional's name] or
[Insert Partnership Name] or
[Insert individual's name]
Doing business as ____[insert name of business]
By: __________________________________
Title: _______________________________
CORPORATE PRESIDENT OR VICE PRESIDENT
Date: _______________________________
ATTEST:
_________________________________ (Corporate Seal)
Corporate Secretary