NAME OF PROJECT Asphalt Overlay Project
SECTION 00020
SUMMARY OF WORK
This work shall consist of asphalt milling, asphalt patching, asphalt overlays, geotextile paving fabric, manhole and
valve box adjustments, and the associated traffic control on designated streets in the City of Fort Collins. Specific
locations are described in Section 3500, Project Map.
DATE CONTRACTS WILL BE AVAILABLE
Feb 25, 2004
REFUNDABLE FEE
$50.00
PREBID CONFERENCE AND JOB WALK
March 8 10:00 am @215 Mason – room tbd
Bid Opening, March 17, 3:00
SECTION 00300
BID SCHEDULE
Bid schedule under separate attachment
SECTION 00430
SCHEDULE OF SUBCONTRACTORS
Subcontractors performing over 15% of contract.
SECTION 00520
ARCHITECT OR CONSULTANT
NA
CONTRACT TIMES
Substantially complete within 45 working days
Final completion within 5 days of substantial completion
LIQUIDATED DAMAGES
Substantial completion: $1000.00
Final Acceptance: $500.00
DRAWINGS
NA
SECTION 00800
SUBSURFACE AND PHYSICAL CONDITIONS:
none
LIMITS OF LIABILITY
Or none lost due to weather.