HomeMy WebLinkAboutCHANGE ORDER - RFP - ART IN PUBLIC PLACES GARDENS ON SPRING CREEKCHANGE ORDER NO.
PROJECT TITLE: APP Gardens on Spring Creek Project
CONTRACTOR: Barry Rose
PROJECT NUMBER:
PURCHASE ORDER NO.: 330779
DESCRIPTION: "Passing the Baton"
1. Reason for change: Additional costs incurred by the artist due to the city's resizing of the
site/pedestal.
2. Description of Change: Artist had to increase the size/scale of the artwork which added
additional costs to the project.
3. Change in Contract Cost: $624
4. Change in Contract Time: none
ORIGINAL CONTRACT COST
$20,979
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
$624
TOTAL THIS CHANGE ORDER
$624
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.:
%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S:
%
ADJUSTED CONTRACT COST
$2,1603
(Assuming all change orders approved)
ACCEPTED BY:
DATE:
_
Contractor's Representative/Artist
ACCEPTED BY:
DATE:
_
Project Manager
REVIEWED BY:
DATE:
Title:
APPROVED BY:
DATE:
Title:
APPROVED BY:
DATE:
Purchasing Agent over $15,000
cc: Purchasing