Loading...
HomeMy WebLinkAboutCHANGE ORDER - REQUISITION - 22444Change Order Form Engineering Department PROJECT TITLE: 2004 Street Maintenance Program PROJECT NUMBER: 320200 (Slurry Seal Project - Bid #5698) CONTRACTOR: Intermountain Slurry Seal (PO #4404275) CHANGE ORDER NUMBER: 4 n preparing change orders s ow in order as separate numbered paragraphs the o owing: 1: Reason for change. 2. Description of change. 3. Change in contract cost. 4. Change in contract time. 1 &2. See attached sheet for detail. 3. The contract cost will decrease by $ (520.00) 4. There will be no change in contract time. ORIGINAL CONTRACT COST $298,136.50 TOTAL APPROVED CHANGE ORDERS $9,484.35 TOTAL PENDING CHANGE ORDERS $0.00 TOTAL THIS CHANGE ORDER ($520.00) TOTAL % OF THIS CHANGE ORDER -0.17% TOTAL C.O. % OF ORIGINAL CONTRACT 3.01% ADJUSTED CONTRACT COST $307,100.85 (Assuming all change orders approved) ACCEPTED BY: APPROVED BY: APPROVED BY: APPROVED BY: APPROVED BY: Project File Head (Purchasing Agent over $30,000) ($400.00) Parking ($120.00) Engineering DATE: a QS- )ATE: l IAI- os-- DATE: ! —/Z 'd DATE: I - 13 -G v DATE: Engineering Department • 281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (970) 221-6605 Change Order Number: 4 Date: 1. Reason For Change: a. Contract quantities do not match actual quantities due to reduced area covered by ice & snow. 2. Desc-sption Of Change: a. Reconcile contract quantities to match actual quantities. 3. Change In Contract Amount: a. Contract Deduction $ (520.00) 4. Change In Contract Time a. There is no change in contract time. H:\p.m.p\PROJECTS\2004\Slurry\2004 Pay Estimate 1 /3/2005 FINAL CHANGE OR. City of Fort Collins 2004 Asphalt Slurry Seal Project Intermountain Slurry Seal Bid No. 5698 - Renewal Item No. Description Unit Contract Quantity it Cast=C11tract UnQuantity Actual +/- Quantity Cost 105.10 Sweeping - All Streets (Day 5 Only) LS 3.0 $ - I r.00 $ 12,000.00 2.97 (0.03) $ (120.00) 105.20 Sweeping - Puking Lots (Day 5 Only) LS 2.0 $ 40ii. Y $ 800.00 1.00 (1.00) S (400.00) Type II Asphalt Slurry Seal - All Street SY 260271.5 $ 1.10 S 286,298.68 260271.53 0.00 $ - 409.01 Locations 409.02 Type It Asphalt Slurry Seal - Parking Lots SY 1760.8 $ 1.15 $ 2,024.92 1760.80 0.00 $ - 6I4.01 "No Parking" Sign With Stand Per Day Per 700.0 $ 0.25 $ 175.00 700.00 0.00 S - Each 614.O1a "No Parking" Sign With Stand (Rented) Per Day Per 625.0 $ 1.15 $ 718.75 625.00 0.00 $ - Each 614.02 Vertical Panel Without Light Per Day Per 0.0 $ 0.25 S=-O0.00 $ - Each 614.03 Type I Barricade Without Light Per Day Per 0.0 $ 0.25 $ - 0.00 0.00 $ - Each 614.04 Type II Barricade Without Light Per Day Per Each 0.0 $ 0.50 S - 0.00 0.00 $ - 614.05 Type III Barricade Without Light Per Day Per 157.0 $ 2.50 $ 392.50 157.00 0.00 S - Each 614.06 Size A Sign With Stand Per Day Per 266.0 $ 2.00 $ 532.00 266.00 0.00 $ - Each 614.07 Size B Sign With Stand Per Day Per 161.0 $ 2.00 S 322.00 161.00 0.00 $ - Each 614.08 Size A Specialty Sign - Cost of Manufacturing Each 0.0 S 50.00 $ - 0.00 0.00 $ - 614.09 Size B Specialty Sign - Cost of Manufacturing Each 0.0 $ 50.00 $ - 0.00 0.00 $ - 614.10 Cane With Reflective Strip Per Day Per 1587.0 S 1.00 $ 1,587.00 1587.00 0.00 $ - Each 614.11 Safety Fence Per Day Per Roll 0.0 $ 10.00 $ - 0.00 0.00 S 614.12 Light - Steady Bum Per Day Per Each 0.0 $ 0.10 $ - 0.00 0.00 S - 614.13 Light- Flashing Per Day Per Each 0.0 $ 0.10 S - 0.00 0.00 $ - Advance Warning Flashing - or Sequencing Per Day Per 0.0 S 15.00 $ - 0.00 0.00 $ - 611414 Arrow Panel Each 614.15 Traffic Control Supervisor/Daily Per Day 7.0 $ 100.00 $ 700.00 7.00 0.00 $ - 614.16 Traffic Control Supervisor/Hourly Per Hour 45.0 $ 15.00 S 675.00 45.00 0.00 $ - 614.17 Flagging Per Hour 139.5 $ 10.00 $ 1,395.00 139.50 0.00 $ - $ (520.00) TOTAL COST Parking $ (400.00) Engineering $-(120.00) $ (520.00) H:\p.m.p\PROJECTS\2004\Slurry\2004 Pay Estimate Page 1 of 1 1 /312005